A9 Southbound Near Dunblane | Surfacing Improvements
Amey is undertaking surfacing improvements on the A9 southbound between Allan Water and Stockbridge from Tuesday 4th August to Tuesday 18th August.
The £324,000 project, which Amey is undertaking on behalf of Transport Scotland, will resurface approximately 1,120 metres of the southbound carriageway, beginning 1.1km before the A820 off-slip to Dunblane.
To ensure the safety of roadworkers and motorists, the work will take place under a rolling programme of traffic management, including lane restrictions and overnight convoy. Details are as follows:
Tuesday 4th August
Overnight lane one restriction with 50mph speed restriction between 7.30pm and 6.30am.
Wednesday 5th August to Tuesday 18th August
Overnight convoy between 7.30pm and 6.30am.
Please note that there will be no works on the 7th, 8th, 14th, 15th and 16th of August.
Thursday 6th August
Lane one restriction with 50mph speed restriction between 6.30am and 7.30pm, this will allow the material to cool.
The resurfacing will benefit more than 15,000 road users who use this route each day, creating a smoother ride for motorists and reducing the need for ongoing maintenance.
All schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.
How to get the latest travel and traffic information
For full information on roadworks on trunk roads in the south-west of Scotland, visit the Amey website.
You can report a defect on the network by filling out this form.
Follow Amey South West Trunk Roads on X at @SWTrunkRoads.