A9 Southbound Blueton Farm And Northbound At Greenloaning | Overnight Surfacing Improvements
Amey is undertaking overnight surfacing improvements on the A9 southbound between east of Blueton Farm and Williamsfield Farm from Thursday 11th June to Friday 19th June. Further works will take place on the northbound carriageway between north of Greenloaning and Williamsfield Farm from Thursday 18th June to Friday 26th June.
Pre‑works will take place in advance of the main programme on Tuesday 9th and Wednesday 10th June under overnight lane restrictions between 7.30pm and 6.30am.
The £350,000 project, which Amey is undertaking on behalf of Transport Scotland, will resurface approximately 2,300 metres of the carriageways.
To ensure the safety of roadworkers and motorists, the works will be carried out under overnight convoy between 7.30pm and 6.30am. To minimise disruption, there will be no convoy works on Friday or Saturday evenings.
Please be aware that there may be delays of up to 8 minutes when the overnight convoy is in place.
The resurfacing will benefit more than 23,000 road users who use these routes each day, creating a smoother ride for motorists and reducing the need for ongoing maintenance.
All schemes are weather dependent and may be cancelled or rescheduled if weather conditions are not favourable.
How to get the latest travel and traffic information
For full information on roadworks on trunk roads in the north-east of Scotland, visit the Amey website.
You can report a defect on the network by filling out this form.
Follow Amey North East Trunk Roads on X at @NETrunkRoads.