Major Events, Projects and Planned Roadworks
Planning ahead
As part of our service, work is undertaken to maintain and develop the trunk road network. Traffic Scotland works with major events organisers and partners to assess the impact of major events on road traffic. To help with your travels, or to find out more view future traffic updates below, or by using our interactive map on the homepage.
Upcoming Events and Future Roadworks
Roads maintained by local authorities
£20 million for electric vehicle loans in 2025-26
Draft Orders published for Pass of Birnam to Tay Crossing section of A9 Dualling programme
A82 North of Arden | Drainage Investigation Works
Summer Events in Scotland
M74 Nethan Viaduct | Bridge Refurbishment
A96 Union Bridge in Keith | Repair Works
A78 Inverkip | Signalised Junction Installation
M8 Junctions 5 & 4a | Major Works Spring Programme
M8 & M80 | Gantry Refurbishments
A9 Tomatin to Moy | Information for abnormal loads using the A9 between from April 2025
A90 Inchture | Drainage Improvements
Bridge Carrying A84 Over M9 | Deck Repairs
A9 Findhorn Bridge | Maintenance Work
A90 Forfar and Bogindollo | Road Safety Upgrade
M90 Glenhead Bridge | Bridge Upgrade
A82 Loch Oich | Rock Slope Works
A95 Ballindalloch | Refurbishment
A82 Invergloy | Overnight Resurfacing Work
A9 Dalwhinnie and Calvine | Carriageway Improvements
M8 Junction 18 Eastbound | Traffic Signal Upgrades
A96 Inveramsay Bridge in Inverurie | Drainage Improvements
M8 Bathgate and Blackburn | Major Works
A1 | Overnight Maintenance
A85 Connel And Taynuilt | Resurfacing
A9 Strathsteven Bridge | Essential Maintenance
M8 Junctions 1 - 6a | Overnight Maintenance
A82 Luss to Culag | Drainage Works
A77 Cairnryan | Essential Drainage Improvements
A830 East of Ranochan | Update on rock slope works
A9 North Of Helmsdale | Overnight Resurfacing Works
A95 North of Drumuillie | Overnight Surfacing Improvements
A90 Laurencekirk | Overnight Resurfacing
A828 North of Barcaldine | Barrier Intallation
A835 West of Tarvie | Resurfacing Work
A68 Earlston to Millerhill | Road Marking Improvements
M90 Junction 2 and 3 | Resurfacing and Bridge Works
A9 Broxden Roundabout approach | Resurfacing
M9 Northbound Junctions 3 - 4 | Resurfacing Work
A90 Fordoun | Surfacing Improvements
A720 slip to A71 | Bridge Works
A96 Inverness Airport | Drainage Improvements
A725 Whistleberry Retail Park | Essential Resurfacing
M8 Junction 6-8 | Inspection Works
A68 North of Pathhead | Drainage Construction
M8 Woodside | Essential Maintenance
M9 Junction 1B | Resurfacing
M8 Woodside (A81 and A804) | Essential Maintenance
A9 North of Dunbeath | Overnight Surfacing
A835 Garve | Overnight Resurfacing
Eden Festival 2025 | Moffat
Kelpies Live 2025 UB40 | Helix Park
Network Rail Langbank Road Closure 13th-14th June | Railway Bridge Survey
Isle of Skye Half 10K and Marathon
Kelpies Live 2025 Jess Glynne | Helix Park
Hot Hatch Day | Knockhill
A84 Strathyre and Doune | Carriageway Improvements
M90 And A9 Broxden Roundabout | Resurfacing
M9 Junction 9-8 Southbound | Safety Barrier Installations
A9 North Kessock | Active Travel Improvements
A75 Inch Church | Resurfacing
A9 Cairnie Bares | Drainage Improvements
A82 Achintore Road | Overnight Drainage Improvements
A1 Eyemouth | Resurfacing and Bridge Works
M74 Junction 5-6 | Lining Works
Stock Car Summer Series | Knockhill
A90 Kingsway | Footbridge Removal Works
A95 Boat Of Garten | Network Rail Closure
The Royal Highland Show 2025
A835 North of Loch Droma | Resurfacing
DF Concerts | Bellahouston Park
A701 Beattock | Essential Investigation
A75 Glenluce | Bridge Expansion Works
A9 Newtonmore | Surfacing Improvements
A720 Lothianburn-Straiton | Resurfacing
A87 Glen Shiel | Resurfacing
A77 Kilmarnock | Network Rail Survey Works
A77 Stranraer | SP Energy Work
A737 Dalry Bypass | Traffic Management
M9 Junction 3-4 | Bridge Refurbishment Works
Network Rail Langbank Road Closure 11th-12th July | Railway Bridge Survey
Network Rail Langbank Road Closure 8th-9th August | Railway Bridge Survey
Network Rail Langbank Road Closure 5th-6th September | Railway Bridge Survey
Network Rail Langbank Road Closure 3rd-4th October | Railway Bridge Survey
Network Rail Langbank Road Closure 31st October-1st November | Railway Bridge Survey
Planned roadworks
-
10th of June 2025, 8:00am10th of June 2025, 4:00pmM74 NB J20-J19 - Hard Shoulder Closure
-
10th of June 2025, 8:00am10th of June 2025, 4:30pmA9 Carrbridge NB - TTL
-
10th of June 2025, 8:00am10th of June 2025, 4:30pmA9 Carrbridge SB - TTL
-
10th of June 2025, 8:00am13th of June 2025, 5:00pmA90 Toll of Birness- Signage only N/B
-
10th of June 2025, 8:00am23rd of June 2025, 5:00pmA830 Morar EB - TTL
-
10th of June 2025, 8:00am23rd of June 2025, 5:00pmA830 Morar WB - TTL
-
10th of June 2025, 8:00am10th of June 2025, 11:59pmA68 SB Pathhead. Portable Traffic lights
-
10th of June 2025, 8:00am10th of June 2025, 11:59pmA68 NB Pathhead. Portable Traffic lights
-
10th of June 2025, 9:00am11th of June 2025, 6:00pmA83 A815 Jnct North of Cairndow - Stop/Go Works
-
10th of June 2025, 9:00am11th of June 2025, 6:00pmA83 Clachan - Stop/Go Works
-
10th of June 2025, 9:00am11th of June 2025, 6:00pmA83 Nursery Cott South of Tullochgorm - Stop/Go Works
-
10th of June 2025, 9:00am11th of June 2025, 6:00pmA83 Lochgair - Stop/Go Works
-
10th of June 2025, 9:00am11th of June 2025, 6:00pmA83 Lochgilphead - Stop/Go Works
-
10th of June 2025, 9:00am11th of June 2025, 6:00pmA83 Tarbert - Stop/Go Works
-
10th of June 2025, 9:00am11th of June 2025, 6:00pmA83 Corranbuie South of Tarbert - Stop/Go Works
-
10th of June 2025, 9:00am15th of June 2025, 11:59pmA96 Auldearn, Nairn- no obstruction- E/B
-
10th of June 2025, 9:30am10th of June 2025, 3:30pmA8 WB Greenock Road @ Woodhall Rbt Lane Closure
-
10th of June 2025, 9:30am10th of June 2025, 3:30pmA737 prior to Beith SB -TTLS
-
10th of June 2025, 9:30am10th of June 2025, 3:30pmA737 after Beith NB - TTLS
-
10th of June 2025, 9:30am11th of June 2025, 4:00pmA78 NB Shore Rd, Wemyss Bay - TTL's
-
10th of June 2025, 9:30am11th of June 2025, 4:00pmA78 SB Shore Rd, Wemyss Bay - TTL's
-
10th of June 2025, 9:30am12th of June 2025, 3:00pmA90 Ellon- Diversion signage N/B
-
10th of June 2025, 9:30am10th of June 2025, 4:30pmA702 - Lamington - NB - Temp Lights
-
10th of June 2025, 9:30am20th of June 2025, 6:30amM90 Broxden - MVMS signage- S/B
-
10th of June 2025, 9:30am20th of June 2025, 6:30amA9 Broxden - MVMS signage- N/B
-
10th of June 2025, 9:30am20th of June 2025, 6:30amA9 Broxden - MVMS signage- S/B
-
10th of June 2025, 4:00pm10th of June 2025, 7:00pmA85 Taynuilt - Give/Take Control
-
10th of June 2025, 7:00pm10th of June 2025, 11:00pmA82 Achintore Rd, Fort William NB - TTL
-
10th of June 2025, 7:00pm10th of June 2025, 11:00pmA82 Achintore Rd, Fort William SB - TTL
-
10th of June 2025, 7:30pm11th of June 2025, 6:00amA83 Loch Restil South of Rest and Be Thankful NB - TTL
-
10th of June 2025, 7:30pm11th of June 2025, 6:00amA83 Loch Restil South of Rest and Be Thankful SB - TTL
-
10th of June 2025, 7:30pm27th of June 2025, 6:30amA68 - NB - North of Pathhead / A6196 Rd Junction - Closure
-
10th of June 2025, 7:30pm27th of June 2025, 6:30amA68 - SB - North of Pathhead / A6196 Rd Junction - Closure
-
10th of June 2025, 7:30pm27th of June 2025, 6:30amA68 - SB - North of Pathhead off-slip to A6106 - Closure
-
10th of June 2025, 7:30pm27th of June 2025, 6:30amA68 - SB - North of Pathhead on-slip from A6106 - Closure
-
10th of June 2025, 7:30pm27th of June 2025, 6:30amA68 - NB - North of Pathhead off-slip to A6106 - Closure
-
10th of June 2025, 7:30pm27th of June 2025, 6:30amA68 - NB - North of Pathhead on-slip to A6106 - Closure
-
10th of June 2025, 7:30pm11th of June 2025, 6:30amA9 Queen Vic off slip, Dunblane- Slip Closure S/B
-
10th of June 2025, 7:30pm11th of June 2025, 6:30amA92 East Dock Street NB - Works on Footway
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 WB Jct 15 to 16 - Lane 3,4 Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 EB Jct 19 Off slip - Advance Signage
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 WB Jct 19 Onslip - Slip Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM80 S/B between J5 Auchenkilns and J4 Westfield - Road Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM80 S/B J5 Auchekilns on-slip - Road Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM80 S/B J4a Low Wood on-slip - Road Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 Jct 14 to Jct 13 EB - Hard Shoulder Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA90 Laurencekirk- Lane closure N/B
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA77 NB Dutchouse Rbt to Bellfield IC - Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA725 Northbound to A7071 - Total closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA90 Keithock- Lane closure N/B
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA77 NB Symington off slip - Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA90 Brechin- Lane closure N/B
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA77 NB Symington on slip - Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA77 NB Bogend off slip - Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA77 NB Bogend on slip - Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA77 NB Spitallhill off slip - Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amA77 NB Bellfield IC off slip - Closure
-
10th of June 2025, 8:00pm18th of June 2025, 6:00amM9 Junction 1B On-Slip Eastbound - Road Closure
-
10th of June 2025, 8:00pm18th of June 2025, 6:00amM9 Junction 1B to Junction 1A Eastbound - Road Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM73 Southbound Junction 2 to Junction 1 - Nearside lane closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 Westbound Junction 6 Newhouse Main line - Total closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 Westbound Junction 6A on-slip - Total Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 Junction 7 Eurocentral on-slip - Total closure
-
10th of June 2025, 8:00pm10th of June 2025, 8:01pmM8 WB Jct 19 Stobcross on ramp - No Obstruction on Carriageway or Footway
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 WB Jct 19 Waterloo St on ramp - Total Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 WB Jct 20 West St offslip - Total Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 WB Jct 19 to Jct 20 - Lane Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM8 WB Jct 19 Newton St - Total Closure
-
10th of June 2025, 8:00pm11th of June 2025, 6:00amM74 NB Jct 3a to 3 Lane Closures
-
10th of June 2025, 8:30pm14th of June 2025, 6:00amM8 - WB - Jct 4a to jct 5 - Road closure
-
10th of June 2025, 8:30pm14th of June 2025, 6:00amM8 - WB - Jct 4a on slip - Road closure
-
10th of June 2025, 8:30pm14th of June 2025, 6:00amM8 - WB - Jct 5 off slip - Road closure
-
10th of June 2025, 9:00pm11th of June 2025, 6:00amA9 Ballinluig NB - Lane Closure
-
10th of June 2025, 9:30pm12th of June 2025, 6:30amA95 Charlestown of Aberlour- TTLS S/B
-
10th of June 2025, 11:59pm13th of June 2025, 6:00amM8 Woodside - Local - A81 SB Garscube Rd Closure
-
10th of June 2025, 11:59pm13th of June 2025, 6:00amM8 Woodside - Local - A81 NB Garscube Rd Closure
-
10th of June 2025, 11:59pm13th of June 2025, 6:00amM8 Woodside - Local - A804 EB Dobbies Loan Closure
-
10th of June 2025, 11:59pm13th of June 2025, 6:00amM8 Woodside - Local - A804 WB Dobbies Loan Closure
-
11th of June 2025, 12:00am20th of July 2025, 11:59pmA78 Snowdon Terrace SB - TTLS
-
11th of June 2025, 12:00am20th of July 2025, 11:59pmA78 Snowdon Terrace NB - TTLS
-
11th of June 2025, 7:00am13th of June 2025, 7:00pmA85 Taynuilt Substation East of Taynuilt - Convoy Works
-
11th of June 2025, 7:00am11th of June 2025, 5:00pmA90 Glendoick- Signage only- S/B
-
11th of June 2025, 7:00am13th of June 2025, 7:00pmA87 Battle of Glen Sheil West of Glen Moriston WB - TTL
-
11th of June 2025, 7:00am13th of June 2025, 7:00pmA87 Battle of Glen Sheil West of Glen Moriston EB - TTL
-
11th of June 2025, 8:00am11th of June 2025, 4:00pmM74 NB J18-J17 - Hard Shoulder Closure
-
11th of June 2025, 8:00am12th of June 2025, 4:00pmM74 NB J16-J15 - Hard Shoulder Closure
-
11th of June 2025, 8:00am11th of June 2025, 4:30pmA86 Tullochroam East of Strathmashie WB - TTL
-
11th of June 2025, 8:00am11th of June 2025, 4:30pmA86 Tullochroam East of Strathmashie EB - TTL
-
11th of June 2025, 8:00am11th of June 2025, 5:00pmA90 Hatton- Div signage N/B
-
11th of June 2025, 8:00am16th of June 2025, 6:00pmA96 Colpy to B992. Diversion signage for LC road closure
-
11th of June 2025, 8:00am11th of June 2025, 5:30pmA95 Craggan. Sign 2 - S/B TTL's
-
11th of June 2025, 8:00am11th of June 2025, 5:30pmA95 Craggan. Sign 3 - N/B TTL's
-
11th of June 2025, 8:00am11th of June 2025, 5:30pmA95 Craggan. Sign 4 - N/B TTL's
-
11th of June 2025, 8:00am11th of June 2025, 12:00pmA82 Inveruglas - Stop/Go Works
-
11th of June 2025, 8:00am11th of June 2025, 6:00pmA85 Methven - Huntingtower - Diversion Signage
-
11th of June 2025, 9:00am11th of June 2025, 6:00pmA83 Cuilartich Bridge North of Tarbert - Stop/Go Works
-
11th of June 2025, 9:00am12th of June 2025, 6:00pmA85 River Orchy Bridge Loch Awe - Stop/Go Works
-
11th of June 2025, 9:00am12th of June 2025, 6:00pmA85 Innis Chonain Lochawe - Stop/Go Works
-
11th of June 2025, 9:00am12th of June 2025, 6:00pmA85 Fearnoch West of Taynuilt - Stop/Go Works
-
11th of June 2025, 9:00am12th of June 2025, 6:00pmA828 Duror - Stop/Go Works
-
11th of June 2025, 9:30am18th of June 2025, 3:30pmA85 Monzievaird West of Crieff - Stop/Go Works
-
11th of June 2025, 9:30am24th of June 2025, 3:30pmA85 St Fillans to Mink East of St Fillans EB - Rolling TTL
-
11th of June 2025, 9:30am24th of June 2025, 3:30pmA85 St Fillans to Mink East of St Fillans WB - Rolling TTL
-
11th of June 2025, 9:30am13th of June 2025, 3:30pmM77 SB Jct 1 to 4 - HS closures
-
11th of June 2025, 9:30am13th of June 2025, 3:30pmM77 NB Jct 4 to 1 - HS closures
-
11th of June 2025, 9:30am12th of June 2025, 7:00amA77 Kirkoswald Rd Turnberry SB - TTLS
-
11th of June 2025, 9:30am12th of June 2025, 7:00amA77 Kirkoswald Rd Turnberry NB - TTLS
-
11th of June 2025, 9:30am11th of June 2025, 3:30pmA7 SB Langholm NR EARSHAW HOLM B7068 From U517a At Elf Knowe To U256a
-
11th of June 2025, 9:30am11th of June 2025, 3:30pmA7 NB Langholm NR EARSHAW HOLM B7068 From U517a At Elf Knowe To U256a
-
11th of June 2025, 9:30am11th of June 2025, 3:30pmM74 SB Jct 2a HS Closure
-
11th of June 2025, 9:30am12th of June 2025, 3:30pmM8 EB Jct 21 Seaward St HS Closure
-
11th of June 2025, 9:30am11th of June 2025, 3:30pmA77 Glenapp BallantraeSB- TTL
-
11th of June 2025, 9:30am11th of June 2025, 3:30pmA77 Glenapp Ballantrae NB- TTL
-
11th of June 2025, 9:30am12th of June 2025, 3:30pmA806 Hornshill rbt. (Inner ring) - Lane Closure
-
11th of June 2025, 9:30am11th of June 2025, 3:30pmA92 Kilmany- TTLS S/B
-
11th of June 2025, 9:30am12th of June 2025, 3:30pmM74 NB Jct 8 Off Slip Lane Closure
-
11th of June 2025, 10:00am11th of June 2025, 4:00pmA82 Inveruglas - Vergeworks
-
11th of June 2025, 4:00pm12th of June 2025, 6:00amA985 - EB - Crombie Layby - Layby Closure
-
11th of June 2025, 5:00pm12th of June 2025, 10:00pmA68 - NB - Lauder - Temp Lights
-
11th of June 2025, 5:00pm12th of June 2025, 10:00pmA68 - SB - Lauder - Temp Lights
-
11th of June 2025, 7:00pm12th of June 2025, 5:00amA85 Crieff WB - TTL
-
11th of June 2025, 7:00pm12th of June 2025, 5:00amA85 Crieff EB - TTL
-
11th of June 2025, 7:00pm16th of June 2025, 6:00amA9 Toremore North of Dunbeath - Convoy Works
-
11th of June 2025, 7:30pm12th of June 2025, 6:30amA9 Keir roundabout- Lane Closure N/B
-
11th of June 2025, 8:00pm19th of June 2025, 6:00amA835 Garve WB - Road Closure with Amnesties
-
11th of June 2025, 8:00pm19th of June 2025, 6:00amA835 Garve EB - Road Closure with Amnesties
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA75 Collin EB- TTL
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA75 Collin WB- TTL
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA83 Lochgilphead NB - TTL
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA83 Lochgilphead SB - TTL
-
11th of June 2025, 8:00pm14th of June 2025, 6:00amA92 Portlethen- Convoy S/B
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM80 N/B between J4 Westfield and J5 Auchenkilns - Road Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM73 N/B between J3 Mollinsburn and M80 merge (J4) - Road Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM73 N/B J3 Mollinsburn on-slip - Road Closure
-
11th of June 2025, 8:00pm14th of June 2025, 6:00amM74 NB Jct 3 to 1 - Lane Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA1 - NB -Dolphingstone to Wallyford - Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA1 - NB -Dolphingstone on slip - Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA1 - NB -Wallyford off slip - Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA90 Laurencekirk- Lane closure S/B
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA725 Northbound Orbiston to Bellziehill main line - Total Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA725 Northbound Orbiston on-slip - Total closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA8 Westbound between Bargeddie Rbt to Swinton Rbt - Total closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA90 Todhills- Lane closure N/B
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA90 Forfar- Lane closure N/B
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA77 NB Bellfield IC to Meiklewood - Closure
-
11th of June 2025, 8:00pm13th of June 2025, 6:00amA76 SB Between New Cumnock to Kirkconnel - TTLs
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA77 NB Bellfield IC on slip - Closure
-
11th of June 2025, 8:00pm13th of June 2025, 6:00amA76 NB between Kirkconnel to New Cumnock - TTLs
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA77 NB Grassyards off slip - Closure
-
11th of June 2025, 8:00pm14th of June 2025, 6:00amA725 James Street overbridge at Diamond both directions - Total closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA77 NB Grassyards on slip - Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA77 NB Meiklewood off slip - road closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM73 Southbound to M74 Northbound link road - Total closure
-
11th of June 2025, 8:00pm18th of June 2025, 6:00amM9 Junction Junction 1A Off-Slip Eastbound - Road Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA92 Cowdenbeath- Lane closure N/B
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amA77 SB Jct 8 to Dutchhouse Rbt - Mobile Lane Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM8 EB Jct 24 to Jct 22 - Lane Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM8 EB Jct 24 on slip from Helen Street - Slip Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM8 EB Jct 23 on slip from Dumbreck Road - Slip Closure
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM74 SB Jct 2 to 3a Lane Closures
-
11th of June 2025, 8:00pm12th of June 2025, 6:00amM74 SB Jct 2a On Slip Total Closure
-
12th of June 2025, 7:30am12th of June 2025, 5:00pmA830 Banavie East of Corpach - Signage
-
12th of June 2025, 8:00am13th of June 2025, 4:00pmM74 SB J18-J19 - Hard Shoulder Closure
-
12th of June 2025, 8:00am13th of June 2025, 4:00pmM74 NB J15-J14 - Hard Shoulder Closure
-
12th of June 2025, 8:00am12th of June 2025, 5:00pmA83 Kennacraig NB - TTL
-
12th of June 2025, 8:00am12th of June 2025, 5:00pmA83 Kennacraig SB - TTL
-
12th of June 2025, 8:00am13th of June 2025, 5:00pmA96 Huntly- Lane Closure E/B
-
12th of June 2025, 8:30am12th of June 2025, 5:00pmA82 Tarbet - Stop/Go Works
-
12th of June 2025, 9:00am13th of June 2025, 6:00pmA82 Ballachulish - Stop/Go Works
-
12th of June 2025, 9:00am13th of June 2025, 6:00pmA82 Glencoe - Stop/Go Works
-
12th of June 2025, 9:00am13th of June 2025, 6:00pmA82 Altnafeadh South of Glencoe - Stop/Go Works
-
12th of June 2025, 9:00am13th of June 2025, 6:00pmA82 Achallader North of Bridge of Orchy - Stop/Go Works
-
12th of June 2025, 9:00am13th of June 2025, 6:00pmA82 Bridge of Orchy - Stop/Go Works
-
12th of June 2025, 9:30am12th of June 2025, 3:30pmA76 Blackwood Auldgirth SB- TTL
-
12th of June 2025, 9:30am12th of June 2025, 3:30pmA76 Blackwood Auldgirth NB- TTL
-
12th of June 2025, 9:30am12th of June 2025, 3:30pmA75 @ Balker Farm Caslte Kennedy WB- TTL
-
12th of June 2025, 9:30am12th of June 2025, 3:30pmA75 @ Balker Farm Castle Kennedy EB- TTL
-
12th of June 2025, 9:30am25th of June 2025, 3:30pmA7 - SB - Skipper's Bridge - Utility reconstruction - TTL's
-
12th of June 2025, 9:30am25th of June 2025, 3:30pmA7 - NB - Skipper's Bridge - Utility reconstruction - TTL's
-
12th of June 2025, 9:30am13th of June 2025, 4:30pmA702 SB - TTL's - Flotterston Inn
-
12th of June 2025, 9:30am13th of June 2025, 4:30pmA702 NB - TTL's - Flotterston Inn
-
12th of June 2025, 9:30am12th of June 2025, 3:30pmA96 Milton of Culloden EB - Temporary traffic signals
-
12th of June 2025, 7:30pm13th of June 2025, 6:30amA9 Blackford- Lane Closure N/B
-
12th of June 2025, 7:30pm13th of June 2025, 6:30amA9 Inveralmond Rbt- Lane closure N/B
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM74 SB Jct 6 Lane Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM74 NB Jct 2a Off Slip Total Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM74 NB Jct 2a Lane Closure
-
12th of June 2025, 8:00pm21st of June 2025, 6:00amA702 - NB - A72 S Jct to Stn Rd Jct Biggar - TTL's
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM74 NB Jct 6 - Lane Closure
-
12th of June 2025, 8:00pm21st of June 2025, 6:00amA702 - SB - A72 S Jct to A72 N Jct Biggar - TTL's
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM74 NB Jct 7 - Lane Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM80 N/B J3 Hornshill to M73 diverge (J4) - Road Closure
-
12th of June 2025, 8:00pm14th of June 2025, 6:00amM80 N/B J3 Hornshill on-slip - Road Closure
-
12th of June 2025, 8:00pm14th of June 2025, 6:00amA1 - NB -Wallyford to Old Craighall - Closure
-
12th of June 2025, 8:00pm14th of June 2025, 6:00amA1 - NB -Wallyford on slip - Closure
-
12th of June 2025, 8:00pm14th of June 2025, 6:00amA1 - NB -Old Craighall off slip - Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA90 Fordoun- Lane closure S/B
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA90 Glasslaw- Lane closure S/B
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA90 Tealing- Lane closure S/B
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA725 Northbound Raith Underpass - Total closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA8 Eastbound Swinton Rbt to Bargddie Rbt - Total closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA77 SB - Meiklewood to Bellfield IC - Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA77 SB - Meiklewood on slip Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA77 SB - Grassyards off slip - Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA77 SB - Grassyards on slip - Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA77 SB - Bellfield IC off slip - Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA8 EB Comet Rbt to M8 - Mobile Lane Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM898 NB M8 off Slip to Great Western Rd - Mobile Lane Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA720 - Calder Offslip - WB - Road Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA83 Lochgair NB - TTL
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM8 Jct 17 onslip WB - Total Closure
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amA83 Lochgair SB - TTL
-
12th of June 2025, 8:00pm13th of June 2025, 6:00amM8 Jct 19 offslip WB - Total Closure
-
12th of June 2025, 9:30pm14th of June 2025, 6:30amA95 Carron cottage to Cobblers cottage, Marypark. S/B TTL's
-
12th of June 2025, 10:00pm13th of June 2025, 11:59pmA726 Queensway - Route part of Diversion
-
12th of June 2025, 10:00pm13th of June 2025, 11:59pmA726 Queensway - Route part of Diversion
-
13th of June 2025, 7:00am13th of June 2025, 7:00pmA83 Auchindrain South of Inveraray NB - TTL
-
13th of June 2025, 7:00am13th of June 2025, 7:00pmA83 Auchindrain South of Inveraray SB - TTL
-
13th of June 2025, 7:30am24th of June 2025, 5:30pmA90 Finavon. N/B lane 1 closure
-
13th of June 2025, 9:00am23rd of June 2025, 3:30pmA9 Gleneagles- Signage only- N/B
-
13th of June 2025, 9:30am13th of June 2025, 3:30pmM77 NB Jct 2 -1 HS Closure
-
13th of June 2025, 7:00pm14th of June 2025, 7:00amA85 Taynuilt Substation East of Taynuilt EB - TTL
-
13th of June 2025, 7:00pm14th of June 2025, 7:00amA85 Taynuilt Substation East of Taynuilt WB - TTL
-
13th of June 2025, 7:00pm14th of June 2025, 7:00amA85 West of Bridge of Awe East of Taynuilt WB - TTL
-
13th of June 2025, 7:00pm14th of June 2025, 7:00amA85 West of Bridge of Awe East of Taynuilt EB - TTL
-
13th of June 2025, 7:30pm14th of June 2025, 6:30amA9 Blackford- Lane Closure S/B
-
13th of June 2025, 7:30pm20th of June 2025, 6:00amA68 - NB - Earlston to Carfraemill Rbt - Road Closure
-
13th of June 2025, 7:30pm20th of June 2025, 6:00amA68 - SB - Earlston to Caffraemill Rbt - Road Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amM77 NB Jct 1 to M8 EB Jct 22 - Lane Closures
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amM77 NB slip to the M8 EB - Total Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amM8 Hillington Interchange Lane Closures
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amM80 N/B J3 Hornshill to M73 diverge (J4) - Road Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA90 Stracathro- Lane closure S/B
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA90 Stracathro- Lane closure S/B
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA90 Laurencekirk- Lane closure S/B
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amM8 Eastbound Junction 6a Chapelhall off-slip - Total closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA8 Eastbound Bargeddie Rbt to Showcase - Total Closure
-
13th of June 2025, 8:00pm16th of June 2025, 6:00amM9 - EB - Newbridge - Hard Shoulder Closure
-
13th of June 2025, 8:00pm16th of June 2025, 6:00amM9 - WB - Newbridge - Hard Shoulder Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA77 SB - Bellfield IC to Dutchouse Rbt - Road Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA77 SB - Bellfield IC on slip - Slip Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA77 SB - Spitallhill on slip - Slip Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA77 SB - Bogend off slip Tarbolton Road - Slip Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA77 SB - Bogend on slip Tarbolton Road - Slip Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA77 SB - Symington off slip - Slip Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA77 SB - Symington on slip - Slip Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA8 WB M8 jct to Comet Rbt - Mobile Lane Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amM898 SB Great Western Rd to M8 On Slip -Mobile Lane Closure
-
13th of June 2025, 8:00pm14th of June 2025, 6:00amA720 - Lasswade Onslip - WB - Road Closure
-
14th of June 2025, 12:00am19th of June 2025, 11:59pmM74 SB J14-J15 - Single Lane Running / Lane Closure
-
14th of June 2025, 6:00am14th of June 2025, 5:00pmM74 NB Jct 6 Off slip - Event Signage
-
14th of June 2025, 6:00am14th of June 2025, 5:00pmM74 SB Jct 6 Off slip - Event Signage
-
14th of June 2025, 6:00am14th of June 2025, 5:00pmM74 SB Jct 5 Off slip - Event Signage
-
14th of June 2025, 10:00am14th of June 2025, 12:00pmA87 Portree - Event Road Closure
-
14th of June 2025, 12:30pm14th of June 2025, 6:00pmA77 Knockcushan/Dalrymple Street Girvan Planned Event
-
14th of June 2025, 12:30pm14th of June 2025, 6:00pmA77 Knockcushan/Dalrymple Street Girvan Planned Event
-
14th of June 2025, 8:00pm15th of June 2025, 6:00amA82 NB Erskine Jct to Tullichewan Rbt to - Mobile Lane Closure
-
15th of June 2025, 9:30am19th of June 2025, 11:59pmA78 Irvine Rd Seamill NB - No Obs On C/Way / F/Way
-
15th of June 2025, 9:30am19th of June 2025, 11:59pmA78 Irvine Rd Seamill SB - No Obs On C/Way / F/Way
-
15th of June 2025, 9:30am19th of June 2025, 11:59pmA9 South of Crossgates- no obstruction- N/B
-
15th of June 2025, 7:00pm18th of June 2025, 5:00amA84 Strathyre NB - Road Closure with Amnesties
-
15th of June 2025, 7:00pm18th of June 2025, 5:00amA84 Strathyre SB - Road Closure with Amnesties
-
15th of June 2025, 7:00pm28th of June 2025, 7:00amA9 Ralia NB - TTL
-
15th of June 2025, 7:00pm28th of June 2025, 7:00amA9 Ralia SB - TTL
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amM90 Kelty to Milnathort- Lane Closure S/B
-
15th of June 2025, 7:30pm3rd of July 2025, 6:00amM9 - EB - J9 Bannockburn - hard shoulder closure
-
15th of June 2025, 7:30pm3rd of July 2025, 6:00amM9 - EB - J9 Bannockburn - Lane closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA9 Broxden Rbt. Nth half of Rbt closed
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA9 Broxden Rbt. Sth half of Rbt closed
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amM90 Craigend to Broxden Rbt. N/B Road closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amM90 Broxden Rbt to Craigend . S/B Road closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amM90 Friarton to Broxden Rbt. N/B off slip closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA9 Broxden Rbt to A85. N/B Road closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA9/A85 off slip to Broxden Rbt. S/B Road closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA9 N/B approach to Broxden Rbt. N/B Lane closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA9 S/B off slip from Broxden Rbt. S/B Lane closure closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amM90 dedicated S/B on slip from A93. S/B road closure closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA93 N/B off slip from Broxden Rbt. N/B lane closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA93 S/B on slip to Broxden Rbt. S/B lane closure
-
15th of June 2025, 7:30pm20th of June 2025, 6:30amA9 S/B on slip from A85 McDiarmid Park to Broxden Rbt. S/B Road closure
-
15th of June 2025, 8:00pm18th of June 2025, 6:00amA9 Etteridge NB - Convoy Works
-
15th of June 2025, 8:00pm18th of June 2025, 6:00amB789 Barrochan Rd - Lane Closure
-
15th of June 2025, 8:00pm18th of June 2025, 6:00amA9 Etteridge NB - Lane Closure
-
15th of June 2025, 8:00pm16th of June 2025, 6:00amA737 NB St James to Linwood - Lane Closure
-
15th of June 2025, 8:00pm16th of June 2025, 6:00amA737 SB St James to Linwood - Lane Closure
-
15th of June 2025, 8:00pm17th of June 2025, 6:00amTreeswood Rd over A77 - TTLs
-
15th of June 2025, 8:00pm4th of July 2025, 6:00amM9 - EB - J9 Bannockburn on slip -Slip Road Closure
-
15th of June 2025, 8:00pm20th of June 2025, 6:00amA737 EB Johnstone - Linwood - Total Closure
-
15th of June 2025, 8:00pm20th of June 2025, 6:00amA737 EB Onslip from Johnstone - Total Closure
-
15th of June 2025, 8:00pm20th of June 2025, 6:00amA737 EB offslip to Linwood - Total Closure
-
15th of June 2025, 8:00pm20th of June 2025, 6:00amA737 EB Kilbarchan - Johnstone - Lane Closure
-
15th of June 2025, 8:00pm16th of June 2025, 6:00amA9 Dalraddy North of Kingussie NB - Lane Closure
-
15th of June 2025, 8:00pm16th of June 2025, 6:00amA82 SB Tullichewan Rbt to Erskine Jct - Mobile Lane Closure
-
16th of June 2025, 6:00am20th of June 2025, 5:30pmA87 Kyle of Lochalsh EB - TTL
-
16th of June 2025, 6:00am20th of June 2025, 5:30pmA87 Kyle of Lochalsh WB - TTL
-
16th of June 2025, 7:00am25th of July 2025, 5:00pmA75 EB Barlae Dual - Lane Closures
-
16th of June 2025, 7:00am25th of July 2025, 5:00pmA75 WB Barlae Dual - 2 Way TTLS
-
16th of June 2025, 7:00am18th of June 2025, 7:00pmA87 Bun Loyne WB - TTL
-
16th of June 2025, 7:00am18th of June 2025, 7:00pmA87 Bun Loyne EB - TTL
-
16th of June 2025, 7:00am18th of June 2025, 7:00pmA887 Bun Loyne EB - TTL
-
16th of June 2025, 7:00am18th of June 2025, 7:00pmA887 Bun Loyne WB - TTL
-
16th of June 2025, 7:00am26th of June 2025, 5:00pmA85 Taynuilt WB - TTL
-
16th of June 2025, 7:30am23rd of June 2025, 4:00pmA985 WB Rosyth. No Obstruction on Carriageway or Footway
-
16th of June 2025, 7:30am23rd of June 2025, 4:00pmA985 EB Rosyth. No Obstruction on Carriageway or Footway
-
16th of June 2025, 8:00am18th of June 2025, 6:00pmA90 North Water Bridge SB - Diversion signage for local road closure
-
16th of June 2025, 8:00am26th of June 2025, 6:00pmA9 Cambusavie North of Dornoch NB - TTL
-
16th of June 2025, 8:00am26th of June 2025, 6:00pmA9 Cambusavie North of Dornoch SB - TTL
-
16th of June 2025, 8:00am17th of June 2025, 5:00pmA85 Dalveich East of Lochearnhead - Stop/Go Works
-
16th of June 2025, 8:00am20th of June 2025, 5:00pmM90 Craigend- Road Closure- S/B
-
16th of June 2025, 8:00am20th of June 2025, 5:00pmA82 Newtown South of Fort Augustus NB - TTL
-
16th of June 2025, 8:00am20th of June 2025, 5:00pmA82 Newtown South of Fort Augustus SB - TTL
-
16th of June 2025, 8:00am29th of June 2025, 6:00pmA75 WB Glenluce to Whitecrook - Route Part of Diversion
-
16th of June 2025, 8:00am29th of June 2025, 6:00pmA75 EB Glenluce to Whitecrook - Route Part of Diversion
-
16th of June 2025, 8:30am27th of June 2025, 6:00pmA87 Sconser WB - TTL
-
16th of June 2025, 8:30am27th of June 2025, 6:00pmA87 Sconser EB - TTL
-
16th of June 2025, 8:30am16th of June 2025, 4:30pmM90 off slip Mawcarse- Hard Shoulder Closure N/B
-
16th of June 2025, 8:30am16th of June 2025, 4:30pmM90 South of Broxden- Hard Shoulder Closure N/B
-
16th of June 2025, 8:30am16th of June 2025, 4:30pmM90 South of Broxden- Hard Shoulder Closure S/B
-
16th of June 2025, 9:00am18th of June 2025, 6:00amA85 East High Street Crieff EB - TTL
-
16th of June 2025, 9:00am18th of June 2025, 6:00amA85 East High Street Crieff WB - TTL
-
16th of June 2025, 9:00am18th of June 2025, 4:00pmA82 Onich NB - TTL
-
16th of June 2025, 9:00am18th of June 2025, 4:00pmA82 Onich SB - TTL
-
16th of June 2025, 9:00am17th of June 2025, 5:00pmA83 Inverneil - Stop/Go Works
-
16th of June 2025, 9:00am18th of June 2025, 3:00pmA9 Greenloaning to Gleneagles. Diversion signage for local road closure
-
16th of June 2025, 9:00am4th of July 2025, 4:00pmA85 Huntingtower - Diversion Signage
-
16th of June 2025, 9:30am18th of June 2025, 3:30pmA75 WB at Haugh of Urr - TTLs
-
16th of June 2025, 9:30am18th of June 2025, 3:30pmA75 EB at Haugh of Urr -TTLs
-
16th of June 2025, 9:30am16th of June 2025, 3:30pmA75 WB Annan - TTL's
-
16th of June 2025, 9:30am16th of June 2025, 3:30pmA75 EB Annan - TTL's
-
16th of June 2025, 9:30am20th of June 2025, 4:00pmA76 N/B Main St Kirkonnel - TTLS
-
16th of June 2025, 9:30am20th of June 2025, 4:00pmA76 S/B Main St Kirkonnel - TTLS
-
16th of June 2025, 9:30am16th of June 2025, 3:30pmA977 - SB - Kilbagie rbt - Fere Gait Kincardine - TTL's
-
16th of June 2025, 9:30am16th of June 2025, 3:30pmA977 - NB - Kilbagie rbt - Fere Gait Kincardine - TTL's
-
16th of June 2025, 9:30am20th of June 2025, 3:30pmA90 Glenfarg- Lane Closure S/B
-
16th of June 2025, 9:30am16th of June 2025, 3:30pmA9 Dunblane- Lane Closure S/B
-
16th of June 2025, 9:30am16th of June 2025, 3:30pmA90 Glendoick SB - Lane closure
-
16th of June 2025, 9:30am18th of June 2025, 6:00pmA90 Fiddes SB - Slip lane closure to the garage
-
16th of June 2025, 9:30am20th of June 2025, 11:59pmA96 West of Nairn- no obstruction- W/B
-
16th of June 2025, 9:30am26th of June 2025, 5:00pmA85 Taynuilt EB - TTL
-
16th of June 2025, 9:30am18th of June 2025, 3:30pmA835 Braes of Ullapool WB - TTL
-
16th of June 2025, 9:30am18th of June 2025, 3:30pmA835 Braes of Ullapool EB - TTL
-
16th of June 2025, 10:00am16th of June 2025, 4:00pmA726 Queensway - West Mains to Carmunnock NS EB closure
-
16th of June 2025, 7:30pm3rd of July 2025, 6:00amA7-NB-South of Selkirk-Road closure
-
16th of June 2025, 7:30pm3rd of July 2025, 6:00amA7-SB-South of Selkirk-Road closure
-
16th of June 2025, 7:30pm25th of July 2025, 6:30amA9 Cairney Braes, Broom of Dalreoch- Lane Closure N/B
-
16th of June 2025, 7:30pm17th of June 2025, 6:30amA90 Swallow Rbt- Lane closure N/B
-
16th of June 2025, 7:30pm17th of June 2025, 6:30amA90 Swallows Rbt- Lane closure N/B
-
16th of June 2025, 7:30pm17th of June 2025, 6:30amA90 Swallows Rbt- Lane closure N/B
-
16th of June 2025, 7:30pm17th of June 2025, 6:30amA90 Kingsway West- Lane closure N/B
-
16th of June 2025, 7:30pm18th of June 2025, 6:30amA90 Emmock Rbt- Lane closure S/B
-
16th of June 2025, 7:30pm18th of June 2025, 6:30amA90 Gateside- Lane closure N/B
-
16th of June 2025, 7:30pm18th of June 2025, 6:30amA90 Forfar- Lane closure N/B
-
16th of June 2025, 7:30pm18th of June 2025, 6:30amA90 Forfar- Lane closure S/B
-
16th of June 2025, 7:30pm19th of June 2025, 6:30amA90 Finavon- Lane closure N/B
-
16th of June 2025, 7:30pm19th of June 2025, 6:30amA90 Finavon- Lane closure S/B
-
16th of June 2025, 7:30pm19th of June 2025, 6:30amA90 Brechin- Lane closure N/B
-
16th of June 2025, 7:30pm19th of June 2025, 6:30amA90 Brechin- Lane closure S/B
-
16th of June 2025, 7:30pm19th of June 2025, 6:30amA90 Brechin- Laner closure S/B
-
16th of June 2025, 7:30pm19th of June 2025, 6:30amA90 Brechin- Lane closure N/B
-
16th of June 2025, 7:30pm25th of June 2025, 6:30amA90 Keilburn Convoy S/B
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM74 SB J22-J45 - Lane Closure
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amA75 WB Inch Church to A751 - Road Closure
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amA75 EB Inch Church to A751 - Road Closure
-
16th of June 2025, 8:00pm18th of June 2025, 6:00amA82 NB Dumbarton Road Milton Lane Closures
-
16th of June 2025, 8:00pm18th of June 2025, 6:00amA82 SB Dumbarton Road Milton Lane Closures
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amA82 Achintore Rd Fort William NB - TTL
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amA82 Achintore Rd Fort William SB - TTL
-
16th of June 2025, 8:00pm8th of July 2025, 6:00amA726 Queensway College Milton Rail Bridge Eastbound - Total Closure
-
16th of June 2025, 8:00pm8th of July 2025, 6:00amA726 Queensway College Milton Rail Bridge Westbound - Total Closure
-
16th of June 2025, 8:00pm8th of July 2025, 6:00amA726 Queensway Collge Milton Bridge - Footway closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:30amA90 Drumlithie SB - Lane closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM80 N/B between J4a Low Wood and J6 Old Inns - Road Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM80 N/B J5 Auchenkilns on-slip - Road Closure
-
16th of June 2025, 8:00pm20th of June 2025, 6:30amA76 New Cumnock Progressive SB TTLs
-
16th of June 2025, 8:00pm20th of June 2025, 6:30amA76 New Cumnock Progressive NB TTLs
-
16th of June 2025, 8:00pm19th of June 2025, 6:00amA725 Southbound Orbiston to Raith - Nearside lane closure
-
16th of June 2025, 8:00pm19th of June 2025, 6:00amA725 Southbound Raith off-slip - Total closure
-
16th of June 2025, 8:00pm19th of June 2025, 6:00amA725 Raith Rbt - Outer ring lane closure
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amBogmoor Rd - TTLs
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amA78 SB Montfode Rbt to Chapelhill Rbt - Road Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amA78 SB Chapelhill Rbt to Sharphill Rbt - Road Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amA78 SB Sharphill Rbt to Pennyburn Rbt -Road Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amA78 SB Pennyburn Rbt to Eglinton IC Road Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amA78 SB Eglinton off slip - Slip Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM77 SB Jct 2 off Slip - Total Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM77 NB Jct 3 - Lane Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM77 SB Jct 2 - Total Closure
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amA725 Raith Roundabout - Inner & Outer ring closure
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amA8 Bargeddie Roundabout - Inner & Outer ring closure
-
16th of June 2025, 8:00pm21st of June 2025, 6:00amA8 Swinton Roundabout - Inner & Outer ring closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM8 Eastbound Junction 8 to Junction 7a - Nearside & Adjacent lane closure
-
16th of June 2025, 8:00pm24th of June 2025, 6:00amM90 - SB - Junction 3 SB Onslip - Road Closure
-
16th of June 2025, 8:00pm24th of June 2025, 6:00amM90 - SB - Mainline from Jct 3 to Junction 2A - Road Closure
-
16th of June 2025, 8:00pm24th of June 2025, 6:00amA92 - SB - Left Lane on Halbeath Roundabout - Lane Closure
-
16th of June 2025, 8:00pm17th of June 2025, 6:00amM876 NB - Lane Closures - Jct 8 to Higgins Neuk Rbt
-
16th of June 2025, 8:00pm27th of June 2025, 6:00amM9 - NB - J1a to J1b - Road Closure
-
16th of June 2025, 8:00pm27th of June 2025, 6:00amM9 - NB - J1a to J1b - Road Closure
-
16th of June 2025, 8:30pm18th of June 2025, 6:00amM8 - WB - Jct 5 to jct 6a - Road closure
-
16th of June 2025, 8:30pm18th of June 2025, 6:00amM8 - WB - Jct 5 on slip - Road closure
-
16th of June 2025, 8:30pm18th of June 2025, 6:00amM8 - WB - Jct 6 off slip - Road closure
-
16th of June 2025, 8:30pm20th of June 2025, 5:30amA82 Torlundy NB - TTL
-
16th of June 2025, 8:30pm20th of June 2025, 5:30amA82 Torlundy SB - TTL
-
16th of June 2025, 8:30pm17th of June 2025, 6:00amA720 - Millerhill Onslip - WB - Road Closure
-
16th of June 2025, 9:00pm19th of June 2025, 5:00amA1 SB Grantshouse. Portable Traffic Lights
-
16th of June 2025, 9:00pm19th of June 2025, 5:00amA1 NB Grantshouse. Portable Traffic Lights
-
16th of June 2025, 9:30pm18th of June 2025, 6:30amA95 Bridge of Avon- TTLS S/B
-
16th of June 2025, 10:00pm19th of July 2025, 6:00amA9 Granish to Carrbridge - Diversion Signage
-
16th of June 2025, 10:00pm17th of June 2025, 6:00amM8 WB JCT 18 TO A804 OB - Road Closure
-
16th of June 2025, 10:00pm17th of June 2025, 6:00amM8 WB JCT 18 -Lane Closure
-
17th of June 2025, 6:00am19th of June 2025, 8:00pmA75 WB Inch Church to A751 - TTL's
-
17th of June 2025, 6:00am19th of June 2025, 8:00pmA75 EB Inch Church to A751 - TTL's
-
17th of June 2025, 6:01am2nd of July 2025, 4:00pmA1 - NB - Eyemouth - TTL's
-
17th of June 2025, 6:01am2nd of July 2025, 4:00pmA1 - SB - Eyemouth - TTL's
-
17th of June 2025, 7:00am18th of June 2025, 5:00pmA77 N/B Lendalfoot to Ardwell - TTLs
-
17th of June 2025, 7:00am18th of June 2025, 5:00pmA77 S/B Lendalfoot to Ardwell - TTLs
-
17th of June 2025, 7:00am18th of June 2025, 7:00pmA86 Allt na Claise East of Aberarder WB - TTL
-
17th of June 2025, 7:00am18th of June 2025, 7:00pmA86 Allt na Claise East of Aberarder EB - TTL
-
17th of June 2025, 8:00am21st of June 2025, 5:00pmA9 Ballinluig to Bankfoot NB - Diversion Signage
-
17th of June 2025, 8:00am18th of June 2025, 6:00pmA90 North Water Bridge- Lane Closure N/B
-
17th of June 2025, 8:00am21st of June 2025, 5:00pmA9 Ballinluig to Bankfoot SB - Diversion Signage
-
17th of June 2025, 9:00am19th of June 2025, 6:00pmA76 Mennock NB - TTLS
-
17th of June 2025, 9:00am19th of June 2025, 6:00pmA76 Mennock SB - TTLS
-
17th of June 2025, 9:30am21st of June 2025, 11:59pmA725 East Kilbride Expressway WB - No Obs On C/Way / F/Way
-
17th of June 2025, 9:30am27th of June 2025, 3:30pmA90 Peterhead - Diversion Signage
-
17th of June 2025, 9:30am19th of June 2025, 3:00pmA85 Perth Rd Crieff WB - TTL
-
17th of June 2025, 9:30am19th of June 2025, 3:00pmA85 Perth Rd Crieff EB - TTL
-
17th of June 2025, 9:30am17th of June 2025, 3:30pmA78 NB Irvine Road, Fairlie - TTL's
-
17th of June 2025, 9:30am17th of June 2025, 3:30pmA78 SB Irvine Road, Fairlie - TTL's
-
17th of June 2025, 10:00am17th of June 2025, 4:00pmA726 Queensway - West Mains to Carmunnock NS WB closure
-
17th of June 2025, 7:30pm5th of July 2025, 6:00amA9 Dunkeld to Ballinluig NB - Diversion Signage
-
17th of June 2025, 7:30pm5th of July 2025, 6:00amA9 Dunkeld to Ballinluig SB - Diversion Signage
-
17th of June 2025, 7:30pm19th of June 2025, 6:00amM9 - SB - Jct 11 - Jct 9 - Closure
-
17th of June 2025, 7:30pm19th of June 2025, 6:00amM9 - SB - Jct 10 - Off Slip Closure
-
17th of June 2025, 7:30pm19th of June 2025, 6:00amM9 - NB - Jct 9 - Jct 11 - Closure
-
17th of June 2025, 7:30pm19th of June 2025, 6:00amM9 - NB - Jct 10- On Slip Closure
-
17th of June 2025, 8:00pm20th of June 2025, 6:00amA77 SB Bellfield I/C to Coodham -Total Closure
-
17th of June 2025, 8:00pm20th of June 2025, 6:00amA77 Coodham to Bellfield I/C NB -Total Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amM80 N/B J6 Old Inns on-slip - Road Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amM80 S/B J6 Old Inns off-slip - Road Closure
-
17th of June 2025, 8:00pm19th of June 2025, 6:00amM74 Jct 6 Off Slip To Hamilton SB - Slip Closure
-
17th of June 2025, 8:00pm19th of June 2025, 6:00amM74 Jct 6 Off Slip To Motherwell SB - Slip Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amM80 N/B between J6 Old Inns & J6a Castlecary - Lane Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amM80 S/B between J6a Castlecary & J6 Old Inns - Lane Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA90 Forfar- Lane closure S/B
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA90 Forfar- Lane closure S/B
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA90 Brechin- Lane closure S/B
-
17th of June 2025, 8:00pm19th of June 2025, 6:00amM74 Southbound Junction 5 main line -Total closure
-
17th of June 2025, 8:00pm19th of June 2025, 6:00amM74 Southbound Junction 5 on-slip - Total closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA78 NB Onslip Irvine Bypass Slip Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA78 NB Eglinton IC to Pennyburn Rbt - Road Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA78 NB Pennyburn Rbt to Sharphill Rbt - Road Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA78 NB Sharphill Rbt to Chapelhill Rbt - Road Closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amA78 NB Chapelhill Rbt to Montfode Rbt - Road closure
-
17th of June 2025, 8:00pm18th of June 2025, 6:00amM8 EB Jct 14 off slip - Total Closure
-
17th of June 2025, 8:00pm19th of June 2025, 6:00amM74 Southbound Junction 6 off-slip - Total closure
-
17th of June 2025, 8:00pm19th of June 2025, 6:00amM74 Jct 6 On Slip From Hamilton SB - Road As Part Of Diversion
-
17th of June 2025, 8:00pm20th of June 2025, 6:00amA78 Irvine Rd @ West Kilbride NB - TTLS
-
17th of June 2025, 8:00pm20th of June 2025, 6:00amA78 Irvine Rd @ West Kilbride SB - TTLS
-
17th of June 2025, 8:00pm21st of June 2025, 6:00amA1 NB - North of Ayton Junction - Road Closure
-
17th of June 2025, 8:00pm21st of June 2025, 6:00amA1SB - North of Ayton Junction - Road Closure
-
17th of June 2025, 10:00pm18th of June 2025, 6:00amM8 WB Great Western Rd On Slip- Slip Closure
-
17th of June 2025, 10:00pm18th of June 2025, 6:00amM8 WB Jct 18 -Lane Closure
-
18th of June 2025, 8:00am26th of June 2025, 5:00pmA96 Huntly- TTLS E/B
-
18th of June 2025, 9:00am20th of June 2025, 3:00pmA9 Bankfoot to Pitlochry SB - Diversion Signage
-
18th of June 2025, 9:00am20th of June 2025, 3:00pmA9 Bankfoot to Pitlochry NB - Diversion Signage
-
18th of June 2025, 9:00am23rd of June 2025, 11:59pmA9 Aldie South of Tain - Vergeworks
-
18th of June 2025, 9:30am27th of June 2025, 3:30pmA85 Lochearnhead EB - TTL
-
18th of June 2025, 9:30am27th of June 2025, 3:30pmA85 Lochearnhead WB - TTL
-
18th of June 2025, 9:30am19th of June 2025, 4:00pmA701 Locharbriggs SB - TTLS
-
18th of June 2025, 9:30am19th of June 2025, 4:00pmA701 Locharbriggs NB - TTLS
-
18th of June 2025, 9:30am18th of June 2025, 3:30pmA96 Blackcastle, Nairn- TTL E/B
-
18th of June 2025, 9:30am18th of June 2025, 3:30pmA8 Eastbound Eurocentral North Rbt to Chapelhall North rbt - Nearside lane closure
-
18th of June 2025, 10:00am19th of June 2025, 4:00pmA726 Queensway - West Mains to Carmunnock OS WB closure
-
18th of June 2025, 10:00am19th of June 2025, 4:00pmA726 Queensway - West Mains to Carmunnock OS EB closure
-
18th of June 2025, 7:00pm20th of June 2025, 5:00amA84 Doune NB - Road Closure with Amnesties
-
18th of June 2025, 7:00pm20th of June 2025, 5:00amA84 Doune SB - Road Closure with Amnesties
-
18th of June 2025, 7:30pm19th of June 2025, 6:00amA96 Inverness- TTLS E/B
-
18th of June 2025, 7:30pm20th of June 2025, 6:00amA1 - NB - North Gladsmuir - Lane Closures
-
18th of June 2025, 8:00pm23rd of June 2025, 6:00amA9 Etteridge SB - Convoy Works
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM8 EB Jct 25a on slip Total Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM8 EB Jct 17 to 16 Lane Closure
-
18th of June 2025, 8:00pm23rd of June 2025, 6:00amA9 Etteridge NB - Convoy Works
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amM8 E/B Jct 6 on-slip. Road Closure.
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM80 N/B J6a Castlecary on-slip - Road Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM80 N/B J7 Haggs off-slip - Road Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM80 S/B J7 Haggs on-slip - Road Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM80 S/B J6a Castlecary off-slip - Road Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM80 N/B between J6a Castlecary and J7 Haggs - Lane Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM80 S/B between J7 Haggs and J6a Castlecary - Lane Closure
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amM8 WB Jct 30 - Jct 31 - Total Closure
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amM8 WB Jct 30 Onslip - Total Closure
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amM8 WB Jct 31 Offslip - Total Closure
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amM8 WB Jct 30 - 27 - Lane Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 NB - Monktonhead Rbt to Meadowhead Rbt - Road closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 NB - Loans off slip - Slip Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 NB - Loans on slip - Slip Closure
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amA726 WB Eaglesham Rbt - West Mains Rbt - Total Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amM8 Eastbound Junction 6 on-slip - Total closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 NB - Barassie off slip - Slip closure
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amA726 WB Eaglesham Rbt - Outer ring Lane Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA8 Eastbound Junction 6 Newhouse main line - Nearside lane closure
-
18th of June 2025, 8:00pm21st of June 2025, 6:00amA726 EB West Mains Rbt - Outer ring Lane Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 SB Eglinton IC to Meadowhead Rbt -Road closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 SB Eglinton IC on slip - Slip Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 SB Warrix IC off slip - Slip Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 SB Warrix IC on slip - Slip Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA725 NB Blantyre onslip - Total Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 SB Newhouse off slip- Slip Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA78 SB Newhouse IC on slip - Slip Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA725 SB Main St onslip - Total Closure
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA724 WB Glasgow Rd - TTLS
-
18th of June 2025, 8:00pm19th of June 2025, 6:00amA724 EB Glasgow Rd - TTLS
-
18th of June 2025, 8:30pm21st of June 2025, 6:00amM8 E/B Jct 6A to Jct 5. Road Closure.
-
18th of June 2025, 8:30pm21st of June 2025, 6:00amM8 E/B Jct 5 off-slip. Road Closure.
-
18th of June 2025, 9:30pm20th of June 2025, 6:30amA95 Cromdale- TTLS S/B
-
18th of June 2025, 10:00pm19th of June 2025, 6:00amA95 S/B Boat of Garten - Road Closure
-
19th of June 2025, 7:00am20th of June 2025, 7:00pmA87 Kyle of Lochalsh - Vergeworks
-
19th of June 2025, 8:00am23rd of June 2025, 5:00pmA96 Colpy- Diversion signage E/B
-
19th of June 2025, 8:00am21st of June 2025, 5:00pmA77 Main Street Ballantrae NB - TTLS
-
19th of June 2025, 8:00am21st of June 2025, 5:00pmA77 Main Street Ballantrae SB - TTLS
-
19th of June 2025, 9:00am21st of June 2025, 6:00amA90 Saltoun Pl. Diversion signage for local road closure
-
19th of June 2025, 9:30am19th of June 2025, 3:30pmA92 Newtonhill SB - Lane closure
-
19th of June 2025, 11:00am19th of June 2025, 3:00pmA702 - SB - West Linton - TTL's
-
19th of June 2025, 11:00am19th of June 2025, 3:00pmA702 - NB - West Linton - TTL's
-
19th of June 2025, 8:00pm24th of June 2025, 6:00amA835 Loch Droma East of Braemore WB - Road Closure with Amnesties
-
19th of June 2025, 8:00pm24th of June 2025, 6:00amA835 Loch Droma East of Braemore EB - Road Closure with Amnesties
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amM80 N/B between J6a Castlecary and J7 Haggs - Lane Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amM80 S/B between J7 Haggs and J6a Castlecary - Lane Closure
-
19th of June 2025, 8:00pm23rd of June 2025, 6:00amA726 EB West Mains Rbt - Eaglesham Rbt - Total Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 NB Meadowhead Rbt to Eglinton IC - Road Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 NB Newhouse offslip - Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 NB Newhouse IC onslip - Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 NB Warrix IC off slip - Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 NB Warrix IC on slip - Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 SB Meadowhead Rbt to Monktonhead Rbt- Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 SB Auchengate Onslip - Slip Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 SB Loans off slip - Slip Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amA78 SB Loans on slip - Slip Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amM8 WB Jct 16 to Jct 17 - Lane Closures
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amM8 WB Jct 17 to Jct 19 - Total Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amM8 Jct 17 onslip WB - Total Closure
-
19th of June 2025, 8:00pm20th of June 2025, 6:00amM8 WB Jct 19 to Jct 21 - Lane Closures
-
20th of June 2025, 8:00am24th of June 2025, 5:00pmA701 Heathhall NB - TTLS
-
20th of June 2025, 8:00am24th of June 2025, 5:00pmA701 Heathhall SB - TTLS
-
20th of June 2025, 7:00pm21st of June 2025, 5:00amA84 Strathyre - Convoy Works
-
20th of June 2025, 7:30pm21st of June 2025, 6:00amA1 - SB - Lemington to Heugh Head - Lane Closures
-
20th of June 2025, 7:30pm21st of June 2025, 6:00amA68 - NB - Earlston - TTLs
-
20th of June 2025, 7:30pm21st of June 2025, 6:00amA68 - SB - Earlston - TTLs
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amA82 SB Stirling Rd at Dumbuckhill Quarry - Nearside Lane Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amM80 S/B between J6 Old Inns and J4a Low Wood - Road Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amM80 S/B J6 Old Inns on-slip - Road Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amM80 S/B J5 Auchenkilns on-slip - Road Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amM8 Eastbound Junction 8 to Junction 7a - Nearside lane closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amA82 NB Barloan to Stoneymollan Rbt - Total Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amA82 NB offslip to Renton Rd - Total Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amA82 Stirling Rd Milton to Dumbarton NB - Nearside Lane Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amA82 S/B Stoneymollan to Barloan – Total Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amA82 S/B Renton On Slip - Total Closure
-
20th of June 2025, 8:00pm21st of June 2025, 6:00amA82 S/B Renton Off Slip - Total Closure
-
20th of June 2025, 9:30pm24th of June 2025, 6:30amA95 Cromdale- TTLS S/B
-
21st of June 2025, 8:00am10th of July 2025, 6:00amA96 Oyne Fork to Old Rayne WB - Diversion signage for local road closure
-
21st of June 2025, 8:00pm28th of June 2025, 6:00amM8 Jct 28A - A737 Linwood SB - Total Closure
-
21st of June 2025, 8:00pm28th of June 2025, 6:00amA737 Linwood SB Onslip from St James- Total Closure
-
21st of June 2025, 8:00pm30th of June 2025, 6:00amA737 Linwood WB Offslip - Total Closure
-
21st of June 2025, 8:00pm28th of June 2025, 6:00amM8 Jct 27 - 28A - Lane Closure
-
21st of June 2025, 8:30pm28th of June 2025, 6:00amM8 - EB - Jct 4 on slip - Closure
-
21st of June 2025, 8:30pm22nd of June 2025, 6:00amM8 EB Jct 3 to 2. Road Closure.
-
21st of June 2025, 8:30pm22nd of June 2025, 6:00amM8 EB Jct 3 on-slip. Road Closure.
-
21st of June 2025, 8:30pm22nd of June 2025, 6:00amM8 EB Jct 2 off-slip. Road Closure.
-
21st of June 2025, 8:30pm22nd of June 2025, 6:00amM8 WB Jct 2 to 3. Road Closure.
-
21st of June 2025, 8:30pm22nd of June 2025, 6:00amM8 WB Jct 3 off-slip. Road Closure.
-
21st of June 2025, 8:30pm22nd of June 2025, 6:00amM9 EB Jct 2 to M8 WB Jct 2. Road Closure.
-
21st of June 2025, 8:30pm28th of June 2025, 5:30amA85 Dunollie Rd Oban EB - TTL
-
21st of June 2025, 8:30pm28th of June 2025, 5:30amA85 Dunollie Rd Oban WB - TTL
-
21st of June 2025, 8:30pm28th of June 2025, 6:00amM8 - WB - Jct 3a on slip - Closure
-
21st of June 2025, 8:30pm28th of June 2025, 6:00amM8 - EB - Jct 4 to 3A - Closure
-
21st of June 2025, 8:30pm28th of June 2025, 6:00amM8 - WB - Jct 3a to Jct 4 - Closure
-
21st of June 2025, 9:30pm29th of June 2025, 3:00amM8 J23 WB offslip - Slip Closure
-
21st of June 2025, 9:30pm29th of June 2025, 3:00amM77 J1 NB Offslip - Lane Closure/Left Turn Ban
-
21st of June 2025, 9:30pm29th of June 2025, 3:00amM77 J1 SB Offslip - Lane Closure/RightTurn Ban
-
21st of June 2025, 9:30pm29th of June 2025, 3:00amM8 EB Jct 23 onslip - Slip Closure
-
22nd of June 2025, 9:00am26th of June 2025, 11:59pmA90 Toll of Birness- no obstruction- N/B
-
22nd of June 2025, 7:00pm27th of June 2025, 7:00amA82 North of Invergloy NB - Road Closure with Amnesties
-
22nd of June 2025, 7:00pm27th of June 2025, 7:00amA82 North of Invergloy SB - Road Closure with Amnesties
-
22nd of June 2025, 7:00pm28th of June 2025, 5:00amA84 Doune - Convoy Works
-
22nd of June 2025, 7:00pm5th of July 2025, 7:00amA82 Bridge of Orchy NB - TTL
-
22nd of June 2025, 7:00pm5th of July 2025, 7:00amA82 Bridge of Orchy SB - TTL
-
22nd of June 2025, 8:00pm24th of June 2025, 6:00amA77 Bellfield Interchange - Lane Closure
-
22nd of June 2025, 8:00pm24th of June 2025, 6:00amA77 SB Off slip to Belfield Interchange - Lane Closure
-
22nd of June 2025, 8:00pm24th of June 2025, 6:00amA77 NB Off slip to Belfield Interchange - Lane closure
-
22nd of June 2025, 8:00pm24th of June 2025, 6:00amA76 NB approach to Bellfield - Lane Closure
-
22nd of June 2025, 8:00pm24th of June 2025, 6:00amA71 NB Approach to Bellfield - Lane Closure
-
22nd of June 2025, 8:00pm24th of June 2025, 6:00amA71 NB Riccarton Rd prior to Bellfield - Lane Closure
-
22nd of June 2025, 8:00pm24th of June 2025, 6:00amA735 Queens Dr approach to Bellfield - Lane closure
-
22nd of June 2025, 8:00pm26th of June 2025, 6:00amM8 WB J23/J24 - Lane closure
-
22nd of June 2025, 8:00pm4th of July 2025, 6:00amM8 J24 off slip to Helen St - Total closure
-
22nd of June 2025, 8:00pm4th of July 2025, 6:00amM8 J22 Sec carriageway to mM WB - Total closure
-
22nd of June 2025, 8:00pm26th of June 2025, 6:00amA75 Bloomfield Rbt Dumfries EB - TTLS
-
22nd of June 2025, 8:00pm26th of June 2025, 6:00amA75 Bloomfield Rbt Dumfries WB - TTLS
-
22nd of June 2025, 8:00pm30th of June 2025, 6:00amA701 NB From B7076 to Beattock I/C - TTLs
-
22nd of June 2025, 8:00pm30th of June 2025, 6:00amA701 SB Beattock IC to B7076 TTLs
-
23rd of June 2025, 12:00am5th of July 2025, 6:00amA8 WB East Hamilton Street- Lane Closure
-
23rd of June 2025, 6:00am27th of June 2025, 7:00pmA9 Broom of Dalreoch to Crossgates. Diversion signage for local road closure
-
23rd of June 2025, 6:00am28th of June 2025, 8:00pmM8 EB Jct 11 between the slips - HS Closure
-
23rd of June 2025, 7:00am1st of July 2025, 7:00pmA84 Runacraig NB - TTL
-
23rd of June 2025, 7:00am1st of July 2025, 7:00pmA84 Runacraig SB - TTL
-
23rd of June 2025, 7:00am27th of June 2025, 7:00pmA87 Sheil Bridge WB - TTL
-
23rd of June 2025, 7:00am27th of June 2025, 7:00pmA87 Sheil Bridge EB - TTL
-
23rd of June 2025, 7:00am11th of July 2025, 7:00pmA835 Contin WB - TTL
-
23rd of June 2025, 7:00am11th of July 2025, 7:00pmA835 Contin EB - TTL
-
23rd of June 2025, 8:00am27th of June 2025, 5:00pmA75 EB Springholm - TTL's
-
23rd of June 2025, 8:00am27th of June 2025, 5:00pmA75 WB Springholm - TTL's
-
23rd of June 2025, 8:00am2nd of July 2025, 5:00pmA90 Laurencekirk- Div signage N/B
-
23rd of June 2025, 8:00am27th of June 2025, 6:00pmA96 Colpy- Div signage E/B
-
23rd of June 2025, 8:00am4th of July 2025, 11:59pmA77 Glendoune St Girvan SB - Road Part Of Diversion
-
23rd of June 2025, 8:00am4th of July 2025, 11:59pmA77 Glendoune St Girvan NB - Road Part Of Diversion
-
23rd of June 2025, 8:00am2nd of July 2025, 4:00pmA9 Ballinluig to Faskally SB - Diversion Signage
-
23rd of June 2025, 8:00am2nd of July 2025, 4:00pmA9 Ballinluig to Faskally NB - Diversion Signage
-
23rd of June 2025, 8:00am4th of July 2025, 5:00pmA75 Glenluce WB - Road As Part Of Diversion
-
23rd of June 2025, 8:00am4th of July 2025, 5:00pmA75 Glenluce EB - Road As Part Of Diversion
-
23rd of June 2025, 8:00am7th of July 2025, 5:00pmA78 Snowdon Terrace NB - Road As Part Of Diversion
-
23rd of June 2025, 8:00am7th of July 2025, 5:00pmA78 Snowdon Terrace SB - Road As Part Of Diversion
-
23rd of June 2025, 9:00am23rd of June 2025, 9:00pmA68 - SB - West High Street - Lauder - Lay-by closure
-
23rd of June 2025, 9:00am2nd of July 2025, 3:00pmM90 Kinross- Signage N/B
-
23rd of June 2025, 9:00am2nd of July 2025, 1:00pmA91 Milnathort- Signage S/B
-
23rd of June 2025, 9:30am24th of June 2025, 3:00pmA85 Methven WB - TTL
-
23rd of June 2025, 9:30am24th of June 2025, 3:00pmA85 Methven EB - TTL
-
23rd of June 2025, 9:30am24th of June 2025, 4:00pmA78 Sharphill Rbt Ardrossan N/B Lane Closures
-
23rd of June 2025, 9:30am24th of June 2025, 4:00pmA78 Sharphill Rbt Ardrossan S/B Lane Closures
-
23rd of June 2025, 9:30am23rd of June 2025, 3:30pmA85 Methven - Diversion Signage
-
23rd of June 2025, 9:30am19th of September 2025, 3:30pmA76 New Cumnock NB TTLS
-
23rd of June 2025, 9:30am19th of September 2025, 3:30pmA76 New Cumnock SB TTLs
-
23rd of June 2025, 9:30am25th of June 2025, 4:00pmA835 Conon Bridge - Stop/Go Works
-
23rd of June 2025, 9:30am27th of June 2025, 4:30pmA702 - NB - Dolphinton - Temp Lights
-
23rd of June 2025, 9:30am27th of June 2025, 4:30pmA702 - SB - West Linton - Temp Lights
-
23rd of June 2025, 9:30am27th of June 2025, 3:30pmA96 Alves- Stop/Go E/B
-
23rd of June 2025, 9:30am27th of June 2025, 3:30pmA96 Nairn- Stop/Go E/B
-
23rd of June 2025, 7:00pm1st of July 2025, 6:00amA9 Longman Rnbt Inverness - Lane Closure
-
23rd of June 2025, 7:00pm1st of July 2025, 6:00amA9 Longman Rnbt SB Inverness - Lane Closure
-
23rd of June 2025, 7:00pm1st of July 2025, 6:00amA9 Longman Rnbt NB Inverness - Lane Closure
-
23rd of June 2025, 7:00pm1st of July 2025, 6:00amA82 Longman Rd Inverness NB - Lane Closure
-
23rd of June 2025, 7:00pm1st of July 2025, 6:00amA82 Longman Rd Inverness SB - Lane Closure
-
23rd of June 2025, 7:00pm3rd of July 2025, 6:00amA701 Ae Junction Parkgate NB Road closure
-
23rd of June 2025, 7:00pm3rd of July 2025, 6:00amA701 Ae Junction Parkgate SB Road closure
-
23rd of June 2025, 7:30pm28th of June 2025, 6:30amM90 Kelty to Milnathort- Lane Closure N/B
-
23rd of June 2025, 7:30pm28th of June 2025, 6:00amA1 - NB - Eyemouth - Road Closure
-
23rd of June 2025, 7:30pm28th of June 2025, 6:00amA1 - SB - Eyemouth - Road Closure
-
23rd of June 2025, 7:30pm27th of June 2025, 6:30amA85 Dundee Rd, Perth W/B lane closures
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amM77 SB Jct 4 off slip - Lane Closure
-
23rd of June 2025, 8:00pm28th of June 2025, 6:00amA75 EB over Water of Luce Glenluce - Convoy
-
23rd of June 2025, 8:00pm28th of June 2025, 6:00amA75 WB over Water of Luce Glenluce - Convoy
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA8 WB East Hamilton St Lane Closures
-
23rd of June 2025, 8:00pm1st of July 2025, 6:00amA9 Braes of Nuide Newtonmore - Convoy Works
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amM8 W/B prior to J31 - Lane Closure
-
23rd of June 2025, 8:00pm25th of June 2025, 6:00amM74 NB Jct 6 off slip - Total closure
-
23rd of June 2025, 8:00pm25th of June 2025, 6:00amA1 - NB - Bilsdean - TTL's
-
23rd of June 2025, 8:00pm25th of June 2025, 6:00amA1 - SB - Bilsdean - TTL's
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amM8 EB Jct 25 to Jct 23 - Lane Closure
-
23rd of June 2025, 8:00pm25th of June 2025, 6:00amM80 S/B between M73 diverge (J4) and J3 Hornshill - Road Closure
-
23rd of June 2025, 8:00pm25th of June 2025, 6:00amM80 S/B J4 Westfield on-slip - Road Closure
-
23rd of June 2025, 8:00pm30th of June 2025, 6:00amM73 Southbound Junction 2 to Junction 1 - Offside lane running
-
23rd of June 2025, 8:00pm30th of June 2025, 6:00amM73 Southbound to M74 Southbound - Total closure
-
23rd of June 2025, 8:00pm30th of June 2025, 6:00amA721 Southbound to M74 Southbound - Total closure
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA8 Newhouse Westbound off-slip - Total closure
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA725 Northbound to M8 Eastbound link road - total closure
-
23rd of June 2025, 8:00pm28th of June 2025, 6:00amFifty Pitches Rd - Road Closure
-
23rd of June 2025, 8:00pm25th of June 2025, 6:30amA90 Invernettie Rbt. S/B lane closures
-
23rd of June 2025, 8:00pm30th of June 2025, 6:00amM74 Jct 3 to Jct 2A NB - Road As Part Of Diversion
-
23rd of June 2025, 8:00pm30th of June 2025, 6:00amM74 Jct 3 to Jct 2A SB - Road As Part Of Diversion
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA82 NB Barloan to Stoneymollan Rbt - Total Closure
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA82 NB offslip to Renton Rd - Total Closure
-
23rd of June 2025, 8:00pm28th of June 2025, 6:00amM8 EB Jct 11 between the slips - Lane Closure
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA82 S/B Stoneymollan to Barloan – Total Closure
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA82 S/B Renton On Slip - Total Closure
-
23rd of June 2025, 8:00pm24th of June 2025, 6:00amA82 S/B Renton Off Slip - Total Closure
-
23rd of June 2025, 8:30pm4th of July 2025, 6:00amA720 - EB - Lothianburn - Closure
-
23rd of June 2025, 8:30pm4th of July 2025, 6:00amA720 - EB - Lothianburn onslip - Closure
-
23rd of June 2025, 8:30pm4th of July 2025, 6:00amA720 - EB - Straiton Off Slip - Closure
-
23rd of June 2025, 8:30pm26th of June 2025, 6:00amM8 - EB - Jct 5 to 4a - Road closure
-
23rd of June 2025, 8:30pm26th of June 2025, 6:00amM8 - EB - Jct 5 on slip - Road closure
-
23rd of June 2025, 8:30pm26th of June 2025, 6:00amM8 - EB - Jct 4a off slip - Road closure
-
23rd of June 2025, 10:00pm24th of June 2025, 6:00amA85 Crianlarich EB - TTL
-
23rd of June 2025, 10:00pm24th of June 2025, 6:00amA85 Crianlarich WB - TTL
-
24th of June 2025, 7:00am26th of June 2025, 7:00pmA86 Newtonmore WB - TTL
-
24th of June 2025, 7:00am26th of June 2025, 7:00pmA86 Newtonmore EB - TTL
-
24th of June 2025, 8:00am24th of June 2025, 4:30pmA702 SB West Linton. No Obstruction on Carriageway or Footway
-
24th of June 2025, 8:00am24th of June 2025, 4:30pmA702 NB West Linton. No Obstruction on Carriageway or Footway
-
24th of June 2025, 9:30am24th of June 2025, 3:30pmA828 Achindarroch North of Duror NB - TTL
-
24th of June 2025, 9:30am24th of June 2025, 3:30pmA828 Achindarroch North of Duror SB - TTL
-
24th of June 2025, 9:30am25th of June 2025, 6:00amA85 Comrie Street Crieff EB - Road Closure
-
24th of June 2025, 9:30am24th of June 2025, 3:30pmA702 SB Candy Mill. Portable Traffic Lights.
-
24th of June 2025, 9:30am24th of June 2025, 3:30pmA702 NB Candy Mill. Portable Traffic Lights.
-
24th of June 2025, 7:00pm30th of June 2025, 6:00amA87 Battle of Glenshiel East of Shiel Bridge WB - Road Closure with Amnesties
-
24th of June 2025, 7:00pm30th of June 2025, 6:00amA87 Battle of Glenshiel East of Shiel Bridge EB - Road Closure with Amnesties
-
24th of June 2025, 7:30pm1st of August 2025, 7:30pmA92 S/B River Ore Bridge, Thornton - Contraflow
-
24th of June 2025, 7:30pm1st of August 2025, 7:30pmA92 N/B River Ore Bridge, Thornton - Contraflow
-
24th of June 2025, 7:30pm28th of June 2025, 6:30amA96 Tyrebagger- Convoy W/B
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 WB Jct 27 to 29 - Lane Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 WB Jct 27 off slip - Slip Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 WB Jct 27 on slip - Slip Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 WB Jct 28 off slip - Slip Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 WB Jct 28a to A737 Linwood onslip - Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amA737 SB St James IC to Linclive IC - Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amA737 SB Linclive IC to Barrochan IC offslip Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 EB Jct 15 Stirling Rd On slip Total Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amA737 NB - Linwood to M8 Jct 28a on slip - Slip Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 WB Jct 15 Stirling Rd Off slip Lane Closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amA737 NB - Linwood on slip - Slip closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amA737 NB St James off slip - Slip closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 EB J28a to J27 - L1 closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 EB J28 on slip - Slip closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 EB J27 off slip- slip closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM90 Craigend- Road Closure N/B on slip
-
24th of June 2025, 8:00pm27th of June 2025, 6:00amM74 SB Jct 7 to Burnhead Rd - Lane Closure
-
24th of June 2025, 8:00pm27th of June 2025, 6:00amM74 SB Jct 8 to Jct 9 - Lane Closure
-
24th of June 2025, 8:00pm27th of June 2025, 6:00amM74 SB Jct 8 Onslip - Lane Closure
-
24th of June 2025, 8:00pm26th of June 2025, 6:00amM8 J24/J23 Eastbound - Lane closure
-
24th of June 2025, 8:00pm26th of June 2025, 6:00amM8 J24 EB on slip - Total closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amA8 Eastbound Showcase to Shawhead Main line - Total closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amA8 Eastbound Showcase on-slip - Total closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM74 Southbound Bothwell Services off-slip - Total closure
-
24th of June 2025, 8:00pm25th of June 2025, 6:00amM8 Eastbound Junction 6a Chapelhall off-slip - Total Closure
-
24th of June 2025, 9:30pm25th of June 2025, 6:30amA95 Speybridge- TTLS S/B
-
24th of June 2025, 10:00pm25th of June 2025, 6:00amA77 NB Bellfield Interchange to Grassyards Rd - Road Closure
-
24th of June 2025, 10:00pm25th of June 2025, 6:00amA77 NB Onslip from Bellfield Interchange - Slip Closure
-
25th of June 2025, 8:00am27th of June 2025, 6:00pmA99 Buldoo Latheron NB - TTL
-
25th of June 2025, 8:00am27th of June 2025, 6:00pmA99 Buldoo Latheron SB - TTL
-
25th of June 2025, 8:00am27th of June 2025, 6:00pmA9 Latheron NB - TTL
-
25th of June 2025, 8:00am27th of June 2025, 6:00pmA9 Latheron SB - TTL
-
25th of June 2025, 9:30am29th of June 2025, 11:59pmA76 Cumnock Rd Mauchline NB - No Obs On C/Way / F/Way
-
25th of June 2025, 9:30am29th of June 2025, 11:59pmA76 Cumnock Rd Mauchline SB - No Obs On C/Way / F/Way
-
25th of June 2025, 9:30am25th of June 2025, 3:30pmA9 Dunblane to Greenloaning NB - Diversion signage for local road closure
-
25th of June 2025, 9:30am26th of June 2025, 7:00amA77 Kirkoswald Rd Turnberry SB - TTLS
-
25th of June 2025, 9:30am26th of June 2025, 7:00amA77 Kirkoswald Rd Turnberry NB - TTLS
-
25th of June 2025, 10:00am25th of June 2025, 11:30amA702 - NB - Lamington - TTL's
-
25th of June 2025, 10:00am25th of June 2025, 11:30amA702 - SB - Lamington - TTL's
-
25th of June 2025, 7:30pm27th of June 2025, 6:00amA985 Kincardine Bridge WB. Road Closure
-
25th of June 2025, 7:30pm27th of June 2025, 6:00amA985 Kincardine Bridge EB. Road Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM8 EB Jct 12 On slip Total Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM8 EB Jct 12 Lane Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM8 EB J29 off slip to St James IC - Slip closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM8 EB J29 onslip St James IC - Slip closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 NB Barrochan IC to Linwood IC - Lane Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 NB Kilbarchan IC on slip - Slip Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 NB Barrochan IC On slip Johnstone - Slip Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 NB Barrochan IC Offslip Johnstone -Slip Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 NB Linclive IC Offslip Linwood - Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 SB Linclive Interchange to Kilbarchan Rd- Lane 1 Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 SB Linclive IC onslip Linwood - Slip Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 SB Barrochan IC onslip Johnstone - Slip Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 SB Barrochan IC offslip Johnstone - Slip Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA737 SB Kilbarchan IC off slip - Slip Closure
-
25th of June 2025, 8:00pm27th of June 2025, 6:00amM74 SB Jct 6 on slip from Motherwell - Total closure
-
25th of June 2025, 8:00pm27th of June 2025, 6:00amM74 NB Jct 6 on slip from Motherwell - Total closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM73 N/B J3 Mollinsburn off-slip - Road Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM80 S/B between J3 Hornshill and J2 Robroyston - Road Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM80 S/B J3 Hornshill on-slip - Road Closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA8 Eastbound to A73 Newhouse off-slip - Total closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amA89 / M8 Westbound Junction 8 on-slip - Total closure
-
25th of June 2025, 8:00pm26th of June 2025, 6:00amM8 Westbound Junction 8 off-slip - Total closure
-
25th of June 2025, 10:00pm26th of June 2025, 6:00amM77 SB Jct 8 to A77 Bellfield Interchange- Road Closure
-
25th of June 2025, 10:00pm26th of June 2025, 6:00amA77 SB Onslip from B7038 - Slip Closure
-
25th of June 2025, 10:00pm26th of June 2025, 6:00amA77 SB Onslip from Grassyards Rd- Slip Closure
-
26th of June 2025, 7:00am11th of July 2025, 7:00pmA90 Pert, North Water Bridge- Lane Closure- S/B
-
26th of June 2025, 8:00am10th of July 2025, 6:00pmA90 North Water Bridge SB - Lane closure
-
26th of June 2025, 9:00am26th of June 2025, 4:00pmA835 Braemore - Stop/Go Works
-
26th of June 2025, 9:30am27th of June 2025, 6:00amA90 Myrekirk Rbt, Kingsway West, Dundee. N/B Lane closures
-
26th of June 2025, 7:30pm27th of June 2025, 6:30amA92 Lochgelly SB Off slip SB - Slip road closure
-
26th of June 2025, 7:30pm27th of June 2025, 6:30amA92 Lochgelly - Lane closure S/B
-
26th of June 2025, 7:30pm27th of June 2025, 6:30amA92 Bankhead Roundabout- Road Closure S/B
-
26th of June 2025, 8:00pm4th of July 2025, 6:00amM8 J23- J25 Westbound - Total Closure
-
26th of June 2025, 8:00pm4th of July 2025, 6:00amM8 J24 WB Onslip - Total closure
-
26th of June 2025, 8:00pm4th of July 2025, 6:00amM8 J25 WB Off slip - Total closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 WB - M8 J31 to Woodhall Rbt - Lane Closures
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 WB Onslip from M8 Jct 31 - Lane Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 WB Greenock Road Woodhall Rbt to Newark Rbt - Road Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 WB, Parklea Rd on slip - Slip Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 WB, Parklea Rd off slip - Slip Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 B789 WB Langbank off slip -Slip Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 WB Langbank on slip - Slip Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 EB Greenock Road - Newark Rbt to Woodhall Rbt - Road closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 EB Greenock Road - Woodhall Rbt to West Ferry IC - Lane Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amM8 EB - JCT 31 off slip - lane closures
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 WB Greenock Rd Port Glasgow Mobile lane Closures GG116
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 EB Greenock Rd Port Glasgow Mobile lane Closures GG116
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amM8 WB Jct 31 Westferry Offslip - Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amM8 EB Jct 31 Westferry on slip to M8 EB - Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amM80 N/B between J2 Robroyston and J3 Hornshill - Road Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amM80 N/B J2 Robroyston on-slip - Road Closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amM8 Eastbound Junction 7 Eurocentral off-slip - Total closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amM8 Westbound Junction 7a to A725 Southbound link Road - Total closure
-
26th of June 2025, 8:00pm27th of June 2025, 6:00amA8 Westbound Bargeddie Rbt to Swinton Rbt - Total closure
-
26th of June 2025, 8:30pm28th of June 2025, 6:00amM8 - EB - Jct 4a to jct 4 - road closure
-
26th of June 2025, 8:30pm28th of June 2025, 6:00amM8 - EB - Jct 4a on slip - road closure
-
26th of June 2025, 8:30pm28th of June 2025, 6:00amM8 - EB - Jct 4 off slip - road closure
-
27th of June 2025, 8:00am27th of June 2025, 4:00pmA90 N/B Fordoun - Diversion Signage
-
27th of June 2025, 9:30am27th of June 2025, 3:30pmA702 - SB - Candymill - Temp lights
-
27th of June 2025, 9:30am27th of June 2025, 3:30pmA702 - NB - Candymill - Temp lights
-
27th of June 2025, 9:30am11th of July 2025, 9:00pmA92 Newtonhill- Lane Closure N/B
-
27th of June 2025, 7:30pm28th of June 2025, 6:00amM876 - WB - Jct 2 to 1 - Lane Closure
-
27th of June 2025, 7:30pm28th of June 2025, 6:00amM876 - WB - Jct 2 to 1 - Lane Closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM74 SB Jct 6 on slip from Motherwell - Total Closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM74 NB Jct 6 on slip from Motherwell - Total Closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM74 NB Jct 6 off slips - Total Closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM73 S/B between M80 diverge (J4) and DBFO end - Road Closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM73 S/B J3 Mollinsburn on-slip - Road Closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM80 N/B J7 Haggs on-slip - Road Closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM8 Eastbound Link Road to A89 & M73 high loop - Total closure
-
27th of June 2025, 8:00pm28th of June 2025, 6:00amM8 Westbound Junction 10 off-slip - Total closure
-
28th of June 2025, 8:00am4th of July 2025, 6:00pmA8 WB Main Street Greenock - Works Entirley on the Footpath
-
28th of June 2025, 8:00am28th of June 2025, 5:00pmA90 Emmock Rbt- Div signage N/B
-
28th of June 2025, 10:30pm17th of August 2025, 9:00amA9 Luncarty to Ballinluig NB - Diversion Signage
-
28th of June 2025, 10:30pm17th of August 2025, 9:00amA9 Luncarty to Ballinluig SB - Diversion Signage
-
29th of June 2025, 8:00am29th of June 2025, 5:00pmA85 East High Street Crieff - Vergeworks
-
29th of June 2025, 9:30am29th of June 2025, 3:30pmA77 Bankfield Rbt Glengall SB- TTL
-
29th of June 2025, 9:30am29th of June 2025, 3:30pmA77 Bankfield rbt Glengall NB- TTL
-
29th of June 2025, 7:00pm30th of June 2025, 7:00amA82 South of Invergloy NB - Road Closure with Amnesties
-
29th of June 2025, 7:00pm30th of June 2025, 7:00amA82 South of Invergloy SB - Road Closure with Amnesties
-
29th of June 2025, 7:00pm18th of July 2025, 7:00amA9 Portgower NB - Road Closure with Amnesties
-
29th of June 2025, 7:00pm18th of July 2025, 7:00amA9 Portgower SB - Road Closure with Amnesties
-
29th of June 2025, 7:30pm1st of July 2025, 6:30amA9 Gleneagles- Lane closure S/B
-
29th of June 2025, 8:00pm2nd of July 2025, 6:00amA82 Nevis Rnbt Fort William - Convoy Works
-
29th of June 2025, 8:00pm11th of July 2025, 6:00amA82 NB Prior to Renton at River Leven - Offside Lane Closure
-
29th of June 2025, 8:00pm11th of July 2025, 6:00amA82 SB Prior to Renton at River Leven - Offside Lane Closure
-
30th of June 2025, 12:01am2nd of July 2025, 11:59pmA92 Newport-on-Tay - Div signage S/B
-
30th of June 2025, 6:00am11th of July 2025, 7:00pmA9 Blackford- Div signage N/B
-
30th of June 2025, 7:00am11th of July 2025, 7:00pmA86 Murlaggan East of Roybridge - Convoy Works
-
30th of June 2025, 7:00am11th of July 2025, 7:00pmA85 Dalveich East of Lochernhead WB - TTL
-
30th of June 2025, 7:00am11th of July 2025, 7:00pmA85 Dalveich East of Lochernhead EB - TTL
-
30th of June 2025, 8:00am8th of August 2025, 6:00pmA96 Inverurie EB - Diversion signage for local road closure
-
30th of June 2025, 8:00am4th of July 2025, 5:00pmA90 Glendoick- Div signage S/B
-
30th of June 2025, 8:00am2nd of July 2025, 5:00pmA96 Colpy to B992. Diversion signage for local road closure
-
30th of June 2025, 8:00am5th of September 2025, 5:00pmA77 SB From A751 Innermessan From Beoch Bridge to P&O Cairnryan- TTLS
-
30th of June 2025, 8:00am5th of September 2025, 5:00pmA77 NB From A751 Innermessan From Beoch Bridge to P&O CairnryanTTLS
-
30th of June 2025, 8:30am15th of August 2025, 4:00pmA85 Huntingtower - Diversion Signage
-
30th of June 2025, 9:00am1st of July 2025, 6:00amA90 Errol SB - Diversion signage for local road closure
-
30th of June 2025, 9:00am30th of June 2025, 4:00pmA92 Fernihill, Parbroath- TTL N/B
-
30th of June 2025, 9:30am16th of July 2025, 6:00amA84 Burn of Cambus to Drumvaich North of Doune NB - TTL
-
30th of June 2025, 9:30am16th of July 2025, 6:00amA84 Burn of Cambus to Drumvaich North of Doune SB - TTL
-
30th of June 2025, 9:30am30th of June 2025, 3:30pmM73 Northbound Junction 2a off-slip - Total closure
-
30th of June 2025, 9:30am1st of July 2025, 3:30pmA7 SB Hawick. Stop/Go Boards
-
30th of June 2025, 9:30am1st of July 2025, 3:30pmA7 NB Hawick. Stop/Go Boards
-
30th of June 2025, 9:30am11th of July 2025, 8:00pmA78 Inverkip Rd Greenock NB - TTLS
-
30th of June 2025, 9:30am11th of July 2025, 8:00pmA78 Inverkip Rd Greenock SB - TTLS
-
30th of June 2025, 7:00pm2nd of July 2025, 2:00amA82 Beinn Odhar Auch NB - TTL
-
30th of June 2025, 7:00pm2nd of July 2025, 2:00amA82 Beinn Odhar Auch SB - TTL
-
30th of June 2025, 7:00pm3rd of July 2025, 6:00amA82 Bunloit South of Drumnadrochit NB - Road Closure with Amnesties
-
30th of June 2025, 7:00pm3rd of July 2025, 6:00amA82 Bunloit South of Drumnadrochit SB - Road Closure with Amnesties
-
30th of June 2025, 7:00pm12th of July 2025, 7:00amA84 Craigforth - Convoy Works
-
30th of June 2025, 7:30pm1st of July 2025, 6:30amA90 Kingsway Slip Closure-On slip S/B
-
30th of June 2025, 7:30pm1st of July 2025, 6:30amA90 Kingsway Lane Closure S/B
-
30th of June 2025, 7:30pm2nd of July 2025, 6:00amM9 Junction 7 SB - Lane Closures
-
30th of June 2025, 7:30pm5th of July 2025, 6:00amA1 - SB - Wallyford - Lane Closure
-
30th of June 2025, 7:30pm5th of July 2025, 6:00amA1 - SB - Wallyford Off-slip - Road Closure
-
30th of June 2025, 7:30pm5th of July 2025, 6:00amA1 - SB - Wallyford On-slip - Road Closure
-
30th of June 2025, 7:30pm4th of July 2025, 6:00amM876 - WB - Jct 1 to M80 - Road Closure
-
30th of June 2025, 7:30pm4th of July 2025, 6:00amM876 - WB - Jct 1 on slip - Road Closure
-
30th of June 2025, 7:30pm2nd of July 2025, 6:00amA68 - NB - Fordel Mains Junction to Millerhill Junction - Road Closure
-
30th of June 2025, 7:30pm2nd of July 2025, 6:00amA68 - SB - Fordel Mains Junction to Millerhill Junction - Road Closure
-
30th of June 2025, 8:00pm4th of September 2025, 6:00amM9 - WB - Junction 4 off slip- Road Closure
-
30th of June 2025, 8:00pm4th of September 2025, 6:00amM9 - EB - Junction 4 off slip - Road Closure
-
30th of June 2025, 8:00pm4th of September 2025, 6:00amM9 - EB - Junction 4 on slip - Road Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA77 Doonholm Road EB - CLOSURE
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA77 Doonholm Road WB - CLOSURE
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA77 Corton Road EB - CLOSURE
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA77 Corton Road WB - CLOSURE
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA77 SB Doonholm Road - RIGHT Turn Lane CLOSURE
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA77 NB Corton Road - RIGHT turn lane CLOSURE
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM77 Jct 2 offslip SB - Total Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 EB J26 to J24 - Lane Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 EB J26 off slip - Slip Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 EB J25 off slip - Slip Closure
-
30th of June 2025, 8:00pm8th of July 2025, 6:00amM80 N/B between J2 Robroyston and J7 Haggs - MLC
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 EB J24 off slip - Slip Closure
-
30th of June 2025, 8:00pm8th of July 2025, 6:00amM80 S/B between J7 Haggs and J2 Robroyston - MLC
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 EB J26 on slip - Slip Closure
-
30th of June 2025, 8:00pm8th of July 2025, 6:00amM73 N/B between J3 Mollinsburn and the M73/M80 Merge (J4) - MLC
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 EB J25a on slip - Slip Closure
-
30th of June 2025, 8:00pm8th of July 2025, 6:00amM73 S/B between the M73/M80 Diverge (J4) and J3 Mollinsburn - MLC
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 EB J25 on slip - Slip Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 WB J15 on slip from Springburn Expressway - Slip Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 WB J15 to J16 - Lane Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 WB J16 off slip - Lane closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 WB J16 off slip - Lane closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM80 SB Jct 1 Link Road to M8 WB - Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 WB Jct 13 to Jct 15 - Lane 1 & 2 Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 WB Jct 14 onslip from Viewpark - Slip Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM8 WB Jct 15 offslip to Stirling Road - Slip Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM74 Southbound to M73 Northbound - total closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM73 Northbound Daldowie on-slip - Total closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM73 Northbound Junction 1 to Junction 2 - Nearside & Adjacent lane closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM73 Northbound to M8 Westbound - Total closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA725 Raith Roundabout - Outer ring closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA7071 Northbound toward A725 Raith rbt - Offside lane closure
-
30th of June 2025, 8:00pm2nd of July 2025, 6:00amA96 Tarnash Farm, Sth of Keith. E/B TTL's
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM90 SB Jct 2 off slip - Slip Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM90 - NB - Jct 2 off slip - Road Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA823(M) WB - Road Closure - Pitreavie Rbt to M90 Jct 2
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amA823(M) WB - Road Closure - Pitreavie Rbt to M90 Jct 2
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM9 - WB - Junction 3 to 4 - Road Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM9 - EB - Junction 4 to 3 - Road Closure
-
30th of June 2025, 8:00pm2nd of July 2025, 6:00amA77 Bellfield Interchange - SpittalHill - Total Closure
-
30th of June 2025, 8:00pm2nd of July 2025, 6:00amA77 Grassyards - Bellfield - Lane Closure
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM74 Jct 3 to Jct 2A NB - Road As Part Of Diversion
-
30th of June 2025, 8:00pm1st of July 2025, 6:00amM74 Jct 3 to Jct 2A SB - Road As Part Of Diversion
-
30th of June 2025, 8:30pm2nd of July 2025, 6:00amM8 - EB - Jct 4 to 3a - Road closure
-
30th of June 2025, 8:30pm2nd of July 2025, 6:00amM8 - EB - Jct 4 on slip - Road closure
-
30th of June 2025, 8:30pm2nd of July 2025, 6:00amM8 - EB - Jct 3a off slip - Road closure
-
30th of June 2025, 9:00pm4th of July 2025, 5:00amA75 Palnure NB - TTLS
-
30th of June 2025, 9:00pm4th of July 2025, 5:00amA75 Palnure SB - TTLS
-
30th of June 2025, 9:00pm4th of July 2025, 5:00amA75 Palnure NB - TTLS
-
30th of June 2025, 9:00pm4th of July 2025, 5:00amA75 Palnure SB - TTLS
-
1st of July 2025, 6:00am11th of July 2025, 7:30pmA7-NB-South of Selkirk- TTLs
-
1st of July 2025, 6:00am11th of July 2025, 7:30pmA7-SB-South of Selkirk-TTLs
-
1st of July 2025, 6:01am25th of July 2025, 8:00pmM9 - EB - Junction 4 to 3 - lane closure
-
1st of July 2025, 6:01am25th of July 2025, 8:00pmM9 - WB - Junction 3 to 4 - lane closure
-
1st of July 2025, 7:00am14th of July 2025, 7:00pmA9 Helmsdale SB - TTL
-
1st of July 2025, 7:00am14th of July 2025, 7:00pmA9 Helmsdale NB - TTL
-
1st of July 2025, 8:00am4th of July 2025, 4:00pmA75/A780 EB Rbt to the A75 Drummore Rbt Route Part of Diverson
-
1st of July 2025, 8:00am4th of July 2025, 4:00pmA75/A780 Rbt WB to the A75 Drummore Rbt Route Part tof Diverson
-
1st of July 2025, 9:30am1st of July 2025, 3:30pmM73 Southbound Junction 2a off-slip - Total closure
-
1st of July 2025, 7:30pm2nd of July 2025, 6:30amA90 Kingsway Off slip- Slip Closure S/B
-
1st of July 2025, 7:30pm2nd of July 2025, 6:30amA90 Kingsway Lane Closure S/B
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 Jct 20 West St onslip EB - Total Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 WB Jct 24 - 25 - Lane Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 WB Jct 24 on slip from Helen Street -Slip Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 WB Junction 25 Off Slip To Fifty Pitches Road- Slip Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 WB Jct 25 to Jct 26 on slip - Lane Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 WB Jct 25 On Slip From Fifty Pitches Road - Slip Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 WB Jct 25a Offslip To Braehead - Slip Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM8 WB Jct 26 Offslip - Slip Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amA737 SB Kilbarchan IC to Howwood Road Closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amA737 NB Howwood to Kilbarchan IC Road Closure
-
1st of July 2025, 8:00pm3rd of July 2025, 6:00amA8 Eastbound Baillieston Lights to Swinton Rbt - Progressive nearside & offside lane closures
-
1st of July 2025, 8:00pm3rd of July 2025, 6:00amA8 Westbound Swinton rbt to Baillieston Lights - Progressive Nearside & Offside lane closure
-
1st of July 2025, 8:00pm2nd of July 2025, 6:00amM73 Northbound Junction 2a on-slip - Total closure
-
2nd of July 2025, 8:00am15th of July 2025, 5:00pmA85 Crieff to Comrie - Diversion Signage
-
2nd of July 2025, 9:00am2nd of July 2025, 4:00pmA835 Inchbae - Stop/Go Works
-
2nd of July 2025, 7:00pm9th of July 2025, 7:00amA82 Glencoe - Convoy
-
2nd of July 2025, 7:00pm10th of July 2025, 7:00amA828 Benderloch NB - Road Closure with Amnesties
-
2nd of July 2025, 7:00pm10th of July 2025, 7:00amA828 Benderloch SB - Road Closure with Amnesties
-
2nd of July 2025, 7:30pm3rd of July 2025, 6:00amM876 Kinnaird House to Bowtrees EB- Lane Closures
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 Jct 15 Loop U onslip WB - Total Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 Jct 16 offslip WB - Total Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 Jct 15 to Jct 16 WB- Lane Closures
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 EB Jct 24 to Jct 22 - Lane Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 EB Jct 24 on slip from Helen Street - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 EB Jct 23 on slip from Dumbreck Road - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 EB Jct 22 to M74 Jct 1 - Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 EB Jct 22 to Jct 20 - Lane 1 Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 EB Jct 22 off slip Seaward St - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 WB Jct 22 Seward Street- Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 WB Jct 22 link Road to M77 Merge - Lane 1 Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM80 SB J2 off slip - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM80 NB J2 on slip - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM80 SB J2 on slip - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM80 SB J1 off slip - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM8 WB Jct 26 on slip from Hillington IC - Slip Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM73 Southbound to M74 Northbound Link Road - Total Closure
-
2nd of July 2025, 8:00pm3rd of July 2025, 6:00amM73 Southbound Junction 2 Baillieston on-slip - total closure
-
2nd of July 2025, 8:00pm4th of July 2025, 6:00amM90 Kinross Lane Closure S/B
-
2nd of July 2025, 8:00pm7th of July 2025, 6:00amA82 NB Lomondgate Rbt to Stoneymollan Rbt - Total Closure
-
2nd of July 2025, 8:00pm7th of July 2025, 6:00amA82 NB Off Slip to Renton Rd - Total Closure
-
2nd of July 2025, 8:00pm16th of July 2025, 6:00amA82 SB Stoneymollan Rbt to Lomondgate Rbt - Offside Lane Closure
-
2nd of July 2025, 8:30pm5th of July 2025, 6:00amM8 - EB - Jct 3a to Jct 3 - Road closure
-
2nd of July 2025, 8:30pm5th of July 2025, 6:00amM8 - EB - Jct 3a on slip - Road closure
-
2nd of July 2025, 8:30pm5th of July 2025, 6:00amM8 - EB - Jct 3 off slip - Road closure
-
3rd of July 2025, 8:00am5th of July 2025, 5:00pmA9 Perth- Signage N/B
-
3rd of July 2025, 8:00am5th of July 2025, 5:00pmA9 Aberuthven- Div signage N/B
-
3rd of July 2025, 9:00am3rd of July 2025, 4:00pmA835 Inchbae Lodge - Stop/Go Works
-
3rd of July 2025, 9:30am3rd of July 2025, 3:30pmM73 Northbound Junction 2 on-slip - Total closure
-
3rd of July 2025, 9:30am3rd of July 2025, 3:30pmM73 Southbound Junction 2 off-slip - Total closure
-
3rd of July 2025, 7:30pm10th of July 2025, 6:00amA702 - NB - North of Abington - Road Closure
-
3rd of July 2025, 7:30pm10th of July 2025, 6:00amA702 - SB - North of Abington - Road Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 prior to Jct 12 offslip WB - Hard Shoulder Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 Jct 12 offslip WB - Total Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 Eastbound Junction 6A to Junction 6 Newhouse - Total closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 18 onslip from Charing Cross - Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 16 onslip from Craighall Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 15 onslip from Castle Street - Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 15 onslip from Stirling Road - Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 15 offslip to Springburn Expressway - Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 14 offslip to Viewpark Avenue - Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 18 to Jct 13 - Lane Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 EB Jct 13 Link Road to M80 NB Jct 2 - Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM80 NB Jct 1 on slip from Blochairn Road - Slip Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM80 NB Jct 2 offslip to Robroyston Link Road - Slip Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM73 Northbound Junction 2 off-slip - Total closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 WB Jct 21 onslip from Carnoustie St on slip - Slip Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 WB Jct 21 to Jct 22 Lane 3 & 4 Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 WB M74 Jct 1 - 22 Sec Cway - Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 WB Jct 23 offslip to Dumbreck Road - Slip Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 WB Jct 24 Offslip to Helen Street - Slip Closure
-
3rd of July 2025, 8:00pm4th of July 2025, 6:00amM8 WB Jct 22 - HS Closure
-
3rd of July 2025, 8:00pm8th of July 2025, 6:00amA82 Invermoriston - Convoy Works
-
3rd of July 2025, 8:00pm8th of July 2025, 6:00amA82 SB Stoneymollan Rbt to Lomondgate Rbt - Total Closure
-
3rd of July 2025, 8:00pm8th of July 2025, 6:00amA82 SB Off Slip to Renton Rd - Total Closure
-
3rd of July 2025, 8:00pm8th of July 2025, 6:00amA82 SB On Slip from Renton Rd - Total Closure
-
3rd of July 2025, 8:00pm16th of July 2025, 6:00amA82 NB Lomondgate Rbt to Stoneymollan Rbt - Offside Lane Closure
-
4th of July 2025, 9:00am5th of July 2025, 6:00amA90 Dundee- Lane closure N/B
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM73 Southbound Junction 2a on-slip - Total Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM74 Northbound Junction 5 main line - Offside & adjacent lane closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amA8(M) Baillieston Roundabout - Progressive inner & outer ring closures
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amA8 Swinton to Baillieston Rbt Eastbound - Progressive nearside & offside lane closures
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM73 Southbound Junction 2 off-slip - Progressive nearside & offside lane closures
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM8 Westbound Junction 8 off-slip - Progressive nearside & offside lane closures
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM73 Northbound Junction 2 off-slip - Progressive nearside & offside lane closures
-
4th of July 2025, 8:00pm11th of July 2025, 6:00amM876 - Jct 2 to M9 Jct 8 - EB - ROAD CLOSURE
-
4th of July 2025, 8:00pm11th of July 2025, 6:00amM876 - Jct 2 EB On Slip - EB - ROAD CLOSURE
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM8 WB Jct 15 on slip from Stirling Rd - Slip Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM8 WB Jct 15 to Jct 18 offside and adjacent - Lane Closures
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM8 WB Jct 17 offslip - Slip Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM8 EB Jct 17 onslip from A82 Great Western Road Slip Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM8 EB Prior to Jct 17 on slip to Jct 15 - OSL Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM8 EB Jct 15 off slip to Stirling Road/Castle Street - Slip Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM77 NB Jct 1 to M8 Jct 22- Road Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM77 NB Jct 1 onslip from Dumbreck Road - Slip Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM77 NB Link Road to M8 EB Jct 22 - Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amM77 NB Jct 1 to M8 EB sec c/way- Closure
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amA78 SB Inverkip Road/IBM lane Closures
-
4th of July 2025, 8:00pm5th of July 2025, 6:00amA78 NB Inverkip Road/IBM - Lane Closures
-
5th of July 2025, 1:00pm5th of July 2025, 2:00pmA83 Tarbert - Planned Event Road Closure
-
5th of July 2025, 8:00pm6th of July 2025, 1:00amA90 Dundee- Div signage N/B
-
6th of July 2025, 7:30pm29th of August 2025, 6:30amA90 Rait Junction to Middlebank Farm - Convoy- N/B
-
6th of July 2025, 7:30pm29th of August 2025, 6:30amA90 Rait Junction to Middlebank Farm - Convoy- S/B
-
6th of July 2025, 7:30pm18th of July 2025, 6:30amM90 Broxden- Lane Closure N/B
-
6th of July 2025, 7:30pm18th of July 2025, 6:30amM90 Broxden- Lane Closure S/B
-
6th of July 2025, 8:00pm9th of July 2025, 6:00amM8 J25 WB on slip - Total closure
-
6th of July 2025, 10:30pm8th of July 2025, 5:00amA96 Oyne - Signage only- E/B
-
7th of July 2025, 6:00am10th of July 2025, 8:00pmA76 Main St Kirkconnel NB - TTLS
-
7th of July 2025, 6:00am10th of July 2025, 8:00pmA76 Main St Kirkconnel SB - TTLS
-
7th of July 2025, 6:00am26th of September 2025, 9:00pmA90 N/B Finavon Overbridge - Contraflow
-
7th of July 2025, 6:00am26th of September 2025, 9:00pmA90 S/B Finavon Overbridge - Contraflow
-
7th of July 2025, 7:00am11th of July 2025, 7:00pmA85 Kilmaronaig East of Connel WB - TTL
-
7th of July 2025, 7:00am29th of August 2025, 7:00pmA835 Inchbae WB - TTL
-
7th of July 2025, 7:00am11th of July 2025, 7:00pmA85 Kilmaronaig East of Connel EB - TTL
-
7th of July 2025, 7:00am29th of August 2025, 7:00pmA835 Inchbae EB - TTL
-
7th of July 2025, 7:00am7th of August 2025, 7:00pmA889 Dochaid Abhacain Dalwhinnie SB - TTL
-
7th of July 2025, 7:00am7th of August 2025, 7:00pmA889 Dochaid Abhacain Dalwhinnie NB - TTL
-
7th of July 2025, 7:00am11th of July 2025, 7:00pmA830 Ranochan WB - TTL
-
7th of July 2025, 7:00am11th of July 2025, 7:00pmA830 Ranochan EB - TTL
-
7th of July 2025, 8:00am11th of July 2025, 6:00pmA77 Dalrymple St SB - Road As Part Of Diversion
-
7th of July 2025, 8:00am9th of July 2025, 6:00pmA82 Grotaig South of Drumnadrochit SB - TTL
-
7th of July 2025, 8:00am9th of July 2025, 6:00pmA82 Grotaig South of Drumnadrochit NB - TTL
-
7th of July 2025, 9:00am22nd of August 2025, 5:00pmA76 SB Between Sanquhar & Mennock - Road Part of Diversion
-
7th of July 2025, 9:00am22nd of August 2025, 5:00pmA76 NB Between Sanquhar & Mennock - Road Part of Diversion
-
7th of July 2025, 9:30am11th of July 2025, 3:30pmA985 WB Rosyth. Portable Traffic Lights.
-
7th of July 2025, 9:30am7th of July 2025, 3:30pmA8 Eastbound Showcase off-slip - Total closure
-
7th of July 2025, 9:30am7th of July 2025, 3:30pmA75 WB after Gretna - Advance Signage
-
7th of July 2025, 9:30am7th of July 2025, 3:30pmA8 Eastbound Showcase on-slip - Total closure
-
7th of July 2025, 9:30am7th of July 2025, 3:30pmA75 EB after Gretna - Advance Signage
-
7th of July 2025, 9:30am11th of July 2025, 3:30pmA985 EB Rosyth. Portable Traffic Lights.
-
7th of July 2025, 7:00pm10th of July 2025, 6:00amA9 Murthly Castle Drive South of Dunkeld NB - TTL
-
7th of July 2025, 7:00pm10th of July 2025, 6:00amA9 Murthly Castle Drive South of Dunkeld SB - TTL
-
7th of July 2025, 7:00pm19th of July 2025, 7:00amA82 Stronaba to Letterfindlay NB - TTL
-
7th of July 2025, 7:00pm19th of July 2025, 7:00amA82 Stronaba to Letterfindlay SB - TTL
-
7th of July 2025, 7:30pm9th of July 2025, 6:00amM9 WB Jct 8 to 9. Lane Closure.
-
7th of July 2025, 7:30pm9th of July 2025, 6:00amM9 EB Jct 9 to 8. Lane Closure.
-
7th of July 2025, 7:30pm12th of July 2025, 6:00amA1 - SB - Dolphingstone - Lane Closure
-
7th of July 2025, 7:30pm12th of July 2025, 6:00amA1 - SB - Dolphingstone Off-slip - Road Closure
-
7th of July 2025, 7:30pm12th of July 2025, 6:00amA1 - SB - Dolphingstone On-slip - Road Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM8 EB J30 Craigton off slip - Slip Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 NB Craigton IC to Erskine Bridge - Lane Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 NB off slip to A726 - Slip Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 NB Spectacles on slip - Slip Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 SB Old toll to Jct 30 slips - lane closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 SB A726 off slip safety coning
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 SB onslip from A726 Slip Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 EB off slip to M8 Jct 30 Slip Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM898 WB off slip to M8 Jct 31 Slip Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM8 WB Jct 30 off slip Slip Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amA8 Westbound Newhouse to Chapelhall Soth Rbt - Total Closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amA8 Westbound Newhouse on-slip - Total closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amA8 Chapelhall North to Chapelhall South Rbt link road - total closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amA8 Northbound Bo'ness South Rbt to Chapelhall South Rbt -total closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM74 Northbound to M73 Northbound link road - Total closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM73 Southbound off-slip to Daldowie - Total closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amA725 Raith Roundabout - Inner ring closure
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM74 Jct 3 to Jct 2A NB - Road As Part Of Diversion
-
7th of July 2025, 8:00pm8th of July 2025, 6:00amM74 Jct 3 to Jct 2A SB - Road As Part Of Diversion
-
7th of July 2025, 8:30pm12th of July 2025, 6:00amM8 - EB - Jct 3 to jct 2 - Road Closure
-
7th of July 2025, 8:30pm12th of July 2025, 6:00amM8 - EB - Jct 3 on slip - Road Closure
-
7th of July 2025, 8:30pm12th of July 2025, 6:00amM8 - EB - Jct 2 off slip - Road Closure
-
7th of July 2025, 9:00pm11th of July 2025, 5:00amA68 - NB - Ancrum - Temp lights
-
7th of July 2025, 9:00pm11th of July 2025, 5:00amA68 - SB - Ancrum - Temp lights
-
8th of July 2025, 9:30am11th of July 2025, 3:30pmA96 Colpy- TTL N/B
-
8th of July 2025, 7:00pm15th of July 2025, 7:00amA82 Glengarry Invergarry NB - Road Closure with Amnesties
-
8th of July 2025, 7:00pm15th of July 2025, 7:00amA82 Glengarry Invergarry SB - Road Closure with Amnesties
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA898 NB Erskine Bridge off slip to A82 SB - Total closure
-
8th of July 2025, 8:00pm14th of July 2025, 6:00amA898 SB Erskine Bridge onslip from A82 SB - Total closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amM898 SB on slip from A726 - Total closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amM74 Northbound Junction 3a Daldowie on-slip - Total closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 Raith Roundabout - Outer ring closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amM74 Northbound Junction 5 off-slip - Offside lane closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA8 Westbound Newhouse on-slip - Total closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB E Kilbride Expy Whirlies to Mavor merge - Road closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB C154 Stoneymeadow Rd onslip to A725 - Road closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Mavor to Whirlies merge -Lane closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Whirlies merge to Bothwell bridge - Lane closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Hamilton rd off slip - Slip closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Douglas st off slip - Slip closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Douglas st on slip - Slip closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Main St off slip - Slip closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Main St on slip - Slip closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Glasgow rd on slip - Slip closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Craighead off slip - Slip closure
-
8th of July 2025, 8:00pm9th of July 2025, 6:00amA725 NB Craighead on slip - Slip closure
-
9th of July 2025, 8:00am11th of July 2025, 6:00pmA77 SB Dalrymple St, Girvan - Road Closure
-
9th of July 2025, 8:00am11th of July 2025, 6:00pmA77 SB Dalrymple St, Girvan - Route part of Diversion
-
9th of July 2025, 9:30am9th of July 2025, 3:30pmA83 Cumlodden Church Furnace NB - TTL
-
9th of July 2025, 9:30am9th of July 2025, 3:30pmA83 Cumlodden Church Furnace SB - TTL
-
9th of July 2025, 9:30am9th of July 2025, 4:00pmA84 Strathyre NB - TTL
-
9th of July 2025, 9:30am9th of July 2025, 4:00pmA84 Strathyre SB - TTL
-
9th of July 2025, 7:00pm14th of July 2025, 6:00amA82 Lon Na Fola South of Drumnadrochit NB - Road Closure with Amnesties
-
9th of July 2025, 7:00pm14th of July 2025, 6:00amA82 Lon Na Fola South of Drumnadrochit SB - Road Closure with Amnesties
-
9th of July 2025, 7:00pm14th of July 2025, 5:00amA84 Anie Loch Lubnaig North of Kilmahog - Convoy Works
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Whistleberry to Whirlies slip - Lane Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Whistleberry Rd off slip - Slip Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Glasgow Rd on slip - Slip Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Main Street off slip - Slip Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Main Street on slip - Slip Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Douglas Street off slip - Slip Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Douglas Street on slip - Slip Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB East Kilbride Expressway @ Whirlies off slip - Slip Closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 SB Whirlies Bypass to Whim Place on slip - Lane Closure
-
9th of July 2025, 8:00pm18th of July 2025, 6:00amM8 J25A - J25 Eastbound - Lane closure
-
9th of July 2025, 8:00pm15th of July 2025, 6:00amM8 J25 A EB onlip - Total closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA8 Eastbound Bargeddie Rbt to Showcase - Total Closure
-
9th of July 2025, 8:00pm11th of July 2025, 6:00amM73 Southbound to M74 Southbound - Total closure
-
9th of July 2025, 8:00pm11th of July 2025, 6:00amA721 on-slip to M74 Southbound - Total closure
-
9th of July 2025, 8:00pm10th of July 2025, 6:00amA725 Raith Underpass - Total closure
-
10th of July 2025, 8:00am20th of July 2025, 6:00pmA90 Forfar- Diversion signage N/B
-
10th of July 2025, 8:00am10th of July 2025, 6:00pmA828 Dalnatrat South of Duror NB - TTL
-
10th of July 2025, 8:00am10th of July 2025, 6:00pmA828 Dalnatrat South of Duror SB - TTL
-
10th of July 2025, 9:30am10th of July 2025, 3:30pmA8 Westbound Showcase off-slip - Total closure
-
10th of July 2025, 9:30am10th of July 2025, 3:30pmA8 Westbound Showcase on-slip -Total closure
-
10th of July 2025, 7:00pm18th of July 2025, 7:00amA828 South of Benderloch NB - Road Closure with Amnesties
-
10th of July 2025, 7:00pm18th of July 2025, 7:00amA828 South of Benderloch SB - Road Closure with Amnesties
-
10th of July 2025, 7:30pm24th of July 2025, 6:00amA1-NB-North of Thistly Cross Rbt-Road closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA82 NB Erskine to Dunglass - Lane Closures
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA82 NB off slip to Erskine Bridge - Slip Closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA898 off slip from Erskine Br to A82 NB - Slip Closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA82 NB Old Kilpatrick off slip - Slip Closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA82 NB Old Kilpatrick on slip - Slip Closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA82 SB Great Western Road from Dunglass Rbt to Erskine - Lane Closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA82 SB off slip to Erskine Bridge - Slip Closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA898 SB on slip to A82 SB Slip Closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amA8 Westbound Eurocentral to Shawhead - Total closure
-
10th of July 2025, 8:00pm11th of July 2025, 6:00amM74 Southbound Junction 5 on-slip - Total closure
-
10th of July 2025, 10:00pm11th of July 2025, 6:00amA8 EB Rue End St to Ratho St - Road Part of Diversion
-
10th of July 2025, 10:00pm11th of July 2025, 6:00amA8 WB Rue End St to Ratho St - Road Part of Diversion
-
11th of July 2025, 12:01am24th of July 2025, 11:59pmA9 Queen Vic Jct to Greenloaning. Diversion signage for local road closure
-
11th of July 2025, 6:00am15th of July 2025, 7:30pmA1-NB-North of Thistly Cross Rbt- Lane closure
-
11th of July 2025, 9:30am11th of July 2025, 3:30pmA702 - SB - Duneatonfoot Bridge to Abington INT - TTL's
-
11th of July 2025, 9:30am11th of July 2025, 3:30pmA702 - NB - Duneatonfoot Bridge to Abington INT - TTL's
-
11th of July 2025, 8:00pm11th of August 2025, 6:00amM8 Jct 30 WB off slip to M898 NB - Total Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM74 Northbound Junction 5 on-slip - total closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amA7071 freeflow to M74 Northbound link road - Total closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amA8 Westbound Showcase to Bargeddie Ebt - Total closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J11 off slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amA8 Westbound Showcase on-slip Total closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J12 off slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J13 off slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J12 to J13 - Lane Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J11 on slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J12 on slip - Slip Closure
-
11th of July 2025, 8:00pm11th of August 2025, 6:00amA898/M898 NB Erskine Bridge - Total closure
-
11th of July 2025, 8:00pm11th of August 2025, 6:00amA898 NB Erskine Bridge slip to Great Western Road WB - Total closure
-
11th of July 2025, 8:00pm11th of August 2025, 6:00amA898 NB Erskine Bridge slip to Great Western Road SB- Total closure
-
11th of July 2025, 8:00pm11th of August 2025, 6:00amA898 NB on slip to Erskine Bridge- Total closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 EB J13 onslip - Slip Closure
-
11th of July 2025, 8:00pm11th of August 2025, 6:00amA898 SB Erskine Bridge - Lane Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 EB J13 to J12 - Lane Closure
-
11th of July 2025, 8:00pm11th of August 2025, 6:00amA898 SB on slip to Erskine Bridge - Total Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 EB J12 off slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 EB J11 off slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 EB J11 on slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 EB J10 off slip - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM74 Jct 6 Off Slip to Hamilton SB - Road As Part Of Diversion
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM74 Jct 6 On Slip to Hamilton NB - Road As Part Of Diversion
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J29 off slip to St James IC - Slip Closure
-
11th of July 2025, 8:00pm12th of July 2025, 6:00amM8 WB J29 on slip St James IC - Slip Closure
-
11th of July 2025, 8:30pm23rd of July 2025, 6:00amA720 - WB - Sheriffhall to Lasswade - Closure
-
11th of July 2025, 8:30pm23rd of July 2025, 6:00amA720 - WB - Gilmerton Slip - Closure
-
12th of July 2025, 7:00pm1st of December 2025, 6:00amA9 Cromarty Bridge - Convoy Works
-
13th of July 2025, 7:30pm25th of July 2025, 6:30amM90 Mawcarse- Lane Closure N/B
-
14th of July 2025, 7:00am15th of July 2025, 7:00pmA86 Craigbeg Moy - Convoy Works
-
14th of July 2025, 8:00am18th of July 2025, 7:00pmA68 - NB - B6400 Jct - Utility works diversion - Signage only
-
14th of July 2025, 8:00am18th of July 2025, 7:00pmA68 - SB - B6400 Jct - Utility works diversion - Signage only
-
14th of July 2025, 8:00am25th of July 2025, 5:00pmA85 Main Street Crieff - Diversion Signage
-
14th of July 2025, 9:30am14th of July 2025, 3:30pmA78 Greenock Rd Largs SB - TTLS
-
14th of July 2025, 9:30am14th of July 2025, 3:30pmA78 Greenock Rd Largs NB - TTLS
-
14th of July 2025, 9:30am14th of July 2025, 3:30pmA83 Furnace NB - TTL
-
14th of July 2025, 9:30am14th of July 2025, 3:30pmA83 Furnace SB - TTL
-
14th of July 2025, 7:00pm19th of July 2025, 4:00amA9 Clashmore NB - TTL
-
14th of July 2025, 7:00pm19th of July 2025, 4:00amA9 Clashmore SB - TTL
-
14th of July 2025, 7:30pm20th of July 2025, 6:30amA90 Fowlis Junction, Invergowrie. N/B lane 1 closure
-
14th of July 2025, 7:30pm20th of July 2025, 6:30amC12 Fowlis Road, Invergowrie. N/B council road closure
-
14th of July 2025, 7:30pm19th of July 2025, 6:00amA1 - SB - Bankton - Lane Closure
-
14th of July 2025, 7:30pm19th of July 2025, 6:00amA1 - SB - Bankton Off-slip - Road Closure
-
14th of July 2025, 7:30pm19th of July 2025, 6:00amA1 - SB - Bankton On-slip - Road Closure
-
14th of July 2025, 8:00pm15th of July 2025, 6:00amM74 SB Jct 7 to Jct 8 - Road closure
-
14th of July 2025, 8:00pm15th of July 2025, 6:00amM74 SB Jct 8 off slip - road closure
-
14th of July 2025, 8:00pm15th of July 2025, 6:00amM74 NB Jct 8 to Jct 7 - Road Closure
-
14th of July 2025, 8:00pm15th of July 2025, 6:00amM74 NB Jct 8 on slip - Slip Closure
-
14th of July 2025, 8:00pm19th of July 2025, 6:00amM8 J18 EB Off slip to A804 - Total Closure
-
14th of July 2025, 8:00pm19th of July 2025, 6:00amM8 J18 EB off slip to A82 GWR - Total closure
-
14th of July 2025, 8:00pm19th of July 2025, 6:00amM8 J19 - J18 EB - lane closure
-
14th of July 2025, 8:00pm19th of July 2025, 6:00amM8 J19 EB on slip from North Street- Total Closures
-
14th of July 2025, 8:00pm19th of July 2025, 6:00amA92 Balfarg. S/B TTL's
-
14th of July 2025, 8:00pm17th of July 2025, 7:00amM9 - EB - Newbridge - Hard Shoulder Closure
-
14th of July 2025, 8:00pm17th of July 2025, 6:00amM9 - WB - Newbridge - Hard Shoulder Closure
-
14th of July 2025, 8:30pm15th of July 2025, 6:00amM8 - EB - Jct 2 on slip - Road closure
-
14th of July 2025, 8:30pm15th of July 2025, 6:00amM8 - EB - Jct 2 to jct 1 - Road closure
-
14th of July 2025, 8:30pm15th of July 2025, 6:00amM8 - EB - Jct 1 off slip - Road closure
-
14th of July 2025, 8:30pm23rd of August 2025, 6:00amM8 - WB - Jct 3 to Jct 2. Lane Closures
-
14th of July 2025, 8:30pm23rd of August 2025, 6:00amM8 - EB - Jct 2 to Jct 3. Lane Closures
-
15th of July 2025, 8:00am17th of July 2025, 6:00pmA75 EB Valleyfield to Ringford - Route part of Diversion
-
15th of July 2025, 8:00am17th of July 2025, 6:00pmA75 WB Valleyfield to Ringford - Route part of Diversion
-
15th of July 2025, 8:00am15th of July 2025, 7:00pmA9 Bankfoot to Ballinluig NB - Diversion Signage
-
15th of July 2025, 8:00am15th of July 2025, 7:00pmA9 Bankfoot to Ballinluig SB - Diversion Signage
-
15th of July 2025, 8:00pm16th of July 2025, 6:00amM74 SB J1a off slip - Slip Closure
-
15th of July 2025, 8:00pm16th of July 2025, 6:00amM74 SB J1a onslip - Slip Closure
-
15th of July 2025, 8:00pm16th of July 2025, 6:00amM74 NB J2 off slip - Slip Closure
-
15th of July 2025, 8:00pm16th of July 2025, 6:00amM74 NB J2 on slip - Slip Closure
-
15th of July 2025, 8:00pm16th of July 2025, 6:00amM74 SB Jct 2a off slip Slip Closure
-
15th of July 2025, 8:00pm16th of July 2025, 6:00amM74 SB Jct 2a on slip Slip Closure
-
15th of July 2025, 8:00pm17th of July 2025, 6:00amM90 - NB - M9 Jct 1a - M90 Jct 1a - Road Closure
-
15th of July 2025, 8:00pm17th of July 2025, 6:00amA90 - NB - Jct 1 -- Road Closure
-
15th of July 2025, 8:00pm17th of July 2025, 6:00amM90 - NB - Jct 1a off slip - Road Closure
-
16th of July 2025, 7:00pm17th of July 2025, 4:00amA9 Alness NB - TTL
-
16th of July 2025, 7:00pm17th of July 2025, 4:00amA9 Alness SB - TTL
-
16th of July 2025, 7:00pm25th of July 2025, 6:00amA86 Rubha Na Magach to Moy Lodge East of Moy EB - Road Closure with Amnesties
-
16th of July 2025, 7:00pm25th of July 2025, 6:00amA86 Rubha Na Magach to Moy Lodge East of Moy WB - Road Closure with Amnesties
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 SB Jct 6 combined slip from Motherwell - Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 SB Jct 6 from Motherwell on slip - Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 NB Jct 6 from Motherwell on Slip - -Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 NB Jct 6 off slip - Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 NB Jct 6 off slip to Hamilton - Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 NB Jct 6 off slip to Motherwell - Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 NB Jct 11 on slip Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 NB Jct 10 off slip Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 SB Jct 10 on slip Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 SB Jct 11 off slip - Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 SB J7 off slip - Slip Closure
-
16th of July 2025, 8:00pm17th of July 2025, 6:00amM74 NB J7 on slip - Slip Closure
-
17th of July 2025, 8:00am17th of July 2025, 5:00pmA96 Huntly- Div signage W/B
-
17th of July 2025, 7:00pm23rd of July 2025, 4:00amA82 Rossdhu House South of Luss NB - TTL
-
17th of July 2025, 7:00pm23rd of July 2025, 4:00amA82 Rossdhu House South of Luss SB - TTL
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 Jct 6 On Slip NB from Hamilton - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 Jct 6 NB from Hamilton to M74 - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 Jct 6 SB from Hamilton to M74 - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 Jct 6 Off Slip SB - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 Jct 6 off slip to Hamilton SB - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 Jct 6 off slip to Motherwell SB - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 SB J9 off slip - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 NB J3 off slip - Slip Closure
-
17th of July 2025, 8:00pm18th of July 2025, 6:00amM74 SB J3 on slip - Slip Closure
-
18th of July 2025, 8:00pm19th of July 2025, 6:00amM74 NB J10 to J8 - Road Closure
-
18th of July 2025, 8:00pm19th of July 2025, 6:00amM74 NB J10 on slip - Slip Closure
-
18th of July 2025, 8:00pm19th of July 2025, 6:00amM74 NB J8 off slip - Slip Closure
-
18th of July 2025, 8:00pm19th of July 2025, 6:00amM74 SB J8 to J10 - Road Closure
-
18th of July 2025, 8:00pm19th of July 2025, 6:00amM74 SB J8 on slip - Slip Closure
-
18th of July 2025, 8:00pm19th of July 2025, 6:00amM74 SB J9 off slip - Slip Closure
-
19th of July 2025, 8:00am20th of July 2025, 5:00pmA9 Broom of Dalreoch - Diversion signage- N/B
-
19th of July 2025, 10:00pm22nd of July 2025, 6:00amA85 Cruachan EB - TTL
-
19th of July 2025, 10:00pm22nd of July 2025, 6:00amA85 Cruachan WB - TTL
-
20th of July 2025, 7:00pm25th of July 2025, 7:00amA82 Glen Orchy Junction South of Bridge of Orchy NB - Road Closure with Amnesties
-
20th of July 2025, 7:00pm25th of July 2025, 7:00amA82 Glen Orchy Junction South of Bridge of Orchy NB - Road Closure with Amnesties
-
20th of July 2025, 7:30pm8th of August 2025, 6:30amM90 Bridge of Earn- Lane Closure N/B
-
20th of July 2025, 7:30pm8th of August 2025, 6:30amM90 Bridge of Earn- Lane Closure S/B
-
20th of July 2025, 7:30pm8th of August 2025, 6:30amM90 Craigend- Lane Closure N/B
-
20th of July 2025, 7:30pm8th of August 2025, 6:30amM90 Craigend- Lane Closure S/B
-
20th of July 2025, 10:30pm24th of July 2025, 5:00amA96 Blackburn- Signage only- W/B
-
21st of July 2025, 7:00am22nd of August 2025, 7:00pmA85 Lix Toll WB - TTL
-
21st of July 2025, 7:00am22nd of August 2025, 7:00pmA85 Lix Toll EB - TTL
-
21st of July 2025, 7:00pm26th of July 2025, 7:00amA82 Bunloit to Grotaig South of Drumnadrochit NB - TTL
-
21st of July 2025, 7:00pm26th of July 2025, 7:00amA82 Bunloit to Grotaig South of Drumnadrochit SB - TTL
-
21st of July 2025, 7:30pm25th of July 2025, 6:30amA9 Cairney Braes, Broom of Dalreoch- Lane Closure S/B
-
21st of July 2025, 7:30pm26th of July 2025, 6:00amA1 - SB - Gladsmuir - Lane Closure
-
21st of July 2025, 7:30pm26th of July 2025, 6:00amA1 - SB - Gladsmuir Off-slip - Road Closure
-
21st of July 2025, 7:30pm26th of July 2025, 6:00amA1 - SB - Gladsmuir On-slip - Road Closure
-
21st of July 2025, 8:00pm24th of July 2025, 6:00amM77 NB Jct 5 - 4 - Total closure
-
21st of July 2025, 8:00pm24th of July 2025, 6:00amM77 NB Jct 5 onslip - Total closure
-
21st of July 2025, 8:00pm24th of July 2025, 6:00amM77 NB Jct 6-5 - Lane Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 SB J2 off slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 SB J2 on slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 NB J1a off slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 NB J1a on slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 NB J2a on slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 NB 2a off slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 NB J1 off slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM74 SB J1 on slip - Slip Closure
-
21st of July 2025, 8:00pm22nd of July 2025, 6:00amM8 Kingston Br EB- Lane 1 closure
-
21st of July 2025, 8:30pm23rd of July 2025, 6:00amA720 - WB - Lothianburn WB Onslip - Road Closure
-
21st of July 2025, 8:30pm23rd of July 2025, 6:00amA720 - WB - Lothianburn Mainline - Road Closure
-
22nd of July 2025, 10:45am22nd of July 2025, 11:15amA83 Inveraray - Event Road Closure
-
22nd of July 2025, 8:00pm23rd of July 2025, 6:00amM8 EB Approach to Kingston Br - Lane Closures
-
22nd of July 2025, 8:00pm23rd of July 2025, 6:00amM8 WB on to Kingston Br - Lane Closure
-
22nd of July 2025, 8:00pm23rd of July 2025, 6:00amM74 SB J1 off slip - Lane Closure
-
22nd of July 2025, 8:00pm23rd of July 2025, 6:00amM8 Hillington Rbt inner - lane closure
-
22nd of July 2025, 8:00pm23rd of July 2025, 6:00amM74 Jct 1 SB-Lane 2 closure
-
22nd of July 2025, 8:00pm23rd of July 2025, 6:00amM74 Jct 1 NB-Lane 2 closure
-
23rd of July 2025, 9:30am23rd of July 2025, 3:30pmA85 Methven EB - TTL
-
23rd of July 2025, 9:30am23rd of July 2025, 3:30pmA85 Methven WB - TTL
-
23rd of July 2025, 7:00pm25th of July 2025, 7:00amA82 Inverarnan NB - TTL
-
23rd of July 2025, 7:00pm25th of July 2025, 7:00amA82 Inverarnan SB - TTL
-
23rd of July 2025, 7:30pm30th of July 2025, 6:00amA702 - SB - Hillend Junction to Easter Howgate - Road Closure
-
23rd of July 2025, 8:30pm30th of July 2025, 6:00amM8 - EB - Jct 4 on slip - Closure
-
23rd of July 2025, 8:30pm31st of July 2025, 6:00amA720 - WB - Baberton mainline - Road Closure
-
23rd of July 2025, 8:30pm31st of July 2025, 6:00amA720 - WB - Dreghorn onslip - Road Closure
-
23rd of July 2025, 8:30pm31st of July 2025, 6:00amA720 - WB - Baberton off slip - Road Closure
-
23rd of July 2025, 8:30pm31st of July 2025, 6:00amA720 - WB - Calder off slip - Road Closure
-
23rd of July 2025, 8:30pm31st of July 2025, 6:00amA720 - WB - Hermiston off slip - Road Closure
-
23rd of July 2025, 8:30pm30th of July 2025, 6:00amM8 - WB - Jct 3a on slip - Closure
-
23rd of July 2025, 8:30pm30th of July 2025, 6:00amM8 - EB - Jct 4 to 3A - Closure
-
23rd of July 2025, 8:30pm30th of July 2025, 6:00amM8 - WB - Jct 3a to Jct 4 - Closure
-
24th of July 2025, 8:00am1st of August 2025, 6:00pmA90 Glendoick Signage S/B
-
24th of July 2025, 7:30pm30th of July 2025, 6:00amA702 - NB - Easter Howgate to Hillend Junction - Road Closure
-
25th of July 2025, 8:01pm26th of July 2025, 6:00amM9 - EB - Junction 3 to 4 - Road Closure
-
26th of July 2025, 6:01am4th of September 2025, 8:00pmM9 - WB - Junction 4 to 3 Contraflow
-
26th of July 2025, 6:01am4th of September 2025, 8:00pmM9 - EB - Junction 3 to 4- Contraflow
-
26th of July 2025, 8:00pm25th of August 2025, 6:00amA898 NB Erskine Bridge - Lane Closure
-
26th of July 2025, 8:00pm25th of August 2025, 6:00amA898 SB Erskine Bridge - Lane Closure
-
27th of July 2025, 7:00pm30th of July 2025, 6:00amA86 Inverpattack Lodge Kinloch Laggan WB - Road Closure with Amnesties
-
27th of July 2025, 7:00pm30th of July 2025, 6:00amA86 Inverpattack Lodge Kinloch Laggan EB - Road Closure with Amnesties
-
28th of July 2025, 7:00am1st of August 2025, 7:00pmA85 St Fillans WB - TTL
-
28th of July 2025, 7:00am1st of August 2025, 7:00pmA85 St Fillans EB - TTL
-
28th of July 2025, 9:00am31st of July 2025, 4:00pmA9 Skelbo to Balvaid North of Dornoch - Stop/Go Works
-
28th of July 2025, 7:30pm2nd of August 2025, 6:00amA1 - SB - Oaktree - Lane Closure
-
28th of July 2025, 7:30pm2nd of August 2025, 6:00amA1 - SB - Oaktree Off-slip - Road Closure
-
28th of July 2025, 7:30pm2nd of August 2025, 6:00amA1 - SB - Oaktree On-slip - Road Closure
-
28th of July 2025, 8:00pm29th of July 2025, 6:00amA1 - NB - Old Cambus - Convoy
-
28th of July 2025, 8:00pm29th of July 2025, 6:00amA1 - SB - Old Cambus - Convoy
-
28th of July 2025, 8:00pm5th of August 2025, 6:00amA82 Kinghouse Hotel NB - TTL
-
28th of July 2025, 8:00pm5th of August 2025, 6:00amA82 Kinghouse Hotel SB - TTL
-
29th of July 2025, 6:00am31st of July 2025, 7:30pmA7-NB-South of Hawick to Parkdaill-TTLs
-
29th of July 2025, 6:01am8th of August 2025, 8:00pmA1 - NB - Old Cambus - Temp Lights
-
29th of July 2025, 6:01am8th of August 2025, 8:00pmA1 - SB - old Cambus - Temp Lights
-
29th of July 2025, 8:00am1st of August 2025, 6:00pmA90 Glendoick- Div sigange S/B
-
29th of July 2025, 8:00am11th of August 2025, 5:00pmA9 Dunblane- Div signage S/B
-
29th of July 2025, 8:00am11th of August 2025, 5:00pmA9 Dunblane- Div signage N/B
-
29th of July 2025, 9:30am29th of July 2025, 4:00pmA76 Auchinleck SB - TTLS
-
29th of July 2025, 9:30am29th of July 2025, 4:00pmA76 Auchinleck NB - TTLS
-
29th of July 2025, 7:30pm1st of August 2025, 6:00amA7-NB-South of Hawick-Road closure
-
29th of July 2025, 7:30pm1st of August 2025, 6:00amA7-SB-South of Hawick-Road closure
-
29th of July 2025, 7:30pm15th of August 2025, 6:00amA7 - NB - North of Linhope - Road closure
-
29th of July 2025, 7:30pm15th of August 2025, 6:00amA7 - SB - North of Linhope - Road closure
-
29th of July 2025, 9:25pm1st of August 2025, 5:15amA85 Bridge of Awe EB - TTL
-
29th of July 2025, 9:25pm1st of August 2025, 5:15amA85 Bridge of Awe WB - TTL
-
30th of July 2025, 6:00am31st of July 2025, 7:30pmA7-SB-South of Hawick to Parkdaill-TTLs
-
30th of July 2025, 6:00am5th of August 2025, 7:30pmA7 - NB - North of Linhope - TTLs
-
30th of July 2025, 6:00am5th of August 2025, 7:30pmA7 - SB - North of Linhope - TTLs
-
30th of July 2025, 7:00pm6th of August 2025, 6:00amA86 Kinloch Laggan WB - Road Closure with Amnesties
-
30th of July 2025, 7:00pm6th of August 2025, 6:00amA86 Kinloch Laggan EB - Road Closure with Amnesties
-
30th of July 2025, 7:00pm13th of August 2025, 6:00amM9 - EB - Jct 7 - Hard Shoulder Closure
-
30th of July 2025, 7:00pm13th of August 2025, 6:00amM876 - EB - Jct 7 - Slip Road Lane Closure
-
30th of July 2025, 8:00pm2nd of August 2025, 6:00amA82 NB Between Stoneymollan & Lomondgate Rbts - Road Closure
-
30th of July 2025, 8:00pm2nd of August 2025, 6:00amA82 SB Between Stoneymollan & Lomondgate Rbts - Total Closure
-
31st of July 2025, 8:00pm7th of August 2025, 6:00amA90 - NB - Dalmeny - Road Closure
-
31st of July 2025, 8:00pm7th of August 2025, 6:00amA90 - NB - Craigiehall Onslip - Road Closure
-
31st of July 2025, 8:00pm7th of August 2025, 6:00amA90 - NB - Dalmeny Off Slip - Road Closure
-
1st of August 2025, 7:30pm14th of August 2025, 6:00amA7-NB-North of Hawick-Road Closure
-
1st of August 2025, 7:30pm14th of August 2025, 6:00amA7-SB-North of Hawick-Road Closure
-
3rd of August 2025, 7:00pm6th of August 2025, 7:00amA830 Arienskill East of Lochailort WB - Road Closure with Amnesties
-
3rd of August 2025, 7:00pm6th of August 2025, 7:00amA830 Arienskill East of Lochailort EB - Road Closure with Amnesties
-
3rd of August 2025, 7:30pm22nd of August 2025, 6:30amM90 Glenfarg- Lane Closure N/B
-
3rd of August 2025, 7:30pm22nd of August 2025, 6:30amM90 Glenfarg- Lane Closure S/B
-
4th of August 2025, 6:00am8th of August 2025, 7:30pmA7-NB-North of Hawick-TTLs
-
4th of August 2025, 6:00am8th of August 2025, 7:30pmA7-SB-North of Hawick-TTLs
-
4th of August 2025, 7:00am15th of August 2025, 7:00pmA726 Queensway WB - Road As Part Of Diversion
-
4th of August 2025, 7:00am15th of August 2025, 7:00pmA726 Queensway EB - Road As Part Of Diversion
-
4th of August 2025, 8:00am13th of August 2025, 4:00pmA92 Portlethen. Diversion for N/B off slip closure
-
4th of August 2025, 8:00am7th of August 2025, 5:00pmA977 - NB - Longannet Rdbt to Kilbagie Rdbt - Stop and Go
-
4th of August 2025, 8:00am7th of August 2025, 5:00pmA977 - SB - Longannet Rdbt to Kilbagie Rdbt - Stop and Go
-
4th of August 2025, 7:00pm20th of August 2025, 6:00amA9 North of Glenaldie Jnct Tain - Convoy Works
-
4th of August 2025, 7:30pm5th of August 2025, 6:30amA90 Forfar to Bogindollo- Lane Closure N/B
-
4th of August 2025, 7:30pm7th of August 2025, 6:00amA876 - EB - Higgins Neuk Roundabout - Road Closure
-
4th of August 2025, 7:30pm7th of August 2025, 6:00amA823(M) - WB - Road Closure
-
4th of August 2025, 7:30pm7th of August 2025, 6:00amA823(M) - WB - Road Closure
-
4th of August 2025, 7:30pm7th of August 2025, 6:00amA823(M) - EB - Road Closure
-
4th of August 2025, 7:30pm7th of August 2025, 6:00amA823(M) - EB - Road Closure
-
4th of August 2025, 7:30pm9th of August 2025, 6:00amA1 - SB - Abbotsview - Lane Closure
-
4th of August 2025, 8:00pm5th of August 2025, 6:00amM77 SB Jct 4 to Ayr Rd - Total Closure
-
4th of August 2025, 8:00pm5th of August 2025, 6:00amM77 SB Jct 3 - 4 - Lane Closure
-
5th of August 2025, 8:00pm6th of August 2025, 6:00amA90 Glendoick Off slip closure N/B
-
5th of August 2025, 8:00pm6th of August 2025, 6:00amA90 Glendoick On slip closure N/B
-
5th of August 2025, 8:00pm6th of August 2025, 6:00amA90 Glendoick Lane closure N/B
-
5th of August 2025, 8:00pm6th of August 2025, 6:00amM77 Jct 2 - Jct 1 NB - Total Closure
-
5th of August 2025, 8:00pm6th of August 2025, 6:00amM77 Jct 2 NB Onslip - Total Closure
-
5th of August 2025, 8:00pm6th of August 2025, 6:00amM77 Jct 1 NB Offslip - Total Closure
-
5th of August 2025, 8:00pm6th of August 2025, 6:00amM77 NB Prior to Jct 2 - Lane closure
-
5th of August 2025, 10:00pm6th of August 2025, 6:00amM8 - EB - Jct3 to Jct 2 - Lane closure
-
6th of August 2025, 6:00am7th of August 2025, 8:00pmA9000/FRB SB. Contraflow.
-
6th of August 2025, 6:00am7th of August 2025, 8:00pmA9000/FRB NB. Contraflow.
-
6th of August 2025, 7:00pm12th of August 2025, 7:00amA830 Ranochan Loch Eilt WB - Road Closure with Amnesties
-
6th of August 2025, 7:00pm12th of August 2025, 7:00amA830 Ranochan Loch Eilt EB - Road Closure with Amnesties
-
6th of August 2025, 7:00pm8th of August 2025, 6:00amA86 Pattack Falls West of Strathmashie WB - Road Closure with Amnesties
-
6th of August 2025, 7:00pm8th of August 2025, 6:00amA86 Pattack Falls West of Strathmashie EB - Road Closure with Amnesties
-
6th of August 2025, 7:30pm8th of August 2025, 6:00amM9 - SB - Jct 11 - Jct 9 - Closure
-
6th of August 2025, 7:30pm8th of August 2025, 6:00amM9 - SB - Jct 10 - Off Slip Closure
-
6th of August 2025, 7:30pm7th of August 2025, 6:00amM9 - NB - Jct 9 - Jct 11 - Closure
-
6th of August 2025, 7:30pm8th of August 2025, 6:00amM9 - NB - Jct 10- On Slip Closure
-
6th of August 2025, 7:30pm8th of August 2025, 6:00amM9 - NB - Jct 9- On Slip Closure
-
6th of August 2025, 7:30pm10th of October 2025, 6:00amM9 - NB - Jct 10- On Slip Closure
-
6th of August 2025, 7:30pm7th of August 2025, 6:00amA1 - SB - Abbotsview Off-slip - Road Closure
-
6th of August 2025, 7:30pm9th of August 2025, 6:00amA1 - SB - Abbotsview On-slip - Road Closure
-
6th of August 2025, 8:00pm7th of August 2025, 6:00amA92 NB Lochgelly- off slip Closure
-
6th of August 2025, 8:00pm8th of August 2025, 6:00amM9 - SB - Jct 9 - Off Slip Closure
-
6th of August 2025, 10:00pm7th of August 2025, 6:00amM8 - WB - Jct 2 to Jct 3 - Lane closure
-
7th of August 2025, 7:00am29th of August 2025, 6:00pmA985 - EB - Admiralty to Higgins Neuk Rdbt - Stop Go
-
7th of August 2025, 7:00am29th of August 2025, 6:00pmA985 - WB - Admiralty to Higgins Neuk Rdbt - Stop Go
-
7th of August 2025, 8:00pm14th of August 2025, 6:00amM876 WB Junction 2 On-Slip closure
-
7th of August 2025, 8:00pm14th of August 2025, 6:00amM876 - WB - Jct 2 - lane closure
-
7th of August 2025, 8:00pm8th of August 2025, 6:00amA90 NB - Lane Closure - Jct 1
-
7th of August 2025, 8:00pm8th of August 2025, 6:00amA90 NB - PTL closure - Jct 1
-
7th of August 2025, 10:00pm8th of August 2025, 6:00amM8 - EB - Jct 3 to Jct 2 - Lane closure
-
7th of August 2025, 10:00pm8th of August 2025, 6:00amM8 - WB - Jct 2 to Jct 3 - Lane closure
-
8th of August 2025, 8:00pm11th of August 2025, 6:00amM9 - EB - Newbridge - Hard Shoulder Closure
-
8th of August 2025, 8:00pm11th of August 2025, 6:00amM9 - WB - Newbridge - Hard Shoulder Closure
-
8th of August 2025, 8:00pm9th of August 2025, 6:00amM9 - EB - Junction 4 to 3 - Road Closure
-
10th of August 2025, 7:00pm14th of August 2025, 6:00amA86 Tulloch West of Roughburn EB - Road Closure with Amnesties
-
10th of August 2025, 7:00pm14th of August 2025, 6:00amA86 Tulloch West of Roughburn WB - Road Closure with Amnesties
-
10th of August 2025, 7:30pm5th of September 2025, 6:30amA92 Cowdenbeath to Denburn Br - NB Lane 2 closures
-
10th of August 2025, 7:30pm5th of September 2025, 6:30amA92 Denburn Br to Cowdenbeath - SB Lane 2 closures
-
11th of August 2025, 6:00am29th of August 2025, 6:00pmM74 SB Jct 9 Off Slip - Hard Shoulder Closure
-
11th of August 2025, 9:00am13th of August 2025, 4:00pmA92 Portlethen. N/B off slip closure
-
11th of August 2025, 9:30am15th of August 2025, 3:30pmA1 S/B Thistly Cross Roundabout. Lane Closure
-
11th of August 2025, 8:00pm12th of August 2025, 6:00amA77 NB Whitlets to Sandyford - Road closure
-
11th of August 2025, 8:00pm12th of August 2025, 6:00amA77 NB Sandyford to Dutchhouse - Road closure
-
11th of August 2025, 8:00pm12th of August 2025, 6:00amA77 SB Dutchhouse to Sandyford - Road Closure
-
11th of August 2025, 8:00pm12th of August 2025, 6:00amA77 SB Sandyford to Whitletts - Road Closure
-
11th of August 2025, 8:00pm12th of August 2025, 6:00amA78 NB Dutchhouse to Monktonhead - Lane1 Closure
-
11th of August 2025, 8:00pm12th of August 2025, 6:00amA78 SB Monktonhead to Dutchhouse - Lane Closure
-
11th of August 2025, 8:00pm12th of August 2025, 6:00amA82 NB Stirling Road Greenhead Road - Round Riding Road- Lane Closures
-
11th of August 2025, 8:00pm15th of August 2025, 4:30amM9 - NB - Grangemouth - Slip Closure
-
11th of August 2025, 9:00pm23rd of August 2025, 6:00amA82 Fort Augustus - Aberchalder SB - TTL
-
11th of August 2025, 9:00pm23rd of August 2025, 6:00amA82 Fort Augustus - Aberchalder NB - TTL
-
12th of August 2025, 8:00am8th of September 2025, 5:00pmA95 Mulben- TTLS N/B
-
12th of August 2025, 9:30am15th of August 2025, 3:30pmA96 Elgin- TTLS W/B
-
12th of August 2025, 7:00pm20th of August 2025, 7:00amA830 Loch Eil Side Station East of Kinlocheil WB - Road Closure with Amnesties
-
12th of August 2025, 7:00pm20th of August 2025, 7:00amA830 Loch Eil Side Station East of Kinlocheil EB - Road Closure with Amnesties
-
12th of August 2025, 8:00pm13th of August 2025, 6:00amA77 NB Dutchouse Rbt to Bellfield IC - Closure
-
12th of August 2025, 8:00pm13th of August 2025, 6:00amA77 NB Symington off slip - Closure
-
12th of August 2025, 8:00pm13th of August 2025, 6:00amA77 NB Symington on slip - Closure
-
12th of August 2025, 8:00pm13th of August 2025, 6:00amA77 NB Bogend off slip - Closure
-
12th of August 2025, 8:00pm13th of August 2025, 6:00amA77 NB Bogend on slip - Closure
-
12th of August 2025, 8:00pm13th of August 2025, 6:00amA77 NB Spitallhill off slip - Closure
-
12th of August 2025, 8:00pm13th of August 2025, 6:00amA77 NB Bellfield IC off slip - Closure
-
12th of August 2025, 8:00pm14th of August 2025, 6:00amA82 NB Dumbarton Road - Greenhead Road - Lane Closures
-
12th of August 2025, 8:00pm14th of August 2025, 6:00amA82 SB Greenhead Road Dumbarton Road- Lane Closures
-
12th of August 2025, 8:00pm14th of August 2025, 6:00amA82 SB Stirling Road - Round Riding Road - Greenhead Road - Lane Closures
-
13th of August 2025, 8:00pm14th of August 2025, 6:00amA77 NB Bellfield IC to Meiklewood - Closure
-
13th of August 2025, 8:00pm14th of August 2025, 6:00amA77 NB Bellfield IC on slip - Closure
-
13th of August 2025, 8:00pm14th of August 2025, 6:00amA77 NB Grassyards off slip - Closure
-
13th of August 2025, 8:00pm14th of August 2025, 6:00amA77 NB Grassyards on slip - Closure
-
13th of August 2025, 8:00pm14th of August 2025, 6:00amA77 NB Meiklewood off slip - road closure
-
13th of August 2025, 8:00pm14th of August 2025, 4:30amM9 - NB - Grangemouth - lane Closure
-
14th of August 2025, 7:00pm20th of August 2025, 6:00amA86 Tullochrome West of Kinloch Laggan EB - Road Closure with Amnesties
-
14th of August 2025, 7:00pm20th of August 2025, 6:00amA86 Tullochrome West of Kinloch Laggan WB - Road Closure with Amnesties
-
14th of August 2025, 7:30pm20th of August 2025, 6:00amA7-NB-North of Ashkirk-Road closure
-
14th of August 2025, 7:30pm19th of August 2025, 6:00amA7-SB-North of Ashkirk-Road closure
-
14th of August 2025, 7:30pm16th of August 2025, 6:00amM9 - SB - Jct 11 - Jct 9 - Closure
-
14th of August 2025, 7:30pm16th of August 2025, 6:00amM9 - SB - Jct 10 - Off Slip Closure
-
14th of August 2025, 7:30pm16th of August 2025, 6:00amM9 - NB - Jct 9 - Jct 11 - Closure
-
14th of August 2025, 7:30pm16th of August 2025, 6:00amM9 - NB - Jct 10- On Slip Closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - WB - Jct 9 to Jct 11 - Road closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - WB - Jct 9 on slip - slip closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM80 - WB - Jct 9 on slip - slip closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - WB - Jct 10 off slip - slip closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - WB - Jct 10 on slip - slip closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - EB - Jct 11 to Jct 9 - Road closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - EB - Jct 10 off slip - Road closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - EB - Jct 10 on slip - Road closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM9 - EB - Jct 9 on slip - Road closure
-
14th of August 2025, 8:00pm16th of August 2025, 6:00amM80 - EB - Jct 9 - Road closure
-
14th of August 2025, 8:00pm18th of October 2025, 6:00amM80 - WB - Jct 9 on slip - slip closure
-
14th of August 2025, 8:00pm15th of August 2025, 6:00amA77 SB - Meiklewood to Bellfield IC - Closure
-
14th of August 2025, 8:00pm15th of August 2025, 6:00amA77 SB - Meiklewood on slip Closure
-
14th of August 2025, 8:00pm15th of August 2025, 6:00amA77 SB - Grassyards off slip - Closure
-
14th of August 2025, 8:00pm15th of August 2025, 6:00amA77 SB - Grassyards on slip - Closure
-
14th of August 2025, 8:00pm15th of August 2025, 6:00amA77 SB - Bellfield IC off slip - Closure
-
14th of August 2025, 8:00pm19th of August 2025, 6:00amA82 SB Stirling Rd at Milton - Lane Closure
-
14th of August 2025, 8:00pm19th of August 2025, 6:00amA82 NB Stirling Rd at Milton - Lane Closure
-
15th of August 2025, 7:00pm16th of August 2025, 6:30amA985 - EB - Limekilns - Road Closure
-
15th of August 2025, 7:00pm16th of August 2025, 6:30amA985 - WB - Limekilns - Road Closure
-
15th of August 2025, 7:30pm19th of August 2025, 6:30amA985 - Layby - Crombie - Closure
-
15th of August 2025, 7:30pm19th of August 2025, 6:30amA985 - WB - Crombie - Road Closure
-
15th of August 2025, 7:30pm19th of August 2025, 6:30amA985 - EB - Crombie - Road Closure
-
15th of August 2025, 8:00pm16th of August 2025, 6:00amA77 SB - Bellfield IC to Dutchouse Rbt - Road Closure
-
15th of August 2025, 8:00pm16th of August 2025, 6:00amA77 SB - Bellfield IC on slip - Slip Closure
-
15th of August 2025, 8:00pm16th of August 2025, 6:00amA77 SB - Spitalhill on slip - Slip Closure
-
15th of August 2025, 8:00pm16th of August 2025, 6:00amA77 SB - Bogend off slip Tarbolton Road - Slip Closure
-
15th of August 2025, 8:00pm16th of August 2025, 6:00amA77 SB - Bogend on slip Tarbolton Road - Slip Closure
-
15th of August 2025, 8:00pm16th of August 2025, 6:00amA77 SB - Symington off slip - Slip Closure
-
15th of August 2025, 8:00pm16th of August 2025, 6:00amA77 SB - Symington on slip - Slip Closure
-
16th of August 2025, 8:30pm23rd of August 2025, 6:00amM8 - EB - Jct 4 on slip - Closure
-
16th of August 2025, 8:30pm23rd of August 2025, 6:00amM8 - WB - Jct 3a on slip - Closure
-
16th of August 2025, 8:30pm23rd of August 2025, 6:00amM8 - EB - Jct 4 to 3A - Closure
-
16th of August 2025, 8:30pm23rd of August 2025, 6:00amM8 - WB - Jct 3a to Jct 4 - Closure
-
17th of August 2025, 8:00am31st of October 2025, 8:00amA985 WB Kincardine Bridge. Portable Traffic Lights
-
17th of August 2025, 8:00am31st of October 2025, 8:00amA985 EB Kincardine Bridge. Portable Traffic Lights
-
17th of August 2025, 7:00pm19th of August 2025, 5:00amA85 West of Ross Bridge Comrie WB - Road Closure with Amnesties
-
17th of August 2025, 7:00pm19th of August 2025, 5:00amA85 West of Ross Bridge Comrie EB - Road Closure with Amnesties
-
17th of August 2025, 7:00pm3rd of September 2025, 6:00amA9 Luncarty NB - Convoy Works
-
17th of August 2025, 7:00pm6th of September 2025, 6:00amA9 Luncarty NB Off Slip - Full Slip Closure
-
17th of August 2025, 7:00pm6th of September 2025, 6:00amA9 Luncarty NB On Slip - Full Slip Closure
-
18th of August 2025, 8:00pm22nd of August 2025, 4:30amM8- EB- On Slip - Hard Shoulder closure - Newbridge
-
18th of August 2025, 8:00pm22nd of August 2025, 4:30amM8- EB- Onslip - lane 1 closure - Newbridge
-
18th of August 2025, 8:00pm8th of September 2025, 6:00amM8 WB Jct 29 Onslip - Slip Closure
-
18th of August 2025, 8:00pm20th of August 2025, 6:00amM876 - EB - M80 to Jct 2 - Road Closure
-
18th of August 2025, 8:00pm20th of August 2025, 6:00amM876 - EB - Jct 1 - Slip Road Closure
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA78 SB Montfode Rbt to Chapelhill Rbt - Road Closure
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA78 SB Chapelhill Rbt to Sharphill Rbt - Road Closure
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA78 SB Sharphill Rbt to Pennyburn Rbt -Road Closure
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA78 SB Pennyburn Rbt to Eglinton IC Road Closure
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA78 SB Eglinton off slip - Slip Closure
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA76 Newbridge SB- TTL
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA76 Newbridge NB- TTL
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA75 Ramhill WB-TTL
-
18th of August 2025, 8:00pm19th of August 2025, 6:00amA75 Ramhill EB-TTL
-
18th of August 2025, 8:00pm20th of August 2025, 6:00amM876 - EB - M80 to Jct 2 - Road Closure
-
18th of August 2025, 8:00pm20th of August 2025, 6:00amM876 - EB - Jct 1 - Slip Road Closure
-
19th of August 2025, 7:30pm20th of August 2025, 6:00amA985 - EB - West of Cairneyhill - Road Closure
-
19th of August 2025, 7:30pm20th of August 2025, 6:00amA985 - WB - West of Cairneyhill - Road Closure.
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA78 NB Onslip Irvine Bypass Slip Closure
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA78 NB Eglinton IC to Pennyburn Rbt - Road Closure
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA78 NB Pennyburn Rbt to Sharphill Rbt - Road Closure
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA78 NB Sharphill Rbt to Chapelhill Rbt - Road Closure
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA78 NB Chapelhill Rbt to Montfode Rbt - Road closure
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA75 Creebridge WB- TTL
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA75 Creebridge EB- TTL
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA75 Shennanton WB- TTL
-
19th of August 2025, 8:00pm20th of August 2025, 6:00amA75 Shennanton EB- TTL
-
20th of August 2025, 8:00am8th of September 2025, 6:00pmA887 Torgyle West of Dundreggan EB - TTL
-
20th of August 2025, 8:00am8th of September 2025, 6:00pmA887 Torgyle West of Dundreggan WB - TTL
-
20th of August 2025, 7:00pm1st of September 2025, 7:00amA830 Mhuidhe East West of Glenfinnan WB - Road Closure with Amnesties
-
20th of August 2025, 7:00pm1st of September 2025, 7:00amA830 Mhuidhe East West of Glenfinnan EB - Road Closure with Amnesties
-
20th of August 2025, 7:00pm3rd of September 2025, 7:00amA9 Dalmore - Convoy Works
-
20th of August 2025, 7:00pm3rd of September 2025, 6:00amA86 Meall Doire Roybridge WB - Road Closure with Amnesties
-
20th of August 2025, 7:00pm3rd of September 2025, 6:00amA86 Meall Doire Roybridge EB - Road Closure with Amnesties
-
20th of August 2025, 7:30pm21st of August 2025, 6:00amA985 - EB - Gowerfield Crossroads - Road Closure
-
20th of August 2025, 7:30pm21st of August 2025, 6:00amA985 - WB - Gowerfield Crossroads - Road Closure
-
20th of August 2025, 7:30pm27th of August 2025, 6:00amA1 - Wallyford to old craighall - Northbound - Closure
-
20th of August 2025, 7:30pm27th of August 2025, 6:00amA1 - Wallyford on slip - Northbound - Closure
-
20th of August 2025, 7:30pm27th of August 2025, 6:00amA1 - Old Craighall - Northbound - Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amM876 - WB - Jct 1 - Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amM8 WB Jct 29 St James IC to 29a Lane Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amM8 EB Jct 29a Bishopton to Jct 29 Lane Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 NB - Monktonhead Rbt to Meadowhead Rbt - Road closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 NB - Loans off slip - Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 NB - Loans on slip - Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 NB - Barassie off slip - Slip closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 SB Eglinton IC to Meadowhead Rbt -Road Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 SB Eglinton IC on slip - Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 SB Warrix IC off slip - Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 SB Warrix IC on slip - Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 SB Newhouse off slip- Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amA78 SB Newhouse IC on slip - Slip Closure
-
20th of August 2025, 8:00pm21st of August 2025, 6:00amM876 - WB - Jct 1 - Slip Closure
-
21st of August 2025, 8:00am21st of August 2025, 5:00pmA92 Cupar- Signage S/B
-
21st of August 2025, 7:30pm23rd of August 2025, 6:00amA985 - EB - Devilla Forest - Closure
-
21st of August 2025, 7:30pm23rd of August 2025, 6:00amA985 - WB - Devilla Forest - Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 NB Meadowhead Rbt to Eglinton IC - Road Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 NB Newhouse offslip - Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 NB Newhouse IC onslip - Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 NB Warrix IC off slip - Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 NB Warrix IC on slip - Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 SB Meadowhead Rbt to Monktonhead Rbt- Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 SB Auchengate Onslip - Slip Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 SB Loans off slip - Slip Closure
-
21st of August 2025, 8:00pm22nd of August 2025, 6:00amA78 SB Loans on slip - Slip Closure
-
22nd of August 2025, 8:00am4th of September 2025, 5:00pmA830 Back of Keppoch West of Arisaig to Morar - Diversion Signage
-
22nd of August 2025, 8:00pm23rd of August 2025, 6:00amA82 S/B Renton On Slip - Total Closure
-
22nd of August 2025, 8:00pm23rd of August 2025, 6:00amA82 S/B Renton Off Slip - Total Closure
-
22nd of August 2025, 8:00pm23rd of August 2025, 6:00amA82 NB Barloan to Stoneymollan Rbt - Total Closure
-
22nd of August 2025, 8:00pm23rd of August 2025, 6:00amA82 NB offslip to Renton Rd - Total Closure
-
22nd of August 2025, 8:00pm23rd of August 2025, 6:00amA82 S/B Stoneymollan to Barloan – Total Closure
-
23rd of August 2025, 7:00am8th of December 2025, 6:30amA96 Keith to Fochabers. Diversion signage for local road closure
-
23rd of August 2025, 12:00pm23rd of August 2025, 2:00pmA95 Granish Jct SB - Event - Road Closure
-
24th of August 2025, 7:30pm5th of September 2025, 6:30amA90 Bullionfield NB - Lane closure
-
24th of August 2025, 7:30pm5th of September 2025, 6:30amA90 Bullionfield SB - Lane closure
-
25th of August 2025, 9:30am29th of August 2025, 3:30amA9 Gleneagles. S/B lane 1 closure
-
25th of August 2025, 8:00pm26th of August 2025, 6:00amA82 S/B Stoneymollan to Barloan – Total Closure
-
25th of August 2025, 8:00pm26th of August 2025, 6:00amA82 S/B Renton On Slip - Total Closure
-
25th of August 2025, 8:00pm26th of August 2025, 6:00amA82 S/B Renton Off Slip - Total Closure
-
25th of August 2025, 8:00pm26th of August 2025, 6:00amM77 SB Jct 4 off slip - Lane Closure
-
25th of August 2025, 8:00pm26th of August 2025, 6:00amA82 NB Barloan to Stoneymollan Rbt - Total Closure
-
25th of August 2025, 8:00pm26th of August 2025, 6:00amA82 NB offslip to Renton Rd - Total Closure
-
26th of August 2025, 8:00am26th of August 2025, 5:00pmA90 Forfar- Diversion signage- S/B
-
26th of August 2025, 9:00am9th of September 2025, 3:00pmA9 Inveralmond- Signage only- S/B
-
26th of August 2025, 9:00am5th of September 2025, 3:00pmA85 Perth to Gilmerton - Diversion Signage
-
26th of August 2025, 9:00am5th of September 2025, 3:00pmA9 Perth to Ballinluig NB - Diversion Signage
-
26th of August 2025, 9:00am5th of September 2025, 3:00pmA9 Perth to Ballinluig SB - Diversion Signage
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 WB Jct 27 to 29 - Lane Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 WB Jct 27 off slip - Slip Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 WB Jct 27 on slip - Slip Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 WB Jct 28 of slip - Slip Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 WB Jct 28a to A737 Linwood onslip - Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amA737 SB St James IC to Linclive IC - Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amA737 SB Linclive IC to Barrochan IC offslip Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amA737 NB - Linwood to M8 Jct 28a on slip - Slip Closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amA737 NB - Linwood on slip - Slip closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amA737 NB St James off slip - Slip closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 EB J28a to J27 - L1 closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 EB J28 on slip - Slip closure
-
26th of August 2025, 8:00pm27th of August 2025, 6:00amM8 EB J27 off slip- slip closure
-
26th of August 2025, 8:30pm29th of August 2025, 6:00amM8 WB Junction 4 Whitburn to 4A Off-Slip
-
26th of August 2025, 8:30pm29th of August 2025, 6:00amM8 WB Junction 4A Off-Slip
-
26th of August 2025, 8:30pm29th of August 2025, 6:00amM8 WB Junction 4 On-Slip
-
27th of August 2025, 8:00am27th of August 2025, 5:00pmA9 Crossgates- Signage only- S/B
-
27th of August 2025, 9:30am10th of September 2025, 3:30pmA96 Nairn TTL W/B
-
27th of August 2025, 7:30pm30th of August 2025, 6:00amA1 - NB - Old Craighall Roundabout - Lane Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amM8 EB J29 off slip to St James IC - Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amM8 EB J29 onslip St James IC - Slip closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 NB Barrochan IC to Linwood IC - Lane Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 NB Kilbarchan IC on slip - Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 NB Barrochan IC On slip Johnstone - Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 NB Barrochan IC Offslip Johnstone -Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 NB Linclive IC Offslip Linwood - Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 SB Linclive Interchange to Kilbarchan Rd- Lane Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 SB Linclive IC onslip linwood - Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 SB Barrochan IC onslip Johnstone - Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 SB Barrochan IC offslip Johnstone - Slip Closure
-
27th of August 2025, 8:00pm28th of August 2025, 6:00amA737 SB Kilbarchan IC off slip - Slip Closure
-
27th of August 2025, 8:00pm29th of August 2025, 6:00amM74 SB Jct 9 Off Slip - Slip Closure
-
27th of August 2025, 8:30pm30th of August 2025, 6:00amA1 - NB - Old Craighall Offslip - Road Closure
-
27th of August 2025, 8:30pm30th of August 2025, 6:00amA1 - NB - Old Craighall Mainline - Road Closure
-
27th of August 2025, 8:30pm30th of August 2025, 6:00amA1 - SB - Old Craighall SB Offslip - Lane Closure
-
27th of August 2025, 8:30pm30th of August 2025, 6:00amA720 - EB - Old Craighall Approach - Lane Closure
-
27th of August 2025, 8:30pm30th of August 2025, 6:00amA1 - SB - Old Craighall Approach - Lane Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 WB - M8 J31 to Woodhall Rbt - Lane Closures
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amM8 WB onslip from J31 - Lane Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 WB Greenock Road Woodhall Rbt to Newark Rbt - Road Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 WB, Parklea Rd on slip - Slip Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 WB, Parklea Rd off slip - Slip Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 B789 WB Langbank off slip -Slip Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 WB Langbank on slip - Slip Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 EB Greenock Road - Newark Rbt to Woodhall Rbt - Road closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 EB Greenock Road - Woodhall Rbt to West Ferry IC - Lane Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amM8 EB - JCT 31 off slip - lane closures
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 WB Greenock Rd Port Glasgow - Mobile Lane Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amA8 EB Greenock Rd Port Glasgow - Mobile Lane Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amM8 WB Jct 31 Westferry Offslip - Closure
-
28th of August 2025, 8:00pm29th of August 2025, 6:00amM8 EB Jct 31 Westferry on slip to M8 EB - Closure
-
29th of August 2025, 9:30am29th of August 2025, 3:30pmA78 SB St Phillans to Netherhall - Route part of Diversion
-
29th of August 2025, 9:30am29th of August 2025, 3:30pmA78 NB St Phillans to Netherhall - Route part of Diversion
-
31st of August 2025, 7:00pm9th of September 2025, 7:00amA87 Bun Loyne WB - Road Closure
-
31st of August 2025, 7:00pm9th of September 2025, 7:00amA87 Bun Loyne EB - Road Closure
-
31st of August 2025, 7:30pm10th of October 2025, 6:30amA90 St Madoes to Glendoick - Lane Closure N/B
-
31st of August 2025, 7:30pm10th of October 2025, 6:30amA90 St Madoes to Glendoick - Lane Closure S/B
-
1st of September 2025, 12:00am19th of December 2025, 6:00amM9 WB Jct 1B to 4. Lane Closure
-
1st of September 2025, 12:00am19th of December 2025, 6:00amM9 EB Jct 4 to 1B. Lane Closure
-
1st of September 2025, 12:00am19th of December 2025, 6:00amM9 WB Jct 1B to 4. Hard Shoulder Closure
-
1st of September 2025, 12:00am19th of December 2025, 6:00amM9 EB Jct 4 to 1B. Hard Shoulder Closure
-
1st of September 2025, 7:00am21st of December 2025, 7:00pmA9 River Spey Bridge North of Kingussie NB - TTL
-
1st of September 2025, 7:00am21st of December 2025, 7:00pmA9 River Spey Bridge North of Kingussie SB - TTL
-
1st of September 2025, 8:00am12th of September 2025, 5:00pmA78 Irvine Rd Largs SB - TTLS
-
1st of September 2025, 8:00am12th of September 2025, 5:00pmA78 Irvine Rd Largs NB - TTLS
-
1st of September 2025, 8:00am3rd of October 2025, 6:00pmA82 Glen Falloch Inverarnan NB - TTL
-
1st of September 2025, 8:00am3rd of October 2025, 6:00pmA82 Glen Falloch Inverarnan SB - TTL
-
1st of September 2025, 9:00am1st of September 2025, 4:00pmA86 Biallidbeg West of Newtonmore - Stop/Go Works
-
1st of September 2025, 9:00am4th of September 2025, 5:00pmA95 Haughs Road, Keith - TTL's
-
1st of September 2025, 9:30am1st of September 2025, 3:30pmA77 Main Rd Kirkoswald SB - TTLS
-
1st of September 2025, 9:30am1st of September 2025, 3:30pmA77 Main Rd Kirkoswald NB - TTLS
-
1st of September 2025, 9:30am1st of September 2025, 3:30pmA78 Castle Kennedy to Glenluce EB - Road As Part Of Diversion
-
1st of September 2025, 9:30am1st of September 2025, 3:30pmA78 Castle Kennedy to Glenluce WB - Road As Part Of Diversion
-
1st of September 2025, 9:30am1st of September 2025, 3:30pmA78 Skelmorlie NB - TTLS
-
1st of September 2025, 9:30am1st of September 2025, 3:30pmA78 Skelmorlie SB - TTLS
-
1st of September 2025, 7:00pm30th of September 2025, 7:00amA9 Jubilee Bridge North of Dunkeld NB - TTL
-
1st of September 2025, 7:00pm30th of September 2025, 7:00amA9 Jubilee Bridge North of Dunkeld SB - TTL
-
1st of September 2025, 7:00pm4th of September 2025, 7:00amA830 Collie Chreag East of Ranochan WB - Road Closure with Amnesties
-
1st of September 2025, 7:00pm4th of September 2025, 7:00amA830 Collie Chreag East of Ranochan EB - Road Closure with Amnesties
-
1st of September 2025, 7:30pm2nd of September 2025, 6:00amM9 EB Jct 4 to 1B. Road Closure
-
1st of September 2025, 7:30pm13th of September 2025, 6:00amA1 - SB - Old Craighall to River Esk - Road Closure
-
1st of September 2025, 7:30pm13th of September 2025, 6:00amA1 - SB - Old Craighall Offslip - Road Closure
-
1st of September 2025, 7:30pm13th of September 2025, 6:00amA1 - SB - Old Craighall Onslip - Road Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 EB J26 to J24 - Lane Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 EB J26 off slip - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 EB J25 off slip - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 EB J24 off slip - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 EB J26 on slip - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 EB J25a on slip - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 EB J25 on slip - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 WB J15 on slip from Springburn Expressway - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 WB J15 to J16 - Lane Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM80 SB Jct 1 Link Road to M8 WB - Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 WB Jct 13 to Jct 15 - Lane 1 & 2 Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM8 WB Jct 15 offslip to Stirling Road - Slip Closure
-
1st of September 2025, 8:00pm2nd of September 2025, 6:00amM9 WB Jct 1 to 1A. Closure
-
1st of September 2025, 8:30pm3rd of September 2025, 6:00amM8 - EB - Jct 6 on slip - Road Clsoure
-
1st of September 2025, 8:30pm3rd of September 2025, 6:00amM8 - EB - Jct 6 - 5 - Road Clsoure
-
1st of September 2025, 8:30pm3rd of September 2025, 6:00amM8 - EB - Jct 5 off slip - Closure
-
1st of September 2025, 8:30pm18th of September 2025, 6:00amM8 - WB - Jct 2 to Jct 3 - Road Closure
-
1st of September 2025, 8:30pm18th of September 2025, 6:00amM8 - WB - Junction 2 WB On-slip - Road Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM8 WB Jct 24 - 25 - Lane Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM8 WB Jct 24 on slip from Helen Street -Slip Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM8 WB Junction 25 Off Slip - Slip Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM8 WB Jct 25 to Jct 26 - Lane Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM8 WB Jct 25 On Slip - Slip Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM8 WB Jct 25a Offslip To Braehead - Slip Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM8 WB Jct 26 Offslip - Slip Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amA737 SB Kilbarchan IC to Howwood Road Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amA737 NB Howwood to Kilbarchan IC Road Closure
-
2nd of September 2025, 8:00pm3rd of September 2025, 6:00amM9 WB Jct 1 on-slip. Closure.
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM9 WB Jct 1A off-slip. Closure.
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM90 SB Jct 1 to M9 Jct 1A WB. Closure
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM9 WB Jct 1B off-slip. Closure
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM9 WB Jct 1A to Jct 4 . Closure
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM9 WB Jct 1B on-slip . Closure
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM9 WB Jct 2 on-slip . Closure
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM9 WB Jct 4 off-slip . Closure
-
2nd of September 2025, 8:00pm5th of September 2025, 6:00amM9 WB Jct 3 off-slip . Closure
-
3rd of September 2025, 9:00am3rd of September 2025, 4:00pmA86 Creagdhu East of Balgowan - Stop/Go Works
-
3rd of September 2025, 9:30am5th of September 2025, 3:30pmA85 Dollerie Terrace to Leadenflower Street Crieff - Diversion Signage
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 EB Jct 24 to Jct 22 - Lane Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 EB Jct 24 on slip from Helen Street - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 EB Jct 23 on slip from Dumbreck Road - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 EB Jct 22 to M74 Jct 1 - Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 EB Jct 22 to Jct 20 - Lane 1 Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 EB Jct 22 off slip Seaward St - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 WB Jct 22 Seward Street- Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 WB Jct 22 link Road to M77 Merge - Lane 1 Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM80 SB J2 off slip - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM80 NB J2 on slip - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM80 SB J2 on slip - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM80 SB J1 off slip - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM8 WB Jct 26 on slip from Hillington IC - Slip Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM9 - EB - Junction 4 to 3 - Road Closure
-
3rd of September 2025, 8:00pm4th of September 2025, 6:00amM9 - WB - Junction 3 to 4 - Road Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 18 onslip from Charing Cross - Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 16 onslip from Craighall Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 15 onslip from Castle Street - Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 15 onslip from Stirling Road - Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 15 offslip to Springburn Expressway - Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 14 offslip to Viewpark Avenue - Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 18 to Jct 13 - Lane Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 EB Jct 13 Link Road to M80 NB Jct 2 - Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM80 NB Jct 1 on slip from Blochairn Road - Slip Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM80 NB Jct 2 offslip to Robroyston Link Road - Slip Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 WB Jct 21 onslip from Carnoustie St on slip - Slip Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 WB Jct 21 to Jct 22 Lane 3 & 4 Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 WB M74 Jct 1 - 22 Sec Cway - Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 WB Jct 23 offslip to Dumbreck Road - Slip Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 WB Jct 24 Offslip to Helen Street - Slip Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM8 WB Jct 22 - HS Closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM9 - WB - Junction 3 to 4 - lane closure
-
4th of September 2025, 8:00pm5th of September 2025, 6:00amM9 - EB - Junction 4 to 3 - lane closure
-
5th of September 2025, 8:00am7th of September 2025, 5:00pmA96 Church Rd, Keith. W/B TTL's
-
5th of September 2025, 8:00pm8th of September 2025, 6:00amM9 - EB - Newbridge - Hard Shoulder Closure
-
5th of September 2025, 8:00pm8th of September 2025, 6:00amM9 - WB - Newbridge - Hard Shoulder Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM9 WB Jct 4 to Jct 5 . Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM9 WB Jct 4 on-slip. Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM9 WB Jct 5 off-slip. Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM8 WB Jct 15 on slip from Stirling Rd - Slip Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM8 WB Jct 15 to Jct 18 offside and adjacent - Lane Closures
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM8 WB Jct 17 offslip - Slip Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM8 EB Jct 17 onslip from A82 Great Western Road - Slip Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM8 EB Prior to Jct 17 on slip to Jct 15 - OSL Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM8 EB Jct 15 off slip to Stirling Road/Castle Street - Slip Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM77 NB Jct 1 to M8 Jct 22- Road Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM77 NB Jct 1 onslip from Dumbreck Road - Slip Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM77 NB Link Road to M8 EB Jct 22 - Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amM77 NB Jct 1 to M8 EB sec c/way- Closure
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amA78 SB Inverkip Road - Lane Closures
-
5th of September 2025, 8:00pm6th of September 2025, 6:00amA78 NB Inverkip Road - Lane Closures
-
7th of September 2025, 7:00am15th of September 2025, 7:00pmA86 Laggan - Convoy Works
-
7th of September 2025, 7:00pm10th of September 2025, 7:00amA828 Lettermore South of Ballachulish SB - Road Closure with Amnesties
-
7th of September 2025, 7:00pm10th of September 2025, 7:00amA828 Lettermore South of Ballachulish NB - Road Closure with Amnesties
-
8th of September 2025, 8:00am30th of January 2026, 6:00pmA95 Aberlour NB - Temporary traffic signals
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB Jct 14 onslip from Viewpark - Slip Closure
-
8th of September 2025, 8:00pm10th of September 2025, 6:00amM9 WB Jct 5 to Jct 7. Closure
-
8th of September 2025, 8:00pm10th of September 2025, 6:00amM9 WB Jct 5 on-slip. Closure
-
8th of September 2025, 8:00pm10th of September 2025, 6:00amM9 WB Jct 6 on-slip. Closure
-
8th of September 2025, 8:00pm10th of September 2025, 6:00amM9 WB Jct 7 off-slip. Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J11 off slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J12 off slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J13 off slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J12 to J13 - Lane Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J11 on slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J12 on slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 EB J13 onslip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 EB J13 to J12 - Lane Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 EB J12 off slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 EB J11 off slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 EB J11 on slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 EB J10 off slip - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J29 off slip to St James IC - Slip Closure
-
8th of September 2025, 8:00pm9th of September 2025, 6:00amM8 WB J29 on slip St James IC - Slip Closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Whirlies merge to Bothwell bridge - Lane closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Hamilton rd off slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Douglas st off slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Douglas st on slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Main St off slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Main St on slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Glasgow Road on slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Craighead off slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Craighead on slip - Slip closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB E Kilbride Expy Whirlies to Mavor merge - Road closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB C154 Stoneymeadow Rd onslip to A725 - Road closure
-
9th of September 2025, 8:00pm10th of September 2025, 6:00amA725 NB Mavor to Whirlies merge -Lane closure
-
10th of September 2025, 7:00am23rd of September 2025, 7:00pmA82 Highbridge South of Spean Bridge - Convoy Works
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Whistleberry to Whirlies slip - Lane Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Whistleberry Rd off slip - Slip Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Glasgow Rd on slip - Slip Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Main Street off slip - Slip Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Main Street on slip - Slip Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Douglas Street off slip - Slip Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Douglas Street on slip - Slip Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB East Kilbride Expressway @ Whirlies off slip - Slip Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amA725 SB Whirlies Bypass to Whim Place on slip - Lane Closure
-
10th of September 2025, 8:00pm11th of September 2025, 6:00amM9 WB Jct 7 to Jct 8. Lane Closures
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA82 NB Erskine to Dunglass - Lane Closures
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA82 NB off slip to Erskine Bridge - Slip Closure
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA898 off slip from Erskine Br to A82 NB - Slip Closure
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA82 NB Old Kilpatrick off slip - Slip Closure
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA82 NB Old Kilpatrick on slip - Slip Closure
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA82 SB Great Western Road from Dunglass Rbt to Erskine - Lane Closure
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA82 SB off slip to Erskine Bridge - Slip Closure
-
11th of September 2025, 8:00pm12th of September 2025, 6:00amA898 SB on slip to A82 SB Slip Closure
-
11th of September 2025, 8:00pm16th of September 2025, 6:00amM9 WB Jct 8 to Jct 9. Closure.
-
11th of September 2025, 8:00pm16th of September 2025, 6:00amM9 WB Jct 9 off-slip. Closure.
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM8 EB J30 Craigton off slip - Slip Closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 NB Craigton IC to Erskine Bridge - Lane Closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 NB off slip to A726 - Slip Closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 NB Spectacles on slip - Slip Closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 SB Old toll to Jct 30 slips - lane closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 SB A726 off slip safety coning
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 SB onslip from A726 Slip Closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 EB off slip to M8 Jct 30 Slip Closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM898 WB off slip to M8 Jct 31 Slip Closure
-
12th of September 2025, 8:00pm13th of September 2025, 6:00amM8 WB Jct 30 off slip Slip Closure
-
13th of September 2025, 8:30pm20th of September 2025, 6:00amM8 - WB - Jct 3a to Jct 4 - Closure
-
13th of September 2025, 8:30pm20th of September 2025, 6:00amM8 - EB - Jct 4 on slip - Closure
-
13th of September 2025, 8:30pm20th of September 2025, 6:00amM8 - WB - Jct 3a on slip - Closure
-
13th of September 2025, 8:30pm20th of September 2025, 6:00amM8 - EB - Jct 4 to 3A - Closure
-
14th of September 2025, 7:30pm24th of October 2025, 6:30amM90 Glenfarg to Kintillo- Lane Closure N/B
-
14th of September 2025, 7:30pm24th of October 2025, 6:30amM90 Glenfarg to Kintillo- Lane Closure S/B
-
15th of September 2025, 7:30pm4th of October 2025, 6:00amA7-NB-South of Canonbie-Road Closure
-
15th of September 2025, 7:30pm4th of October 2025, 6:00amA7-SB-South of Canonbie-Road Closure
-
15th of September 2025, 8:00pm26th of September 2025, 4:30amM8- EB -on slip - Lane 1 closure
-
15th of September 2025, 8:00pm16th of September 2025, 6:00amM74 SB Jct 7 to Jct 8 - Road closure
-
15th of September 2025, 8:00pm16th of September 2025, 6:00amM74 SB Jct 8 off slip - road closure
-
15th of September 2025, 8:00pm16th of September 2025, 6:00amM74 NB Jct 8 to Jct 7 Road Closure
-
15th of September 2025, 8:00pm16th of September 2025, 6:00amM74 NB Jct 8 on slip - Slip Closure
-
15th of September 2025, 8:00pm16th of September 2025, 6:00amM90 NB Jct 2A off slip - Slip Road Closure
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM9 WB Jct 9 to Jct 10. Closure.
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM9 WB Jct 9 on-slip. Closure.
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM9 WB Jct 10 off-slip. Closure.
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM80 WB Jct 9 to M9. Closure.
-
16th of September 2025, 8:00pm17th of September 2025, 6:00amM74 SB J1a off slip - Slip Closure
-
16th of September 2025, 8:00pm17th of September 2025, 6:00amM74 SB J1a onslip - Slip Closure
-
16th of September 2025, 8:00pm17th of September 2025, 6:00amM74 NB J2 off slip - Slip Closure
-
16th of September 2025, 8:00pm17th of September 2025, 6:00amM74 NB J2 on slip - Slip Closure
-
16th of September 2025, 8:00pm17th of September 2025, 6:00amM74 SB Jct 2a off slip Slip Closure
-
16th of September 2025, 8:00pm17th of September 2025, 6:00amM74 SB Jct 2a on slip Slip Closure
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM9 WB Jct 9 to Jct 10. Closure.
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM9 WB Jct 9 on-slip. Closure.
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM9 WB Jct 10 off-slip. Closure.
-
16th of September 2025, 8:00pm19th of September 2025, 6:00amM80 WB Jct 9 to M9. Closure.
-
16th of September 2025, 8:00pm17th of September 2025, 6:00amM90 SB - Road closure - Jct2 offslip from A92
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 SB Jct 6 combined slip from Motherwell Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 SB Jct 6 from Motherwell on slip - Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 NB Jct 6 from Motherwell on Slip - -Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 NB Jct 6 off slip Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 NB Jct 6 off slip to Hamilton Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 NB Jct 6 off slip to Motherwell Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 NB Jct 11 on slip- Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 NB Jct 10 off slip -Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 SB Jct 10 on slip - Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 SB Jct 11 off slip - Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 SB J7 off slip - Slip Closure
-
17th of September 2025, 8:00pm18th of September 2025, 6:00amM74 NB J7 on slip - Slip Closure
-
17th of September 2025, 8:00pm23rd of September 2025, 6:00amM8 Junction 4 On-Slip Westbound
-
17th of September 2025, 8:00pm23rd of September 2025, 6:00amM8 Junction 4 to Junction 4A Mainline Carriageway Westbound
-
17th of September 2025, 8:00pm23rd of September 2025, 6:00amM8 Junction 4A Off-Slip Westbound
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 Jct 6 On Slip NB from Hamilton - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 Jct 6 NB from Hamilton to M74 - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 Jct 6 SB from Hamilton to M74 - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 Jct 6 Off Slip SB - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 Jct 6 off slip to Hamilton SB - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 Jct 6 off slip to Motherwell SB - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 SB J9 off slip - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 NB J3 off slip - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amM74 SB J3 on slip - Slip Closure
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amA90 NB - Lane Closure - Jct 1
-
18th of September 2025, 8:00pm19th of September 2025, 6:00amA90 NB - PTL closure - Jct 1
-
19th of September 2025, 8:00pm23rd of September 2025, 6:00amM9 WB Jct 10 to Jct 11. Closure.
-
19th of September 2025, 8:00pm23rd of September 2025, 6:00amM9 WB Jct 10 on slip Closure.
-
19th of September 2025, 8:00pm20th of September 2025, 6:00amM74 NB J10 to J8 - Road Closure
-
19th of September 2025, 8:00pm20th of September 2025, 6:00amM74 NB J10 on slip - Slip Closure
-
19th of September 2025, 8:00pm20th of September 2025, 6:00amM74 NB J8 off slip - Slip Closure
-
19th of September 2025, 8:00pm20th of September 2025, 6:00amM74 SB J8 to J10 - Road Closure
-
19th of September 2025, 8:00pm20th of September 2025, 6:00amM74 SB J8 on slip - Slip Closure
-
19th of September 2025, 8:00pm20th of September 2025, 6:00amM74 SB J9 off slip - Slip Closure
-
21st of September 2025, 7:00pm25th of September 2025, 7:00amA87 Bun Loyne WB - Road Closure
-
21st of September 2025, 7:00pm25th of September 2025, 7:00amA87 Bun Loyne EB - Road Closure
-
22nd of September 2025, 8:00am26th of September 2025, 5:00pmA876 15 Haughs O'Airth
-
22nd of September 2025, 8:00am26th of September 2025, 5:00pmA876 15 Haughs O'Airth
-
22nd of September 2025, 6:30pm31st of October 2025, 6:30amA96 Huntly to Keith- TTL W/B
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 SB J2 off slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 SB J2 on slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 NB J1a off slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 NB J1a on slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 NB J2a on slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 NB 2a off slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 NB J1 off slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM74 SB J1 on slip - Slip Closure
-
22nd of September 2025, 8:00pm23rd of September 2025, 6:00amM8 Kingston Br EB- Lane 1 closure
-
22nd of September 2025, 8:00pm25th of September 2025, 6:00amA1 - NB - North of Spott RBT - NB Closure
-
23rd of September 2025, 8:00pm24th of September 2025, 6:00amM8 EB Approach to Kingston Br - Lane Closures
-
23rd of September 2025, 8:00pm24th of September 2025, 6:00amM8 WB on to Kingston Br - Lane Closure
-
23rd of September 2025, 8:00pm24th of September 2025, 6:00amM74 SB J1 off slip - Lane Closure
-
23rd of September 2025, 8:00pm24th of September 2025, 6:00amM8 Hillington Rbt inner - lane closure
-
23rd of September 2025, 8:00pm24th of September 2025, 6:00amM74 Jct 1 SB-Lane 2 closure
-
23rd of September 2025, 8:00pm24th of September 2025, 6:00amM74 Jct 1 NB-Lane 2 closure
-
23rd of September 2025, 8:00pm25th of September 2025, 6:00amM9 EB Jct 11 to Jct 10 Closure.
-
23rd of September 2025, 8:00pm25th of September 2025, 6:00amM9 EB Jct 11 to Jct 10 Closure.
-
23rd of September 2025, 8:30pm9th of October 2025, 6:00amM8 Jct3A - Jct2 Road Closure
-
23rd of September 2025, 8:30pm9th of October 2025, 6:00amM8 Jct3A EB Onslip - Slip Closure
-
23rd of September 2025, 8:30pm9th of October 2025, 6:00amM8 Jct3 EB Onslip - Road Closure
-
23rd of September 2025, 8:30pm9th of October 2025, 6:00amM8 Jct 3 Onslip - Road Closure
-
23rd of September 2025, 8:30pm9th of October 2025, 6:00amM8 Jct2 EB Onslip - Road Closure
-
24th of September 2025, 7:00pm3rd of October 2025, 7:00amA86 Roybridge WB - Road Closure with Amnesties
-
24th of September 2025, 7:00pm3rd of October 2025, 7:00amA86 Roybridge EB - Road Closure with Amnesties
-
25th of September 2025, 7:00pm26th of September 2025, 7:00amA87 Feith Ghrianach East of Bun Loyne WB - Road Closure
-
25th of September 2025, 7:00pm26th of September 2025, 7:00amA87 Feith Ghrianach East of Bun Loyne EB - Road Closure
-
25th of September 2025, 7:30pm27th of September 2025, 6:00amA1 - NB - North of Cockburnspath - Road Closure
-
25th of September 2025, 7:30pm27th of September 2025, 6:00amA1 - SB - North of Cockburnspath - Road Closure
-
25th of September 2025, 8:00pm27th of September 2025, 6:00amM9 EB Jct 10 to Jct 9 Closure.
-
25th of September 2025, 8:00pm27th of September 2025, 6:00amM9 EB Jct 10 on slip Closure.
-
25th of September 2025, 8:00pm27th of September 2025, 6:00amM9 EB Jct 9 off slip Closure.
-
25th of September 2025, 8:00pm27th of September 2025, 6:00amM9 EB Jct 9 off slip to M80 Closure.
-
27th of September 2025, 10:30pm29th of September 2025, 6:30amA90 Glendoick to Grange. Diversion signage for local road closure
-
28th of September 2025, 7:00pm10th of October 2025, 7:00amA9 Evanton - Convoy Works
-
28th of September 2025, 8:00pm5th of April 2026, 6:00amA725 Southbound Diamond main line - Total closure
-
28th of September 2025, 8:00pm5th of April 2026, 6:00amA725 Northbound Daimond Main line - Offside lane closure
-
28th of September 2025, 8:00pm5th of April 2026, 6:00amA725 Northbound Diamond main line - Contraflow
-
28th of September 2025, 8:00pm5th of April 2026, 6:00amA725 Southbound Diamond Main line - Contraflow
-
29th of September 2025, 7:30pm1st of October 2025, 6:00amA1 - NB - Cedar Café - Road Closure
-
29th of September 2025, 7:30pm1st of October 2025, 6:00amA1 - SB - Cedar Café - Road Closure
-
29th of September 2025, 8:00pm2nd of October 2025, 6:00amM9 EB Jct 9 on slip Closure.
-
29th of September 2025, 8:00pm2nd of October 2025, 6:00amM876 EB Jct 2 to M9 merge Closure.
-
29th of September 2025, 8:00pm2nd of October 2025, 6:00amM876 EB M9 merge to jct 3 Closure.
-
29th of September 2025, 8:00pm2nd of October 2025, 6:00amM876 EB jct 3 off slip Closure.
-
29th of September 2025, 8:00pm2nd of October 2025, 6:00amM9 EB Jct 9 to Jct 7 Closure.
-
29th of September 2025, 9:00pm1st of October 2025, 6:00amA90 Longforgan SB - Lane closure
-
1st of October 2025, 7:00am23rd of December 2025, 7:00pmA9 South if Bridge of Tacher Achavanich - Convoy Works
-
1st of October 2025, 7:00pm2nd of October 2025, 7:00amA82 Tyndrum - Convoy Works
-
1st of October 2025, 7:00pm3rd of October 2025, 7:00amA87 Cluanie Inn Glen Moriston EB - Road Closure with Amnesties
-
1st of October 2025, 7:00pm2nd of October 2025, 5:00amA87 Braes Jnct East of Portree WB - Road Closure with Amnesties
-
1st of October 2025, 7:00pm2nd of October 2025, 5:00amA87 Braes Jnct East of Portree EB - Road Closure with Amnesties
-
1st of October 2025, 8:00pm4th of October 2025, 6:00amA720 - WB - Millerhill WB Onslip - Road Closure
-
1st of October 2025, 8:00pm4th of October 2025, 6:00amA720 - WB - Millerhill Mainline - Road Closure
-
1st of October 2025, 8:00pm4th of October 2025, 6:00amA68 - NB - Millerhill Junction - Lane Closure
-
1st of October 2025, 9:00pm4th of October 2025, 6:00amA90 Inchture SB - Lane closure
-
2nd of October 2025, 7:00pm10th of October 2025, 7:00amA82 Cattle Ranch South of Spean Bridge NB - Road Closure with Amnesties
-
2nd of October 2025, 7:00pm10th of October 2025, 7:00amA82 Cattle Ranch South of Spean Bridge SB - Road Closure with Amnesties
-
2nd of October 2025, 7:00pm3rd of October 2025, 7:00amA87 Cluanie Inn Glen Moriston WB - Road Closure with Amnesties
-
2nd of October 2025, 8:00pm3rd of October 2025, 6:00amM9 EB Jct 8 to Jct 7. Lane Closures.
-
3rd of October 2025, 8:00pm7th of October 2025, 6:00amM9 EB Jct 7 to Jct 6. Road Closure.
-
3rd of October 2025, 8:00pm7th of October 2025, 6:00amM876 EB Jct 3 to M9 EB Jct 7. Road Closure.
-
3rd of October 2025, 8:00pm7th of October 2025, 6:00amM9 EB Jct 6 off-slip. Road Closure.
-
5th of October 2025, 7:30pm24th of October 2025, 6:30amA9 Stockbridge- Lane Closure N/B
-
5th of October 2025, 7:30pm24th of October 2025, 6:30amA9 Stockbridge- Lane Closure S/B
-
6th of October 2025, 7:00am26th of December 2025, 7:00pmA82 Meeting of 3 Waters South of Glencoe NB - TTL
-
6th of October 2025, 7:00am26th of December 2025, 7:00pmA82 Meeting of 3 Waters South of Glencoe SB - TTL
-
6th of October 2025, 7:00pm11th of October 2025, 7:00amA87 Breakish East of Broadford WB - Road Closure with Amnesties
-
6th of October 2025, 7:00pm11th of October 2025, 7:00amA87 Breakish East of Broadford EB - Road Closure with Amnesties
-
6th of October 2025, 8:00pm8th of October 2025, 6:00amM8 WB Jct 9 to Jct 11 - Offside Lane Closure
-
6th of October 2025, 8:00pm8th of October 2025, 6:00amM8 EB Jct 12 to Jct 10 - Offside and Adjacent Lane Closures
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amM8 Jct 27 onslip WB - Total Closure
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amM8 Jct 27 to Jct 28 WB - Nearside Lane Closure
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amM8 Jct 28 offslip WB - Total Closure
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amM8 Jct 28 onslip EB - Total Closure
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amM8 Jct 28 to Jct 27 EB - Nearside Lane Closure
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amM8 Jct 27 offslip EB - Total Closure
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amA737 Linwood onslip NB - Total Closure
-
6th of October 2025, 8:00pm8th of October 2025, 6:00amM9 - EB - Newbridge - Hard Shoulder Closure
-
6th of October 2025, 8:00pm7th of October 2025, 6:00amA737 Linwood to St James' NB - Nearside Lane Closure
-
6th of October 2025, 8:00pm9th of October 2025, 6:00amM9 - WB - Newbridge - Hard Shoulder Closure
-
6th of October 2025, 8:30pm9th of October 2025, 6:00amA720 - EB - Calder EB Onslip - Road Closure
-
6th of October 2025, 8:30pm9th of October 2025, 6:30amA720 - EB - Calder EB Mainline - Lane Closure
-
6th of October 2025, 8:30pm9th of October 2025, 6:00amA71 - WB - Calder Junction - Lane Closure
-
6th of October 2025, 9:00pm7th of October 2025, 6:00amA90 Errol NB - Lane closure
-
6th of October 2025, 9:00pm16th of October 2025, 6:00amA78 Irvine Rd Fairlie NB - TTLS
-
6th of October 2025, 9:00pm16th of October 2025, 6:00amA78 Irvine Rd Fairlie SB - TTLS
-
7th of October 2025, 8:00pm8th of October 2025, 6:00amM9 EB Jct 6-5. Road Closure.
-
7th of October 2025, 8:00pm8th of October 2025, 6:00amM9 EB Jct 5 off-slip. Road Closure.
-
7th of October 2025, 8:00pm8th of October 2025, 6:00amM8 Jct 11 onslip WB -Road Part of Diversion Route
-
7th of October 2025, 8:00pm8th of October 2025, 6:00amM8 Jct 11 onslip EB -Road Part of a Diversion Route
-
7th of October 2025, 9:00pm10th of October 2025, 6:00amA90 Kinfauns to St Madoes NB - Lane closure
-
8th of October 2025, 7:30pm10th of October 2025, 6:00amM9 - SB - Jct 11 - Jct 9 - Closure
-
8th of October 2025, 7:30pm10th of October 2025, 6:00amM9 - SB - Jct 10 - Off Slip Closure
-
8th of October 2025, 7:30pm10th of October 2025, 6:00amM9 - NB - Jct 9 - Jct 11 - Closure
-
8th of October 2025, 7:30pm10th of October 2025, 6:00amM9 - SB - Jct 9 - Off Slip Closure
-
8th of October 2025, 7:30pm10th of October 2025, 6:00amM9 - NB - Jct 9- On Slip Closure
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM9 EB Jct 5 to Jct 2. Road Closure.
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM9 EB Jct 5 on-slip. Road Closure.
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM9 EB Jct 4 off-slip. Road Closure.
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM9 EB Jct 4 off-slip. Road Closure.
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM9 EB Jct 3 on-slip. Road Closure.
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM9 EB Jct off-slip. Road Closure.
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM80 SB slip to the M8 WB - Total Closure
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM8 Jct 27 onslip EB - Total Closure
-
8th of October 2025, 8:00pm9th of October 2025, 6:00amM8 Jct 12 onslip EB - Total Closure
-
8th of October 2025, 8:30pm18th of October 2025, 6:00amM8 EB Jct3A-3 - Road Closure
-
8th of October 2025, 8:30pm18th of October 2025, 6:00amM8 Jct3A EB Onslip - Road Clsoure
-
8th of October 2025, 8:30pm18th of October 2025, 6:00amM8 Jct3 EB Offslip - Road Closure
-
9th of October 2025, 7:30pm16th of October 2025, 6:00amA7-NB-North of Langholm-Road Closure
-
9th of October 2025, 7:30pm16th of October 2025, 6:00amA7-SB-North of Langholm-Road Closure
-
9th of October 2025, 8:00pm10th of October 2025, 6:00amM74 NB Jct 6 onslip from Hamilton - Total Closure
-
9th of October 2025, 8:00pm10th of October 2025, 6:00amM74 SB Jct 6 onslip from Hamilton - Total Closure
-
9th of October 2025, 8:00pm10th of October 2025, 6:00amM74 NB Jct 1a to Jct 1 - Hard Shoulder Closure
-
9th of October 2025, 8:00pm10th of October 2025, 6:00amM74 SB Jct 1 to Jct 1a - Hard Shoulder Closure
-
9th of October 2025, 8:00pm10th of October 2025, 6:00amM8 Jct 20 West St onslip EB - Total Closure
-
10th of October 2025, 6:00am10th of October 2025, 7:30pmA7-NB-North of Langholm-TTLs
-
10th of October 2025, 6:00am10th of October 2025, 7:30pmA7-SB-North of Langholm-TTLs
-
10th of October 2025, 8:00pm11th of October 2025, 6:00amM8 Jct 19 Stobcross onramp WB - Total Closure
-
10th of October 2025, 8:00pm11th of October 2025, 6:00amM8 Jct 19 Waterloo St onramp WB - Total Closure
-
10th of October 2025, 8:00pm11th of October 2025, 6:00amM8 Jct 20 West St offslip WB - Total Closure
-
10th of October 2025, 8:00pm11th of October 2025, 6:00amM8 Jct 19 to Jct 20 WB - Lane Closures
-
10th of October 2025, 8:00pm11th of October 2025, 6:00amM8 Jct 19 Newton St onslip WB - Total Closure
-
11th of October 2025, 12:01am19th of December 2025, 11:59pmA86 Murlaggan East of Roybridge EB - TTL
-
11th of October 2025, 12:01am19th of December 2025, 11:59pmA86 Murlaggan East of Roybridge WB - TTL
-
12th of October 2025, 7:00pm21st of October 2025, 7:00amA82 Loch Linnhe Picnic Area North of Corran NB - Road Closure with Amnesties
-
12th of October 2025, 7:00pm21st of October 2025, 7:00amA82 Loch Linnhe Picnic Area North of Corran SB - Road Closure with Amnesties
-
12th of October 2025, 7:00pm21st of October 2025, 6:00amA835 Braemore WB - Road Closure with Amnesties
-
12th of October 2025, 7:00pm21st of October 2025, 6:00amA835 Braemore EB - Road Closure with Amnesties
-
13th of October 2025, 7:00pm18th of October 2025, 7:00amA87 Glenvarragil South of Portree WB - Road Closure with Amnesties
-
13th of October 2025, 7:00pm18th of October 2025, 7:00amA87 Glenvarragil South of Portree EB - Road Closure with Amnesties
-
13th of October 2025, 7:30pm14th of October 2025, 6:00amM90 Bridge of Earn slip to Broxden Rbt. N/B off slip closure
-
13th of October 2025, 7:30pm14th of October 2025, 6:00amM90 Bridge of Earn to A912 Edinburgh Rd, Perth. N/B off Slip closure
-
13th of October 2025, 8:00pm18th of October 2025, 4:30amM8- EB Main line- Hard shoulder - After Jct2
-
13th of October 2025, 8:00pm18th of October 2025, 4:30amM8 - EB Main line - Lane 1 closure - After Jct2
-
13th of October 2025, 8:00pm15th of October 2025, 6:00amM9 EB Jct 2 to 1A Road Closure.
-
13th of October 2025, 8:00pm15th of October 2025, 6:00amM9 EB Jct 1B off slip Road Closure.
-
13th of October 2025, 8:00pm15th of October 2025, 6:00amM9 EB Jct 1B on slip Road Closure.
-
13th of October 2025, 8:00pm15th of October 2025, 6:00amM9 EB Jct 1A off slip Road Closure.
-
13th of October 2025, 8:00pm14th of October 2025, 6:00amM74 NB Jct 6 offslip to Hamilton - Total Closure
-
13th of October 2025, 8:00pm14th of October 2025, 6:00amM74 NB Jct 6 offslip to Motherwell - Total Closure
-
13th of October 2025, 8:00pm14th of October 2025, 6:00amM8 Jct 15 Loop U onslip WB - Total Closure
-
13th of October 2025, 8:00pm14th of October 2025, 6:00amM8 Jct 17 onslip WB - Total Closure
-
13th of October 2025, 8:00pm14th of October 2025, 6:00amM8 Jct 19 Argyle St offslip WB - Total Closure
-
13th of October 2025, 8:00pm14th of October 2025, 6:00amM8 Jct 15 Castle St offslip WB - Total Closure
-
13th of October 2025, 8:00pm14th of October 2025, 6:00amM8 Jct 15 to Jct 19 WB - Nearside and Adjacent lane closure
-
14th of October 2025, 7:30pm15th of October 2025, 6:30amM90 Broxden Rbt to Edinburgh S/B on slip. Slip closure
-
14th of October 2025, 8:00pm15th of October 2025, 6:00amM74 SB Jct 6 onslip from Motherwell - Total Closure
-
14th of October 2025, 8:00pm15th of October 2025, 6:00amM74 NB Jct 6 onslip from Motherwell - Total Closure
-
14th of October 2025, 8:00pm16th of October 2025, 6:00amM8 Jct 19 Anderston onslip EB - Total Closure
-
14th of October 2025, 8:00pm16th of October 2025, 6:00amM8 Jct 18 offslip to GWR/St Georges Rd EB - Total Closure
-
14th of October 2025, 8:00pm16th of October 2025, 6:00amM8 Jct 16 onslip EB - Total Closure
-
14th of October 2025, 8:00pm16th of October 2025, 6:00amM8 Jct 15 Springburn offslip EB - Total Closure
-
14th of October 2025, 8:00pm16th of October 2025, 6:00amM8 Jct 21 to 15 EB - Nearside and Adjacent Lane Closure
-
14th of October 2025, 8:00pm16th of October 2025, 6:00amM8 Jct 18 Charing Cross onslip EB - Total Closure
-
15th of October 2025, 7:30pm16th of October 2025, 6:30amM90 from A912 Edinburgh Rd to S/B on slip. Slip closure
-
15th of October 2025, 7:30pm16th of October 2025, 6:30amM90 Friarton Bridge to S/B on slip from A912. S/B Lane closures
-
15th of October 2025, 7:30pm16th of October 2025, 6:30amM90 Craigend to N/B on slip from Broxden. N/B Lane closures
-
15th of October 2025, 7:30pm16th of October 2025, 6:30amM90 Broxden Rbt to Friarton N/B on slip. Slip closure
-
15th of October 2025, 8:00pm16th of October 2025, 6:00amM9 EB Jct 1A to 1 Road Closure.
-
15th of October 2025, 8:00pm16th of October 2025, 6:00amM9 EB Queensferry to jct 1A Road Closure.
-
15th of October 2025, 8:00pm16th of October 2025, 6:00amM9 EB Jct 1 off slip Road Closure.
-
15th of October 2025, 8:00pm16th of October 2025, 6:00amM74 SB Jct 6 offslip to Motherwell - Total Closure
-
15th of October 2025, 8:00pm16th of October 2025, 6:00amM74 SB Jct 6 offslip to Hamilton - Total Closure
-
15th of October 2025, 8:00pm16th of October 2025, 6:00amM74 SB Jct 6 - Nearside Lane Closure
-
16th of October 2025, 7:30pm17th of October 2025, 6:30amM90 Friarton to Broxden Rbt. N/B on slip. Slip closure
-
16th of October 2025, 7:30pm22nd of October 2025, 6:00amA7-NB-South of Teinside-Road Closure
-
16th of October 2025, 7:30pm22nd of October 2025, 6:00amA7-SB-South of Teinside-Road Closure
-
16th of October 2025, 8:00pm17th of October 2025, 6:00amM74 SB Jct 6 onslip from Hamilton - Total Closure
-
16th of October 2025, 8:00pm17th of October 2025, 6:00amM74 SB Jct 6 between the slips - Nearside Lane Closure
-
16th of October 2025, 8:00pm17th of October 2025, 6:00amM74 NB Jct 6 offslip to Hamilton - Total Closure
-
16th of October 2025, 8:00pm17th of October 2025, 6:00amM74 NB Jct 6 offslip to Motherwell - Total Closure
-
16th of October 2025, 8:00pm17th of October 2025, 6:00amM74 NB Jct 6 between the slips - Nearside Lane Closure
-
16th of October 2025, 8:00pm17th of October 2025, 6:00amM74 NB Jct 6 onslip from Motherwell - Total Closure
-
17th of October 2025, 6:00am17th of October 2025, 7:30pmA7-NB-South of Teinside-TTLs
-
17th of October 2025, 6:00am17th of October 2025, 7:30pmA7-SB-South of Teinside-TTLs
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - WB - Jct 9 to Jct 11 - Road closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - WB - Jct 9 on slip - slip closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - WB - Jct 10 off slip - slip closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - WB - Jct 10 on slip - slip closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - EB - Jct 11 to Jct 9 - Road closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - EB - Jct 10 off slip - Road closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - EB - Jct 10 on slip - Road closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM9 - EB - Jct 9 on slip - Road closure
-
17th of October 2025, 8:00pm18th of October 2025, 6:00amM80 - EB - Jct 9 - Road closure
-
20th of October 2025, 7:00pm25th of October 2025, 7:00amA87 Peinmore South of Portree WB - Road Closure with Amnesties
-
20th of October 2025, 7:00pm25th of October 2025, 7:00amA87 Peinmore South of Portree EB - Road Closure with Amnesties
-
20th of October 2025, 7:00pm29th of October 2025, 6:00amA9 Shalmstry South of Thurso NB - Road Closure with Amnesties
-
20th of October 2025, 7:00pm29th of October 2025, 6:00amA9 Shalmstry South of Thurso SB - Road Closure with Amnesties
-
20th of October 2025, 7:30pm23rd of October 2025, 6:00amM80 NB Jct. 7 - 9 Road closure
-
20th of October 2025, 7:30pm23rd of October 2025, 6:00amM876 EB M80 to Jct. 1 Road Closure
-
20th of October 2025, 7:30pm23rd of October 2025, 6:00amM80 Jct. 9 NB Offslip - Slip Closure
-
20th of October 2025, 7:30pm23rd of October 2025, 6:00amM80 Jct. 7 Onslip
-
20th of October 2025, 7:30pm23rd of October 2025, 6:00amM876 Jct. 1 EB Offslip
-
20th of October 2025, 8:00pm25th of October 2025, 4:30amM8- WB- Main line- hard shoulder closure -
-
20th of October 2025, 8:00pm25th of October 2025, 4:30amM8- WB- Main line- lane 1 closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM8 WB Jct 14 onslip - Total Closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM8 WB Jct 14 to Jct 15 Stirling Rd offslip - Nearside Lane Closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM8 WB Jct 15 Loop U onslip - Total Closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amAlexandra Parade - Nearside Lane Closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM8 EB Jct 18 offslip to Great Western Rd - Total Closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM90 - NB - Jct 1B to 2 - Road closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM90 - NB - Jct 1B on slip - Road closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM90 - NB - Jct 1c off slip - Road closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM90 - NB - Jct 1c on slip - Road closure
-
20th of October 2025, 8:00pm21st of October 2025, 6:00amM90 - NB - Jct 2 off slip - Road closure
-
21st of October 2025, 7:00pm30th of October 2025, 7:00amA82 Inchree North of Corran NB - Road Closure with Amnesties
-
21st of October 2025, 7:00pm30th of October 2025, 7:00amA82 Inchree North of Corran SB - Road Closure with Amnesties
-
21st of October 2025, 7:00pm24th of October 2025, 6:00amA835 Inchbae WB - Road Closure with Amnesties
-
21st of October 2025, 7:00pm24th of October 2025, 6:00amA835 Inchbae EB - Road Closure with Amnesties
-
21st of October 2025, 8:00pm22nd of October 2025, 6:00amM8 EB Jct 25a to Jct 25 - Offside and Adjacent Lane Closure
-
21st of October 2025, 8:00pm22nd of October 2025, 6:00amM8 WB Jct 24 to Jct 25 - Offside Lane Closure
-
21st of October 2025, 8:00pm22nd of October 2025, 6:00amA739 Berryknowes Rd slip to Cardonald Interchange - Total Closure
-
21st of October 2025, 8:00pm22nd of October 2025, 6:00amA739 NB - Total Closure
-
21st of October 2025, 8:00pm22nd of October 2025, 6:00amM8 EB Jct 24 onslip - Total Closure
-
21st of October 2025, 8:00pm22nd of October 2025, 6:00amM8 EB Jct 23 onslip - Total Closure
-
21st of October 2025, 8:00pm22nd of October 2025, 6:00amM8 EB Jct 24 to Sec c/way Jct 22 - Nearside Lane Closure
-
21st of October 2025, 8:00pm24th of October 2025, 6:00amM90 - NB - jct 2 to jct 3 - road closure
-
21st of October 2025, 8:00pm24th of October 2025, 6:00amM90 - NB - jct 2 on slip - road closure
-
21st of October 2025, 8:00pm24th of October 2025, 6:00amM90 - NB - A92 on slip - road closure
-
21st of October 2025, 8:00pm24th of October 2025, 6:00amM90 - NB - jct 3 off slip - road closure
-
22nd of October 2025, 7:30pm25th of October 2025, 6:00amA7-NB-Boleside-Road Closure
-
22nd of October 2025, 7:30pm25th of October 2025, 6:00amA7-SB-Boleside-Road Closure
-
22nd of October 2025, 8:00pm23rd of October 2025, 6:00amM8 EB Jct 21 to Jct 18 - Offside and Adjacent Lane Closure
-
22nd of October 2025, 8:00pm23rd of October 2025, 6:00amM8 EB Jct 19 Anderston onslip - Total Closure
-
22nd of October 2025, 8:00pm23rd of October 2025, 6:00amM8 EB Jct 19 to Jct 18 - Total Closure
-
22nd of October 2025, 8:00pm23rd of October 2025, 6:00amM8 WB Jct 17 to Jct 22 - Offside Lane Closure
-
23rd of October 2025, 6:00am24th of October 2025, 7:30pmA7-NB-Boleside-TTLs
-
23rd of October 2025, 6:00am24th of October 2025, 7:30pmA7-SB-Boleside-TTLs
-
23rd of October 2025, 8:00pm24th of October 2025, 6:00amM74 NB Jct 1a to M8 Sec c/way Jct 22 - Nearside Lane Closure
-
23rd of October 2025, 8:00pm24th of October 2025, 6:00amM74 NB Jct 1 offslip - Total Closure
-
23rd of October 2025, 8:00pm24th of October 2025, 6:00amM8 WB Sec c/way Seaward St onslip - Total Closure
-
23rd of October 2025, 8:00pm24th of October 2025, 6:00amM77 SB from M8 Jct 22 - Total Closure
-
23rd of October 2025, 8:00pm24th of October 2025, 6:00amM8 EB Jct 22 to West St - Nearside and Adjacent Lane Closure
-
24th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - Jct 3 to Jct 2 - Road Closure
-
24th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - Jct 3 on slip - Road Closure
-
24th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - A92 on slip - Road Closure
-
24th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - Jct 2 off slip - Road Closure
-
24th of October 2025, 8:30pm30th of October 2025, 6:30amA92 S/B Access to M90 - Road Closure
-
26th of October 2025, 7:00pm31st of October 2025, 6:00amA835 Conon Bridge - Convoy Works
-
26th of October 2025, 7:30pm14th of November 2025, 6:30amM90 Glenfarg- Lane Closure N/B
-
26th of October 2025, 7:30pm14th of November 2025, 6:30amM90 Glenfarg- Lane Closure S/B
-
27th of October 2025, 7:30pm1st of November 2025, 6:00amA1 - NB - Lamberton - Road Closure
-
27th of October 2025, 7:30pm1st of November 2025, 6:00amA1 - SB - Lamberton - Road Closure
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA75 Cuckoo Bridge Rbt - Inner and Middle Ring Lane Closures
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA76 SB Glasgow Rd approach to Cuckoo Bridge Rbt - Lane Closures
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA76 Glasgow Rd NB approach to Cuckoo Bridge Rbt - Lane Closures
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA75 EB approach to Cuckoo Bridge Rbt - Lane Closures
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA75 WB approach to Cuckoo Bridge Rbt - Lane Closures
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA75 Bloomfield Rbt - 4-way TTL
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA75 Bloomfield Rbt - 4-way TTL
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA75 Bloomfield Rbt - 4-way TTL
-
27th of October 2025, 8:00pm28th of October 2025, 6:00amA75 Bloomfield Rbt - 4-way TTL
-
28th of October 2025, 8:00pm31st of October 2025, 6:00amM8 Jct 15 to Jct 13 EB - Offside Lane Closure
-
28th of October 2025, 8:00pm31st of October 2025, 6:00amM8 Jct 12 to Jct 15 WB - Offside Lane Closure
-
29th of October 2025, 7:00pm7th of November 2025, 7:00amA82 Belford Rd Fort William NB - Road Closure with Amnesties
-
29th of October 2025, 7:00pm7th of November 2025, 7:00amA82 Belford Rd Fort William SB - Road Closure with Amnesties
-
29th of October 2025, 7:30pm8th of November 2025, 6:00amA702 - NB - Dolphinton - Closure
-
29th of October 2025, 7:30pm8th of November 2025, 6:00amA702 - SB - Dolphinton - Closure
-
29th of October 2025, 8:00pm30th of October 2025, 6:00amm90 - SB - Jct 2 to Jct 1B - Road Closure
-
29th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - Jct 2 on slip - Road Closure
-
29th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - Jct 1c off slip - Road Closure
-
29th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - Jct 1c on slip - Road Closure
-
29th of October 2025, 8:00pm30th of October 2025, 6:00amM90 - SB - Jct 1B on slip - Road Closure
-
30th of October 2025, 8:00pm4th of November 2025, 6:00amM90 - SB - Jct 1a to M9 jct 1a - Road closure
-
30th of October 2025, 8:00pm4th of November 2025, 6:00amM90 - SB - Jct 1a on slip - Road closure
-
30th of October 2025, 8:00pm4th of November 2025, 6:00amM90 - SB - Jct 1a to M9 jct 1a - Road closure
-
2nd of November 2025, 7:00pm7th of November 2025, 6:00amA835 Conon Bridge - Convoy Works
-
2nd of November 2025, 7:30pm14th of November 2025, 6:30amM90 Rhynd Road- Lane Closure N/B
-
2nd of November 2025, 7:30pm14th of November 2025, 6:30amM90 Rhynd Road- Lane Closure S/B
-
3rd of November 2025, 7:30pm4th of November 2025, 6:00amA1 - NB - Lamberton Jct - Road Closure
-
3rd of November 2025, 7:30pm4th of November 2025, 6:00amA1 - SB - Lamberton Jct - Road Closure
-
3rd of November 2025, 8:00pm6th of November 2025, 6:00amM8 Jct 14 to Jct 12 EB - Offside Lane Closure
-
3rd of November 2025, 8:00pm6th of November 2025, 6:00amM8 Jct 11 to Jct 13 WB - Offside Lane Closure
-
4th of November 2025, 7:30pm29th of November 2025, 6:00amA1 - NB - Gladsmuir to Bankton - Road Closure
-
4th of November 2025, 7:30pm29th of November 2025, 6:00amA1 - NB - Gladsmuir NB On slip - Road Closure
-
4th of November 2025, 7:30pm29th of November 2025, 6:00amA1 - NB - Bankton NB Offslip - Road Closure
-
6th of November 2025, 8:00pm12th of November 2025, 6:00amM8 Jct 12 to Jct 10 EB - Offside Lane Closure
-
6th of November 2025, 8:00pm12th of November 2025, 6:00amM8 Jct 9 to Jct 12 WB - Offside Lane Closure
-
9th of November 2025, 7:00pm13th of November 2025, 7:00amA82 Beinn Odhar Auch NB - Road Closure with Amnesties
-
9th of November 2025, 7:00pm13th of November 2025, 7:00amA82 Beinn Odhar Auch SB - Road Closure with Amnesties
-
10th of November 2025, 12:00am28th of November 2025, 3:30pmA78 Inverkip Village - TTLs
-
10th of November 2025, 12:00am28th of November 2025, 3:30pmA78 Inverkip Village - TTLs
-
10th of November 2025, 8:00pm23rd of November 2025, 4:30amM8 WB - HS Closure - Jct2 Onslip
-
10th of November 2025, 8:00pm22nd of November 2025, 4:30amM8 WB - Lane Closure - Jct 2 Onslip
-
10th of November 2025, 8:00pm21st of November 2025, 6:00amM9 Jct4-3 SB - Road Closure
-
10th of November 2025, 8:00pm21st of November 2025, 6:00amM9 Jct4 SB Onslip - Road Closure
-
12th of November 2025, 8:00pm28th of November 2025, 6:00amM8 EB Jct 26 to Jct 21 - Progressive Offside Lane Closures
-
12th of November 2025, 8:00pm28th of November 2025, 6:00amM8 WB Jct 18 to Jct 26 - Progressive Offside Lane Closures
-
13th of November 2025, 7:00pm19th of November 2025, 7:00amA82 Clachaig Inn Glencoe NB - Road Closure with Amnesties
-
13th of November 2025, 7:00pm19th of November 2025, 7:00amA82 Clachaig Inn Glencoe SB - Road Closure with Amnesties
-
20th of November 2025, 8:30pm27th of November 2025, 6:00amM8 Jct2-3 - Road Closure
-
20th of November 2025, 8:30pm27th of November 2025, 6:00amM8 Jct2 WB Onslip - Road Closure
-
20th of November 2025, 8:30pm27th of November 2025, 6:00amM8 Jct3 WB Offslip - Road Closure
-
23rd of November 2025, 7:00pm28th of November 2025, 6:00amA82 Strone North of Urquhart Castle Drumnardochit NB - Road Closure with Amnesties
-
23rd of November 2025, 7:00pm28th of November 2025, 6:00amA82 Strone North of Urquhart Castle Drumnardochit SB - Road Closure with Amnesties
-
23rd of November 2025, 8:00pm25th of November 2025, 6:00amA85 George St Oban WB - Road Closure with Amnesties
-
27th of November 2025, 8:30pm2nd of December 2025, 6:00amM8 Junction 3a Westbound On slip - Road Closure
-
27th of November 2025, 8:30pm2nd of December 2025, 6:00amM8 Mainline from Junction 3a Westbound - Full Closure
-
27th of November 2025, 8:30pm2nd of December 2025, 6:00amStarlaw West Roundabout - Outer Lane Closure
-
27th of November 2025, 8:30pm28th of November 2025, 6:00amM8 Jct3A-4 - Road Closure
-
27th of November 2025, 8:30pm28th of November 2025, 6:00amM8 Jct3A Onslip - Road Closure
-
27th of November 2025, 8:30pm28th of November 2025, 6:00amM8 Jct4 Offslip - Road Closure
-
28th of November 2025, 7:30pm3rd of December 2025, 6:00amA1 - NB - Bankton NB Onslip - Slip Closure
-
28th of November 2025, 7:30pm3rd of December 2025, 6:00amA1 - NB - Bankton NB Onslip - Mainline Closure
-
28th of November 2025, 7:30pm3rd of December 2025, 6:00amA1 - NB - Bankton Junction South Roundabout - TTL`s
-
30th of November 2025, 7:00pm4th of December 2025, 7:00amA828 South of Connel Bridge NB - Road Closure with Amnesties
-
30th of November 2025, 7:00pm4th of December 2025, 7:00amA828 South of Connel Bridge SB - Road Closure with Amnesties
-
30th of November 2025, 7:00pm5th of December 2025, 6:00amA82 Grotaig South of Drumnadrochit NB - Road Closure with Amnesties
-
30th of November 2025, 7:00pm5th of December 2025, 6:00amA82 Grotaig South of Drumnadrochit SB - Road Closure with Amnesties
-
1st of December 2025, 8:00pm2nd of December 2025, 6:00amM80 SB slip to the M8 WB - Total Closure
-
1st of December 2025, 8:00pm2nd of December 2025, 6:00amM80 Jct 1 onslip NB - Total Closure
-
1st of December 2025, 8:00pm2nd of December 2025, 6:00amM80 Jct 1 to Royston Road O/B NB - Hard Shoulder Closure
-
2nd of December 2025, 8:00pm3rd of December 2025, 6:00amA723 WB Motherwell Rd - Hard Shoulder Closure
-
2nd of December 2025, 8:00pm3rd of December 2025, 6:00amA723 EB Motherwell Rd - Hard Shoulder Closure
-
3rd of December 2025, 7:30pm12th of December 2025, 6:00amA702 - NB - Flotterstone - Road Closure
-
3rd of December 2025, 7:30pm12th of December 2025, 6:00amA702 - SB - Flotterstone - Road Closure
-
3rd of December 2025, 8:00pm4th of December 2025, 6:00amM8 EB Jct 13 slip to the M80 NB - Hard Shoulder Closure
-
3rd of December 2025, 8:00pm4th of December 2025, 6:00amM80 SB Jct 1 offslip - Hard Shoulder Closure
-
4th of December 2025, 7:00pm12th of December 2025, 7:00amA828 Dallachulish South of Creagan NB - Road Closure with Amnesties
-
4th of December 2025, 7:00pm12th of December 2025, 7:00amA828 Dallachulish South of Creagan SB - Road Closure with Amnesties
-
4th of December 2025, 8:00pm5th of December 2025, 6:00amM8 EB Jct 25 onslip - Total Closure
-
4th of December 2025, 8:00pm5th of December 2025, 6:00amM8 WB Jct 25 onslip - Total Closure
-
4th of December 2025, 8:00pm5th of December 2025, 6:00amBerryknowes Rd NB offslip - Total Closure
-
4th of December 2025, 8:00pm5th of December 2025, 6:00amM8 WB Sec c/way Jct 21 - Hard Shoulder Closure
-
4th of December 2025, 8:00pm5th of December 2025, 6:00amM8 WB Sec c/way Jct 22 - Hard Shoulder Closure
-
4th of December 2025, 8:30pm6th of December 2025, 6:00amM8 - EB - Junction 4 Off-slip - Road Closure
-
4th of December 2025, 8:30pm6th of December 2025, 6:00amM8 - EB - Junction 4a -4 - Road Closure
-
4th of December 2025, 8:30pm6th of December 2025, 6:00amM8 - EB - Junction 4 Roundabout.- Lane Closure
-
4th of December 2025, 8:30pm6th of December 2025, 6:00amM8 EB Jct 4A on-slip. Road Closure.
-
7th of December 2025, 7:00pm16th of December 2025, 6:00amA82 Altsigh NB - Road Closure with Amnesties
-
7th of December 2025, 7:00pm16th of December 2025, 6:00amA82 Altsigh SB - Road Closure with Amnesties
-
8th of December 2025, 9:30am8th of December 2025, 3:30pmA84 Doune - Diversion Signage
-
8th of December 2025, 8:00pm20th of December 2025, 4:30amM8- WB- Jct2 Offslip - hard shoulder closure
-
8th of December 2025, 8:00pm20th of December 2025, 4:30amM8- WB- Jct2 Offlsip- lane 1 closure
-
8th of December 2025, 8:00pm9th of December 2025, 6:00amM8 EB Jct 23 to M8 EB Sec c/way - Hard Shoulder Closure
-
8th of December 2025, 8:00pm9th of December 2025, 6:00amM8 WB to M77 SB slip - Hard Shoulder Closure
-
9th of December 2025, 8:00pm10th of December 2025, 6:00amM8 Jct 18 offslip to Charing Cross WB - Total Closure
-
9th of December 2025, 8:00pm10th of December 2025, 6:00amM8 Jct 17 to Jct 18 WB - Offside Lane Closure
-
9th of December 2025, 8:00pm10th of December 2025, 6:00amM8 Jct 21 to Jct 17 EB - Offside Lane Closure
-
9th of December 2025, 8:00pm10th of December 2025, 6:00amGreat Western Rd WB - Nearside Lane Closure
-
9th of December 2025, 8:00pm10th of December 2025, 6:00amM8 Jct 17 onslip from Great Western Rd WB - Hard Shoulder Closure
-
9th of December 2025, 8:00pm10th of December 2025, 6:00amM8 EB Jct 23 to Jct 22 Sec c/way - Nearside Lane Closure
-
10th of December 2025, 8:00pm11th of December 2025, 6:00amM8 EB Jct 15 Stirling Rd onslip - Total Closure
-
10th of December 2025, 8:00pm11th of December 2025, 6:00amM8 WB Jct 15 Stirling Rd offslip - Total Closure
-
10th of December 2025, 8:00pm11th of December 2025, 6:00amM8 WB Jct 14 on Slip - Total Closure
-
10th of December 2025, 8:00pm11th of December 2025, 6:00amM8 WB Jct 13 to Jct 15 - Lane Closure
-
10th of December 2025, 8:00pm11th of December 2025, 6:00amM80 SB onto the M8 WB - Total Closure
-
10th of December 2025, 8:00pm11th of December 2025, 6:00amM8 Jct 15 offslip to Stirling Rd - Hard Shoulder Closure
-
11th of December 2025, 8:00pm12th of December 2025, 6:00amM8 Jct 15 Loop U onslip WB - Total Closure
-
11th of December 2025, 8:00pm12th of December 2025, 6:00amM8 Jct 15 to Jct 16 WB - Nearside Lane Closure
-
11th of December 2025, 8:00pm12th of December 2025, 6:00amM8 Jct 16 offslip WB - Total Closure
-
15th of December 2025, 8:00pm17th of December 2025, 6:00amM8 Jct 16 onslip EB - Total Closure
-
15th of December 2025, 8:00pm17th of December 2025, 6:00amM8 Jct 17 to Jct 15 EB - Nearside Lane Closure
-
15th of December 2025, 8:00pm17th of December 2025, 6:00amM8 Jct 15 offslip to Springburn EB - Total Closure
-
5th of January 2026, 7:00am31st of March 2026, 7:00pmA87 Portree WB - TTL
-
5th of January 2026, 7:00am31st of March 2026, 7:00pmA87 Portree EB - TTL
-
11th of January 2026, 7:00pm23rd of January 2026, 6:00amA86 Strathmashie WB - Road Closure with Amnesties
-
11th of January 2026, 7:00pm23rd of January 2026, 6:00amA86 Strathmashie EB - Road Closure with Amnesties
-
21st of January 2026, 7:30pm23rd of January 2026, 6:00amA1 - NB - South of Little Pinkerton Jct - Road Closure
-
21st of January 2026, 7:30pm23rd of January 2026, 6:00amA1 - SB - South of Little Pinkerton Jct - Road Closure
-
9th of February 2026, 8:30pm11th of February 2026, 6:00amM8 - EB - Harthill BusStop - Lane Closure
-
13th of April 2026, 8:30pm17th of April 2026, 6:00amM80 SB Jct 9 to M876 Merge - Road Closure
-
13th of April 2026, 8:30pm17th of April 2026, 6:00amM876 - WB - Junction 1 - Road Closure
-
13th of April 2026, 8:30pm17th of April 2026, 6:00amM80 - WB - Stirling Services - On-slip Closure
-
2nd of June 2026, 7:00am30th of September 2026, 7:00pmA835 Strathgarve Forest West of Garve WB - TTL
-
2nd of June 2026, 7:00am30th of September 2026, 7:00pmA835 Strathgarve Forest West of Garve EB - TTL
Local roadworks
The Traffic Scotland Service does not cover local roads. These are managed and maintained by local authorities.
Visit The Road Works Scotland website for information on local roads. The website provides information on all programmed and emergency works carried out by utility companies, construction companies, and the local authority on local roads.