A82 at Fort William | Resurfacing Works

A82 at Fort William
10th of May 2026, 8:00pm to 30th of June 2026, 6:00am

UPDATE (01/06/2026): Due to unsuitable weather conditions, overnight resurfacing on the A82 in Fort William could not go ahead last night. Please see new dates below.

Phase 1: A82 Belford Hospital to Nevis Roundabout – Sunday 10 May to morning of Tuesday 2 June
Phase 2: Gleamer Garage to North Road Retail Park – Monday 8 June to the morning of Friday 19 June
Phase 3: A82 Fort William Duals Northbound (West end  to Transport Roundabouts) – Sunday 21 June to the morning of Tuesday 30 June
 

UPDATE (26/05/2026): Due to additional works required, overnight resurfacing on the A82 between Belford Road and Fort William duals will now be completed by the morning of Monday 29 June.

Phase 1: A82 Belford Hospital to Nevis Roundabout – Sunday 10 May to morning of Monday 1 June

Phase 2: Gleamer Garage to North Road Retail Park – Monday 1 June, then Monday 8 June to the morning of Thursday 18 June

Phase 3: A82 Fort William Duals Northbound (West end  to Transport Roundabouts) – Thursday 18 June to the morning of Monday 29 June

BEAR Scotland, on behalf of Transport Scotland, will undertake a programme of  overnight resurfacing works on the A82 at three locations in Fort William, beginning on Sunday 10 May.

The works are required to address defects within the existing carriageway and will help ensure the long term durability, resilience, and safety of this key section of the trunk road network.

The resurfacing will be delivered in three phases and carried out overnight between 8:00pm and 6:00am. To protect both the workforce and road users, a convoy traffic management system will be in operation, with vehicles escorted safely through the works at approximately 10mph.

To minimise disruption, no works will take place on Friday or Saturday nights, nor during the period Monday 18 May to Wednesday 20 May inclusive. Temporary traffic management will be removed outwith working hours, and the road will be fully reopened during the day:

Phase 1: A82 Belford Hospital to Nevis Roundabout – Sunday 10 May to Wednesday 27 May
Phase 2: Gleamer Garage to North Road Retail Park – Wednesday 27 May to Tuesday 9 June
Phase 3: A82 Fort William Duals Northbound (West end  to Transport Roundabouts) – Tuesday 9 June to Monday 22 June

Steve Taylor, BEAR Scotland’s North West Design Manager, said “These essential resurfacing works will provide a significant upgrade to the existing road surface and allow for the installation of new road markings, improving both the quality and safety of the A82 through Fort William.  

“We would like to thank road users, residents and local businesses for their patience while these important improvements are carried out.”

How to get the latest travel and traffic information

For full information on roadworks on trunk roads in the north-west and south-east of Scotland, visit the Bear Scotland website.

You can report a defect on the network by filling out this form.