Planned Roadwork details
Location
M80 SB J2 off slip - Slip Closure
Direction
Southbound
Starting
9th of September 2026, 8:00pm
Ending
10th of September 2026, 6:00am
Days & times affected
Week commencing 7th Sep
Early Morning (00:00 - 06:00)
Thursday.
Evening (18:00 - 00:00)
Wednesday.
Roadwork description
Works:
Grass Cutting
Traffic Management:
Road Closure.
Diversion Information:
continue M80 SB - leave M80 J1 - Rbt take 2nd exit - at Jct turn right onto Provan Rd - at mini Bbt take 2nd exit onto M80 NB J1 on slip - leave M80 NB J2 - end
Grass Cutting
Traffic Management:
Road Closure.
Diversion Information:
continue M80 SB - leave M80 J1 - Rbt take 2nd exit - at Jct turn right onto Provan Rd - at mini Bbt take 2nd exit onto M80 NB J1 on slip - leave M80 NB J2 - end