Roadwork details
Location
A8 W/B East Hamilton St - Lane closures
Direction
Westbound
Starting
26th of June 2023, 9:30am
Ending
14th of December 2023, 4:00pm
Days & times affected
Week commencing 2nd Oct
All Day
Monday, Tuesday, Wednesday, Thursday, Friday, Saturday, Sunday.
Week commencing 9th Oct
Early Morning (00:00 - 06:00)
Thursday.
Late Morning (06:00 - 12:00)
Thursday.
Afternoon (12:00 - 18:00)
Thursday.
Evening (18:00 - 00:00)
Thursday.
All Day
Monday, Tuesday, Wednesday, Friday, Saturday, Sunday.
Roadwork description
Works:
Utility Works
Phase 1 – Lane 1 E/B with push to Lane 2 closure + Lane 2 closure W/B. (3 weeks, 26/06-14/07).
Phase 2 – Lane 2 closure W/B + Lane 1 closure E/B then into a contraflow. (13 weeks 14/07 – 12/10).
Phase 3 – Same as Phase 1. (1.5 weeks 12/10-23/10)
Phase 4 – Lane 1 closure W/B, Lane 1 closure E/B with push to lane 2 closure then into a Contraflow (7 weeks 23/10-14/12)
Utility Works
Phase 1 – Lane 1 E/B with push to Lane 2 closure + Lane 2 closure W/B. (3 weeks, 26/06-14/07).
Phase 2 – Lane 2 closure W/B + Lane 1 closure E/B then into a contraflow. (13 weeks 14/07 – 12/10).
Phase 3 – Same as Phase 1. (1.5 weeks 12/10-23/10)
Phase 4 – Lane 1 closure W/B, Lane 1 closure E/B with push to lane 2 closure then into a Contraflow (7 weeks 23/10-14/12)