Planned Roadwork details
Location
A83 Dunderave North of Inveraray NB - Road Closure
Direction
Northbound
Starting
3rd of December 2024, 7:00pm
Ending
6th of December 2024, 7:00am
Days & times affected
Week commencing 2nd Dec
Early Morning (00:00 - 06:00)
Wednesday, Thursday, Friday.
Late Morning (06:00 - 12:00)
Wednesday, Thursday, Friday.
Evening (18:00 - 00:00)
Tuesday, Wednesday, Thursday.
Activity PeriodsExpand
- Tue 3rd Dec - 19:00 to 23:59
- Wed 4th Dec - 00:00 to 07:00
- Wed 4th Dec - 19:00 to 23:59
- Thu 5th Dec - 00:00 to 07:00
- Thu 5th Dec - 19:00 to 23:59
- Fri 6th Dec - 00:00 to 07:00
Roadwork description
Works:
Resurfacing
Traffic Management:
Road Closure.
Diversion Information:
via A82, A85 & A819
Resurfacing
Traffic Management:
Road Closure.
Diversion Information:
via A82, A85 & A819