M8 Eastbound Near Livingston | Resurfacing Works

M8 Livingston
23rd of September 2025, 8:30pm to 18th of October 2025, 6:00am

BEAR Scotland, Transport Scotland’s operating company, will be conducting major resurfacing works on the M8 Eastbound at Junction 3 from Tuesday 23 September until Friday 17 October.

The works will be completed across two phases, with details as follows:

M8 Livingston Schedule Of Works

Access for emergency vehicles will be maintained at all times.

Tommy Deans, BEAR Scotland’s South East Network Manager, said:

“This section of the M8 eastbound is nearing the end of its serviceable life and it is essential that we replace the road surface before it deteriorates. We’ve scheduled the works at night to minimise disruption, however we appreciate that this will cause delays for some people and thank the public in advance for their patience and understanding.”

Consultation has been carried out with emergency services and other relevant stakeholders to share information about the project in advance.

All works are weather dependent and subject to postponement in the event of adverse conditions.

How to get the latest travel and traffic information

For full information on roadworks on trunk roads in the north-west and south-east of Scotland, visit the Bear Scotland website.

You can report a defect on the network by filling out this form.

Follow Bear Scotland on X at @bear_scotland and at @SETrunkRoads.