Planned Works on M8 Junctions 16 to 17 (Woodside Viaduct)
Works run from 12 March 2021 to early 2026.
Planned roadworks have been implemented on the M8 Junctions 16 to 17 in Glasgow to undertake maintenance to the Woodside Viaduct structure.
Restrictions and road closures
To ensure the safety of roadworks and the travelling public, there are speed and lane restrictions on the M8 in this area. There are closures of the slip roads eastbound at Junction 18 (Charing X), Junction 17 (Great Western Road) and westbound at Junction 15 on Slip (Townhead) and Junction 17 Off Slip (West Graham Street). Signed routes are in operation.
Lane closures are in place to reduce the load on the structures. There are also some narrow lanes which are less suitable for HGVs on the M8 between junctions 16 and 17. To assist with this, we ask that HGVs consider using an alternative route.
Plan ahead and consider alternative routes
The traffic management and diversions have been planned in consultation with Transport Scotland, Traffic Scotland, Glasgow City Council and the emergency services. Road users should plan their journey accordingly and allow extra time for travel or consider an alternative route.
A structural assessment of both the eastbound and westbound areas of the Viaduct in early March 2021 recommended action to be taken immediately. Find more information and updates on Amey's website.
Diversion routes are shown in the maps below. Additional information about the roadworks and traffic management are outlined in our FAQ below.
Visit our homepage and use the map and its route checker to view any live and future disruptions that may impact your journey.
M8 Woodside Viaduct - Diversion Routes
Woodside FAQs
What works are about to be undertaken on this section of the M8?
- Ahead of planned refurbishment work, inspections and intrusive investigations into the condition of the supports of each viaduct (crossheads) were undertaken in late 2020 and 2021 to help determine the extent of works. These investigations found that the condition of the concrete viaducts’ crossheads were in a much worse condition than anticipated. Temporary traffic management, lane closures and slip road restrictions, were installed on the motorway in March 2021 to reduce the traffic load on the viaducts.
- The work involves propping the viaducts to take load off the existing supports. Propping requires excavation to foundation level, avoidance or re-positioning of many services and installation of specially manufactured steel supports with jacks to remove load from the supports. In one location, due to services which can’t be moved, propping from foundation level is not possible and the deck is being propped via steel collars around the columns. At four locations around the SPT underground tunnels, which pass under the western end of the viaducts, special structures will be constructed to allow the deck to be propped and the load to be transferred to areas such that it doesn’t affect the tunnels.
- The first stage of the construction programme involving excavations, piling and other ground works around the existing viaduct columns commenced in August 2021. The installation of the props at the first location followed in February 2022. There are 23 locations that require propping.
What traffic management and restrictions are currently in place?
To ensure the safety of road workers and the travelling public, speed and lane restrictions are in place on the M8 for the full length of both viaducts; the eastbound on-slip at Junction 17, westbound on-slip at Junction 15 and nearside off-slip at Junction 17 are closed. The slip road at Junction 16 remains open. Signed diversion routes are in operation.
Narrowed lanes have been introduced on the main carriageway of the M8 over the viaducts. HGVs are being encouraged to consider using an alternative route via the M74 where possible due to these narrow sections.
On the local road network, below the viaducts, the A804 Phoenix Road is closed. An alternative alignment of M8 junction 17 westbound on-slip has been created to allow Westbound traffic to access the M8 via West Graham Street.
There is currently no access to New City Road via Phoenix Road. A signed diversion is in place via Scott Street and Shamrock Street to New City Road. These restrictions are required to allow for essential excavation works to take place safely under the viaducts.
How long is disruption on the M8 structure likely to continue?
The traffic management on the M8 will be removed once all the required propping works have been completed.
The temporary propping works aim to minimise disruption as far as possible whilst keeping this stretch of the motorway open to the 150,000 vehicles that use it on a daily basis.
Do you have an estimate of when the temporary propping works will be completed?
The temporary propping work is expected to be fully completed in early 2026. However, Amey is working towards delivering the eastbound carriageway sooner, in Summer 2025.
Amey will continue to explore opportunities to bring work forward where possible. These dates are subject to change due to unforeseen circumstances such as adverse weather or unexpected service diversions.
Why have the dates for completion of the propping changed since the beginning of the work?
The work to undertake the temporary propping is extremely complex. Each of the 23 supports requires individual propping designs to take account of the varying column heights, span length and widths resulting in different loads to be supported by the props. The propping foundations at some locations are affected by a number of buried services and the SPT Subway tunnels beneath the viaducts, which has a major impact on the solutions available. The extent of the work required on each support is unknown until work gets underway.
Do you have an estimate of when the repair will be completed?
Completion of the installation of the temporary propping is expected in early 2026, subject to any unforeseen events such as adverse weather or unexpected service diversions. However, the contractor is working towards delivering the eastbound carriageway sooner, in Summer 2025.
Transport Scotland is currently progressing a procurement competition to appoint technical advisors to develop the permanent works solution. Further information will be available in due course.
How much will the repair cost?
The cost of the temporary propping works is expected to be between £126m - £152m.
Work is ongoing to develop a procurement strategy for the permanent works. A cost estimate will be developed to inform the procurement process to appoint a Contractor. The cost will be refined once the construction contract has been awarded.
Will changes to the construction programme influence the final cost of the repair scheme?
With the design progressing and detailed information being gathered to inform the construction of the permanent repair, the associated costs for propping and repairs will continue to be subject to change. Elements, such as the price of materials, will fluctuate due to external factors and changes in the market, which also influence overall costs.
What traffic delays can be expected on the motorway network while this work is taking place?
During the morning (8:55am - 9:05am) and evening (4:55pm – 5:05pm) peak travel periods, eastbound delays of 6 to 10 minutes are common due to traffic volumes. Out with peak times, delays are generally 2 to 5 minutes.
During the morning (8:55am – 9:05am) and evening (4:55pm – 5:05pm) peak travel periods, westbound delays of 6 to 10 minutes are common due to traffic volumes. Out with peak times, delays are generally 2 to 5 minutes.
Will the footpaths beneath the M8 Woodside at Phoenix Road and New City Road remain open?
To ensure the safety of pedestrians and cyclists some footpaths may be subject to localised closures with temporary diversions provided. These diversions will be well signposted, with lighting provided on all diversion routes. Every effort will be made to ensure through routes for active travel are maintained during the project. However, cyclists are requested to observe ‘dismount’ signage where appropriate.
What work has been undertaken to date?
You can visit Amey’s website for more information or updates on the progress of the project.
Why are there periods of time when it appears no one is working at this location?
The majority of construction work on the project takes place underneath the M8 carriageways which aren’t visible from the M8.
How do I contact Amey if I have a complaint, a query or spot an issue on the network related to this work?
Please visit the Amey Southwest trunk road network website to report a problem on the network.
How can I get more information and further updates about this project?
You can visit Amey's website for more information or updates on this project. A free Road Work Alerts service is available from the Amey website, an email address is all that is required to sign up for the service.